Fire-Stop Marketing v Mae Engineering: Construction Contract Dispute over Fire-Rated Board Cladding Payment

In Fire-Stop Marketing Services Pte Ltd v Mae Engineering Ltd, the High Court of Singapore, on 31 May 2004, addressed a dispute over the construction of a sub-contract for the installation of fire-rated board claddings. Fire-Stop Marketing Services Pte Ltd (Plaintiff) sued Mae Engineering Ltd (Defendant) to determine whether payment should be based on the area of the cladded or uncladded ACMV duct. The court ruled in favor of the Plaintiff, determining that payment should be based on the area of the cladded ACMV duct. The defendant's counterclaim was dismissed.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Judgment for Plaintiff

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Dispute over payment for fire-rated board cladding installation. The court ruled payment should be based on the area of the cladded ACMV duct.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Fire-Stop Marketing Services Pte LtdPlaintiffCorporationClaim allowed with costsWonJohn Chung
Mae Engineering LtdDefendantCorporationCounterclaim dismissed with costsLostKaram S Parmar, Dawn Chew

3. Judges

Judge NameTitleDelivered Judgment
Lai Kew ChaiJudgeYes

4. Counsels

Counsel NameOrganization
John ChungKelvin Chia Partnership
Karam S ParmarTan Kok Quan Partnership
Dawn ChewTan Kok Quan Partnership

4. Facts

  1. Fire-Stop Marketing Services was contracted to supply and install fire-rated board claddings.
  2. Mae Engineering was the ACMV sub-contractor for The Esplanade project.
  3. The sub-contract price was initially a lump sum of $400,000 for 5000m² of ACMV ductwork.
  4. Agreed rates for variations beyond 5000m² were $80 per m² for 2-hour and $165 per m² for 4-hour fire-rated cladding.
  5. The sub-contract was silent on the mode of measurement of work done.
  6. The value of the cladded ACMV, for materials supplied and work done, was $1,028,576.22.
  7. The value of the cladded ACMV duct area was agreed at $529,610.00.

5. Formal Citations

  1. Fire-Stop Marketing Services Pte Ltd v Mae Engineering Ltd, Suit 287/2003, [2004] SGHC 116

6. Timeline

DateEvent
Sub-contract agreement signed
Work progressed
Work progressed
Judgment reserved

7. Legal Issues

  1. Construction of Contract Terms
    • Outcome: The court determined that payment should be based on the area of the cladded ACMV duct.
    • Category: Substantive

8. Remedies Sought

  1. Monetary Damages

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Construction Law
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
No cited cases

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
No applicable statutes

15. Key Terms and Keywords

15.1 Key Terms

  • Fire-rated board cladding
  • ACMV ductwork
  • Lump sum
  • Sub-contract
  • Cladded ACMV duct
  • Uncladded ACMV duct
  • Progress payments

15.2 Keywords

  • Fire-Stop Marketing
  • Mae Engineering
  • Construction contract
  • Fire-rated cladding
  • Payment dispute
  • Singapore High Court

16. Subjects

  • Construction Dispute
  • Contract Law

17. Areas of Law

  • Building and Construction Law
  • Contract Law