Petrosin Corp v Clough Engineering: Breach of Contract & Oral Agreement Dispute

Petrosin Corp Pte Ltd, a Singaporean company, sued Clough Engineering Ltd, an Australian company, in the High Court of Singapore, alleging breach of an oral agreement made on 18 October 2001, regarding the Sawan Field Project. Petrosin claimed that Clough agreed to award all local works to Petrosin exclusively, without pre-qualification or OMV approval. Tay Yong Kwang J dismissed Petrosin's claim, finding no concluded oral agreement.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Plaintiff's claim dismissed with costs at 75%.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Petrosin Corp sued Clough Engineering for breach of an oral agreement regarding a construction project. The court dismissed Petrosin's claim.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Petrosin Corp Pte LtdPlaintiffCorporationClaim DismissedLostKenneth Tan, Oommen Matthew
Clough Engineering LtdDefendantCorporationJudgment for DefendantWonSteven Chong, Sim Kwan Kiat, Kelvin Poon

3. Judges

Judge NameTitleDelivered Judgment
Tay Yong KwangJudgeYes

4. Counsels

Counsel NameOrganization
Kenneth TanKenneth Tan Partnership
Oommen MatthewHaq and Selvam
Steven ChongRajah and Tann
Sim Kwan KiatRajah and Tann
Kelvin PoonRajah and Tann

4. Facts

  1. Petrosin assisted Clough in securing the Sawan Field Project.
  2. Latif and Roberton negotiated three proposed agreements.
  3. Latif claimed an oral agreement was reached on 18 October 2001.
  4. Roberton took the unsigned MOU back to Perth for review.
  5. Clough sent a revised MOU on 28 October 2001.
  6. Petrosin rejected the revised MOU.
  7. Clough awarded the local works to other parties.

5. Formal Citations

  1. Petrosin Corp Pte Ltd v Clough Engineering Ltd, Suit 229/2004, [2005] SGHC 170

6. Timeline

DateEvent
Petrosin Corp Pte Ltd incorporated.
Negotiations began between Latif and Roberton on three proposed agreements.
Latif met Roberton in Singapore.
Latif sent an e-mail to Roberton regarding in-country work.
Latif sent a draft MOU to Roberton by e-mail.
Latif met the defendant’s officers in Perth.
Latif raised the question of signing the MOU.
Roberton replied to Latif's email.
Latif and Roberton met in Singapore.
Roberton e-mailed to say that he expected to send the signed agreements to Latif the next day.
Roberton telephoned Latif to say that he had problems with his subordinates and further discussions on the MOU were necessary.
Latif sent an e-mail asserting that “we both reached an agreement”.
Roberton replied to say that he had faxed the signed copies of the three agreements to Latif.
Latif met Harold Clough at the Conrad Hotel.
The plaintiff’s Pakistani office received a request for pre-qualification in respect of “camp building” from the defendant.
The plaintiff accepted the defendant’s repudiation.
Further and Better Particulars dated.
Decision Date

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found that there was no concluded oral agreement and therefore no breach of contract.
    • Category: Substantive
    • Sub-Issues:
      • Failure to award subcontract work
      • Introduction of new contract terms
  2. Formation of Contract
    • Outcome: The court found that there was no concluded oral agreement on 18 October 2001.
    • Category: Substantive
    • Sub-Issues:
      • Oral agreement
      • Memorandum of Understanding
  3. Consideration
    • Outcome: The court found that there was valuable consideration moving from the plaintiff to the defendant.
    • Category: Substantive
    • Sub-Issues:
      • Past consideration
      • Sufficiency of consideration
    • Related Cases:
      • [1980] AC 614
  4. Enforceability of Agreement
    • Outcome: The court found that s 6(e) of the Civil Law Act did not apply because performance of the agreement was to begin within one year.
    • Category: Procedural
    • Sub-Issues:
      • Agreement not to be performed within one year
      • Requirement of written agreement

8. Remedies Sought

  1. Loss and damages

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Commercial Litigation
  • Construction Disputes

11. Industries

  • Construction
  • Oil and Gas

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Projection Pte Ltd v The Tai Ping Insurance Co LtdHigh CourtYes[2001] 2 SLR 399SingaporeCited for the objective test to determine whether agreement had been reached between parties.
Pao On v Lau Yiu LongPrivy CouncilYes[1980] AC 614United KingdomCited regarding past consideration and the burden of proving valuable consideration.
SM Integrated Transware Pte Ltd v Schenker Singapore (Pte) LtdHigh CourtYes[2005] 2 SLR 651SingaporeCited regarding whether e-mail correspondence are included in the words “in writing” for the purpose of s 6(d) of the Civil Law Act.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Civil Law Act (Cap 43, 1999 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Memorandum of Understanding
  • Local works agreement
  • Sawan Field Project
  • Pre-qualification
  • OMV approval
  • In-country work
  • Agency agreement
  • Subcontract
  • Right of first refusal

15.2 Keywords

  • contract
  • agreement
  • construction
  • Sawan Field Project
  • MOU
  • breach of contract
  • oral agreement

16. Subjects

  • Contract Law
  • Construction Law
  • Breach of Contract
  • Oral Agreement

17. Areas of Law

  • Contract Law
  • Construction Law