Multiplex Constructions v Sintal: Stay of Proceedings & Arbitration for Delay Damages
In a dispute between Multiplex Constructions Pty Ltd and Sintal Enterprise Pte Ltd, the Court of Appeal of Singapore heard an appeal regarding the stay of court proceedings in favor of arbitration. Multiplex sought a stay of Sintal's High Court claim for sums due under two sub-contracts, arguing that disputes existed regarding delay damages and the validity of set-off notices. The court allowed the appeal in part, granting a stay for claims related to interim certificates 28, 29, and 30, but denying a stay for interim certificate 27.
1. Case Overview
1.1 Court
Court of Appeal of the Republic of Singapore1.2 Outcome
Appeal Allowed in Part
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Appeal regarding stay of court proceedings in favor of arbitration. Court of Appeal addressed disputes over delay damages and set-off notices.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Multiplex Constructions Pty Ltd | Appellant | Corporation | Appeal allowed in part | Partial | Vinodh S Coomaraswamy, Pradeep Pillai |
Sintal Enterprise Pte Ltd | Respondent | Corporation | Appeal partially dismissed | Partial | Andre Maniam, Paul Sandosham |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Chao Hick Tin | Justice of Appeal | Yes |
Judith Prakash | Judge | No |
4. Counsels
Counsel Name | Organization |
---|---|
Vinodh S Coomaraswamy | Shook Lin and Bok |
Pradeep Pillai | Shook Lin and Bok |
Andre Maniam | Wong Partnership |
Paul Sandosham | Wong Partnership |
4. Facts
- Multiplex was employed to build a housing development at Haig Road.
- Multiplex entered into two sub-contracts with Sintal for stonework.
- Sintal sued Multiplex for sums due under both sub-contracts.
- Multiplex applied for a stay of proceedings based on arbitration clauses.
- Multiplex sought to set off losses against certified sums due to Sintal.
- Multiplex issued four set-off notices against Sintal’s claim for the certified sums.
- The architect issued interim certificates nos 27, 28, 29 and 30 for a total amount of $485,268.55 in respect of marble supplied by Sintal.
5. Formal Citations
- Multiplex Constructions Pty Ltd v Sintal Enterprise Pte Ltd, CA 61/2004, [2005] SGCA 10
6. Timeline
Date | Event |
---|---|
Multiplex employed by Great Eastern Life Assurance Company Ltd to build a housing development at Haig Road | |
Letter of acceptance signed by both parties | |
Original completion date for the main contract | |
Architect issued interim certificate number 27 | |
Architect issued interim certificate number 28 | |
Architect issued interim certificate number 29 | |
Architect issued interim certificate number 30 | |
Sintal sued Multiplex in the High Court | |
Justice Lai Siu Chiu dismissed Multiplex's appeal | |
Judgment reserved |
7. Legal Issues
- Stay of Court Proceedings
- Outcome: The court allowed a partial stay of proceedings in favor of arbitration.
- Category: Procedural
- General Damages for Delay
- Outcome: The court found that there was a dispute regarding the interpretation of the damages provisions of the sub-contract that must go to arbitration.
- Category: Substantive
- Validity of Set-Off Notices
- Outcome: The court found that apart from the first set-off notice, the set-off notices complied with clause 11.5(i) and that there were disputes which should be referred to arbitration.
- Category: Substantive
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Commercial Litigation
- Arbitration
- Construction Law
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Kwan Im Tong Chinese Temple v Fong Choon Hung Construction Pte Ltd | Court of Appeal | Yes | [1998] 2 SLR 137 | Singapore | Cited for the holistic and common-sense approach towards determining the existence of a dispute in arbitration cases. |
Tradax Internacional SA v Cerrahogullari TAS (The M Eregli) | N/A | Yes | [1981] 2 Lloyd’s Rep 169 | N/A | Cited for the principle that the court has jurisdiction to hear a matter instead of referring it to arbitration if the claim is indisputable. |
Uni-Navigation Pte Ltd v Wei Loong Shipping Pte Ltd | N/A | Yes | [1993] 1 SLR 876 | Singapore | Cited for the observation that courts should adopt a holistic and commonsense approach to see if there is a dispute in arbitration agreements. |
Home and Overseas Insurance Co Ltd v Mentor Insurance Co (UK) Ltd | N/A | Yes | [1990] 1 WLR 153 | United Kingdom | Cited for the principle that full-scale argument should not be permitted in a situation where there is an arbitration clause, except in a very clear case. |
JDC Corporation v Lightweight Concrete Pte Ltd | Court of Appeal | Yes | [1999] 1 SLR 615 | Singapore | Cited regarding the issue of the type of damages claimable by a contractor from his sub-contractor under the provisions of a construction contract. |
Homburg Houtimport BV v Agrosin Private Ltd | House of Lords | Yes | [2004] 1 AC 715 | United Kingdom | Cited for the principle that greater weight should attach to terms which the contracting parties had chosen to include in the contract than to pre-printed conditions. |
Archital Luxfer Limited v AJ Dunning and Sons (Weyhill) Limited | English Court of Appeal | Yes | (1989) 5 Const LJ 47 | England and Wales | Cited regarding a similarly-worded procedural requirement which had to be satisfied before a set-off could be exercised. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Arbitration Act (Cap 10, 2002 Rev Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Arbitration
- Stay of Proceedings
- Set-Off
- Liquidated Damages
- General Damages
- Sub-Contract
- Interim Certificate
- Delay Damages
- Conditions of Sub-Contract
15.2 Keywords
- Arbitration
- Construction
- Singapore
- Contract
- Stay of Proceedings
- Damages
- Set-off
16. Subjects
- Construction Dispute
- Arbitration
- Contract Law
17. Areas of Law
- Arbitration Law
- Contract Law
- Construction Law
- Civil Procedure