Multiplex Constructions v Sintal: Stay of Proceedings & Arbitration for Delay Damages

In a dispute between Multiplex Constructions Pty Ltd and Sintal Enterprise Pte Ltd, the Court of Appeal of Singapore heard an appeal regarding the stay of court proceedings in favor of arbitration. Multiplex sought a stay of Sintal's High Court claim for sums due under two sub-contracts, arguing that disputes existed regarding delay damages and the validity of set-off notices. The court allowed the appeal in part, granting a stay for claims related to interim certificates 28, 29, and 30, but denying a stay for interim certificate 27.

1. Case Overview

1.1 Court

Court of Appeal of the Republic of Singapore

1.2 Outcome

Appeal Allowed in Part

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Appeal regarding stay of court proceedings in favor of arbitration. Court of Appeal addressed disputes over delay damages and set-off notices.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Multiplex Constructions Pty LtdAppellantCorporationAppeal allowed in partPartialVinodh S Coomaraswamy, Pradeep Pillai
Sintal Enterprise Pte LtdRespondentCorporationAppeal partially dismissedPartialAndre Maniam, Paul Sandosham

3. Judges

Judge NameTitleDelivered Judgment
Chao Hick TinJustice of AppealYes
Judith PrakashJudgeNo

4. Counsels

Counsel NameOrganization
Vinodh S CoomaraswamyShook Lin and Bok
Pradeep PillaiShook Lin and Bok
Andre ManiamWong Partnership
Paul SandoshamWong Partnership

4. Facts

  1. Multiplex was employed to build a housing development at Haig Road.
  2. Multiplex entered into two sub-contracts with Sintal for stonework.
  3. Sintal sued Multiplex for sums due under both sub-contracts.
  4. Multiplex applied for a stay of proceedings based on arbitration clauses.
  5. Multiplex sought to set off losses against certified sums due to Sintal.
  6. Multiplex issued four set-off notices against Sintal’s claim for the certified sums.
  7. The architect issued interim certificates nos 27, 28, 29 and 30 for a total amount of $485,268.55 in respect of marble supplied by Sintal.

5. Formal Citations

  1. Multiplex Constructions Pty Ltd v Sintal Enterprise Pte Ltd, CA 61/2004, [2005] SGCA 10

6. Timeline

DateEvent
Multiplex employed by Great Eastern Life Assurance Company Ltd to build a housing development at Haig Road
Letter of acceptance signed by both parties
Original completion date for the main contract
Architect issued interim certificate number 27
Architect issued interim certificate number 28
Architect issued interim certificate number 29
Architect issued interim certificate number 30
Sintal sued Multiplex in the High Court
Justice Lai Siu Chiu dismissed Multiplex's appeal
Judgment reserved

7. Legal Issues

  1. Stay of Court Proceedings
    • Outcome: The court allowed a partial stay of proceedings in favor of arbitration.
    • Category: Procedural
  2. General Damages for Delay
    • Outcome: The court found that there was a dispute regarding the interpretation of the damages provisions of the sub-contract that must go to arbitration.
    • Category: Substantive
  3. Validity of Set-Off Notices
    • Outcome: The court found that apart from the first set-off notice, the set-off notices complied with clause 11.5(i) and that there were disputes which should be referred to arbitration.
    • Category: Substantive

8. Remedies Sought

  1. Monetary Damages

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Commercial Litigation
  • Arbitration
  • Construction Law

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Kwan Im Tong Chinese Temple v Fong Choon Hung Construction Pte LtdCourt of AppealYes[1998] 2 SLR 137SingaporeCited for the holistic and common-sense approach towards determining the existence of a dispute in arbitration cases.
Tradax Internacional SA v Cerrahogullari TAS (The M Eregli)N/AYes[1981] 2 Lloyd’s Rep 169N/ACited for the principle that the court has jurisdiction to hear a matter instead of referring it to arbitration if the claim is indisputable.
Uni-Navigation Pte Ltd v Wei Loong Shipping Pte LtdN/AYes[1993] 1 SLR 876SingaporeCited for the observation that courts should adopt a holistic and commonsense approach to see if there is a dispute in arbitration agreements.
Home and Overseas Insurance Co Ltd v Mentor Insurance Co (UK) LtdN/AYes[1990] 1 WLR 153United KingdomCited for the principle that full-scale argument should not be permitted in a situation where there is an arbitration clause, except in a very clear case.
JDC Corporation v Lightweight Concrete Pte LtdCourt of AppealYes[1999] 1 SLR 615SingaporeCited regarding the issue of the type of damages claimable by a contractor from his sub-contractor under the provisions of a construction contract.
Homburg Houtimport BV v Agrosin Private LtdHouse of LordsYes[2004] 1 AC 715United KingdomCited for the principle that greater weight should attach to terms which the contracting parties had chosen to include in the contract than to pre-printed conditions.
Archital Luxfer Limited v AJ Dunning and Sons (Weyhill) LimitedEnglish Court of AppealYes(1989) 5 Const LJ 47England and WalesCited regarding a similarly-worded procedural requirement which had to be satisfied before a set-off could be exercised.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Arbitration Act (Cap 10, 2002 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Arbitration
  • Stay of Proceedings
  • Set-Off
  • Liquidated Damages
  • General Damages
  • Sub-Contract
  • Interim Certificate
  • Delay Damages
  • Conditions of Sub-Contract

15.2 Keywords

  • Arbitration
  • Construction
  • Singapore
  • Contract
  • Stay of Proceedings
  • Damages
  • Set-off

16. Subjects

  • Construction Dispute
  • Arbitration
  • Contract Law

17. Areas of Law

  • Arbitration Law
  • Contract Law
  • Construction Law
  • Civil Procedure