Luzon Hydro v Transfield: Setting Aside Arbitral Award for Alleged Breach of Natural Justice

Luzon Hydro Corporation sought to set aside an arbitral award against Transfield Philippines Inc. The High Court of Singapore, presided over by Judith Prakash J, dismissed the motion, finding no grounds to support the claim that the arbitral procedure was not in accordance with the parties' agreement or that a breach of the rules of natural justice had occurred. The dispute arose from a contract for the construction of a power station, with Luzon claiming liquidated damages and Transfield claiming extensions of time and outstanding payments. Luzon's application was based on concerns about the role of an expert appointed by the arbitral tribunal.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Motion dismissed with costs.

1.3 Case Type

Arbitration

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Luzon Hydro's application to set aside an arbitral award was dismissed, as no breach of natural justice or procedural irregularity was found.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Luzon Hydro CorpApplicantCorporationMotion dismissed with costsLostWong Meng Meng, Anthony Soh, Carrie Gill
Transfield Philippines IncRespondentCorporationMotion dismissedWonGiam Chin Toon, Hui Choon Wai

3. Judges

Judge NameTitleDelivered Judgment
Judith PrakashJudgeYes

4. Counsels

Counsel NameOrganization
Wong Meng MengWong Partnership
Anthony SohColin Ng and Partners
Carrie GillColin Ng and Partners
Giam Chin ToonWee Swee Teow and Co
Hui Choon WaiWee Swee Teow and Co

4. Facts

  1. Luzon and Transfield entered into a contract for the construction of a power station.
  2. Disputes arose between the parties regarding extensions of time and payments.
  3. The parties agreed to arbitration in Singapore under ICC rules.
  4. An arbitral tribunal was formed, and an expert was engaged to assist the tribunal.
  5. Luzon sought to set aside the arbitral award, alleging procedural irregularities and breach of natural justice.
  6. Luzon argued that the expert had overstepped his role and that the tribunal had relied on his advice without giving the parties an opportunity to comment.

5. Formal Citations

  1. Luzon Hydro Corp v Transfield Philippines Inc, OM 27/2004, [2004] SGHC 204

6. Timeline

DateEvent
Luzon employed Transfield to design, construct, commission, test, complete and hand over the power station.
Disputes arose between the parties.
Transfield served a request for arbitration to the Secretariat of the International Court of Arbitration.
The arbitral tribunal ordered that the arbitration proceedings be divided into three parts.
The parties agreed that the first liability hearing should take place in Melbourne rather than Singapore.
The parties and the arbitral tribunal agreed to engage Mr Rohan D Shorland as an expert to assist the arbitral tribunal.
First hearing on liability conducted in Melbourne.
First hearing on liability conducted in Melbourne.
Mr Shorland rendered invoices on a monthly basis for work done during the period between May 2003 and December 2003.
Mr Shorland rendered invoices on a monthly basis for work done during the period between May 2003 and December 2003.
The chairman of the tribunal wrote to the parties and informed them that the tribunal had found it unnecessary to seek any written opinion from Mr Shorland.
Third Partial Award was issued.
Motion to set aside the Third Partial Award was dismissed with costs.

7. Legal Issues

  1. Setting aside arbitral award
    • Outcome: The court found no grounds to set aside the arbitral award.
    • Category: Procedural
    • Sub-Issues:
      • Breach of natural justice
      • Arbitral procedure not in accordance with parties' agreement
  2. Breach of natural justice
    • Outcome: The court found no breach of the rules of natural justice.
    • Category: Substantive
  3. Arbitral procedure
    • Outcome: The court found that the arbitral procedure was in accordance with the agreement of the parties.
    • Category: Procedural

8. Remedies Sought

  1. Setting aside of arbitral award

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Arbitration

11. Industries

  • Construction
  • Energy

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Luzon Hydro Corp v Transfield Philippines IncHigh CourtYes[2004] SGHC 204SingaporeThis is the current case.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
International Arbitration Act (Cap 143A, 2002 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Arbitration
  • Arbitral award
  • Setting aside
  • Natural justice
  • International Arbitration Act
  • ICC Rules
  • Expert
  • Arbitral tribunal
  • Extension of time
  • Power station

15.2 Keywords

  • Arbitration
  • Setting aside
  • Natural justice
  • Construction
  • Singapore

16. Subjects

  • Arbitration
  • Construction Law

17. Areas of Law

  • Arbitration Law
  • International Arbitration