Yee Hong v Powen: Arbitrator Removal for Improper Conduct in Construction Arbitration
In Yee Hong Pte Ltd v Powen Electrical Engineering Pte Ltd, the High Court of Singapore dismissed Yee Hong's application to remove an arbitrator, Lim Kheng Chye, in an arbitration proceeding initiated by Powen against Yee Hong, the main contractor for a condominium project. Yee Hong alleged that the arbitrator failed to properly conduct the arbitration by proceeding with a hearing despite Yee Hong's request for further discovery and extension of time to exchange affidavits. The court, presided over by Belinda Ang Saw Ean J, found no evidence of substantial injustice caused to Yee Hong and dismissed the application with costs.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Application dismissed with costs.
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Yee Hong's application to remove an arbitrator for improper conduct was dismissed. The court found no substantial injustice caused by the arbitrator's actions.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Powen Electrical Engineering Pte Ltd | Respondent | Corporation | Application Dismissed | Won | |
Yee Hong Pte Ltd | Applicant | Corporation | Application Dismissed | Lost |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Belinda Ang Saw Ean | Judge | Yes |
4. Counsels
4. Facts
- Yee Hong was the main contractor for a condominium project.
- Powen was the electrical installation sub-contractor.
- Arbitration proceedings commenced on or about 24 June 2003.
- Yee Hong sought further discovery of documents.
- Yee Hong requested an extension of time to exchange affidavits.
- The arbitrator ordered exchange of affidavits by a certain date.
- Yee Hong failed to exchange affidavits by the deadline.
5. Formal Citations
- Yee Hong Pte Ltd v Powen Electrical Engineering Pte Ltd, OM 1/2005, [2005] SGHC 114
6. Timeline
Date | Event |
---|---|
Arbitration proceedings commenced by Powen against Yee Hong | |
Lim Kheng Chye appointed as sole arbitrator | |
Arbitrator proposed preliminary meeting | |
Preliminary meeting held | |
Statement of Claim dated | |
Yee Hong submitted Defence and Counterclaim | |
Arbitrator requested Statement of Reply | |
AsiaLegal submitted Reply and Defence to Counterclaim | |
Arbitrator requested Statement of Reply from Rajah & Tann | |
Suit No 814 of 2003 commenced in the High Court | |
Yee Hong requested six categories of documents | |
Tribunal directions: affidavits of evidence-in-chief to be exchanged on 2004-12-17 | |
Powen provided two categories of documents | |
Rajah & Tann said they would apply for further discovery if they did not hear positively from AsiaLegal by 2004-11-24 | |
AsiaLegal objected to discovery | |
Yee Hong requested Powen to agree to exchange affidavits of evidence-in-chief on 2005-01-07 | |
Yee Hong requested Powen to agree to exchange affidavits of evidence-in-chief on 2005-01-07 | |
Arbitrator informed of the situation | |
Yee Hong informed Powen it was not ready to exchange affidavits | |
Rajah & Tann requested further discovery and better particulars | |
Mr Jeya Putra asked that the hearing of the arbitration proceed as previously directed | |
Urgent meeting convened by the tribunal | |
Arbitrator issued Directions No 1 | |
Mr Jeya Putra informed the arbitrator that documents were sent to Rajah & Tann | |
Rajah & Tann stated documents forwarded were relevant to the claim | |
Arbitrator issued Peremptory Order to Respondents | |
Arbitrator issued Directions No 2 | |
Yee Hong's application for further discovery faxed to arbitrator | |
Originating motion filed by Rajah & Tann on behalf of Yee Hong | |
Parties exchanged affidavits of evidence-in-chief | |
Application came up for hearing before the judge | |
Hearing re-scheduled | |
Hearing re-scheduled | |
Hearing re-scheduled | |
Last day of hearing | |
Decision Date |
7. Legal Issues
- Improper Conduct of Arbitration Proceedings
- Outcome: The court found no improper conduct of arbitration proceedings.
- Category: Procedural
- Sub-Issues:
- Failure to call for hearing of application before making order
- Violation of rules of natural justice
- Excess of Power by Arbitrator
- Outcome: The court found that the arbitrator did not act in excess of power.
- Category: Procedural
- Removal of Arbitrator
- Outcome: The court found no basis for the removal of the arbitrator.
- Category: Procedural
- Sub-Issues:
- Improper conduct
- Loss of confidence in arbitrator
- Substantial injustice
8. Remedies Sought
- Removal of arbitrator
9. Cause of Actions
- Failure to properly conduct the arbitration proceedings
10. Practice Areas
- Arbitration
- Construction Law
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Koh Bros Building & Civil Engineering Construction Pte Ltd v Scotts Development (Saraca) Pte Ltd | High Court | Yes | [2002] 4 SLR 748 | Singapore | Cited as not helpful to the present case. |
Conder Structures v Kvaerner Construction Ltd | N/A | Yes | [1999] ADRLJ 305 | United Kingdom | Cited for the principle that loss of confidence in an arbitrator is neither a sufficient nor a necessary condition of substantial injustice. |
13. Applicable Rules
Rule Name |
---|
Singapore Institute of Architects Arbitration Rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Arbitration Act (Cap 10, 2002 Rev Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Arbitration
- Arbitrator
- Improper conduct
- Discovery
- Affidavits
- Peremptory order
- Substantial injustice
- Singapore Institute of Architects Arbitration Rules
15.2 Keywords
- arbitration
- arbitrator
- removal
- improper conduct
- construction
- singapore
17. Areas of Law
Area Name | Relevance Score |
---|---|
Arbitration | 95 |
Natural justice | 60 |
Civil Procedure | 40 |
Commercial Disputes | 30 |
16. Subjects
- Arbitration
- Construction Dispute
- Civil Procedure