Lim Chin San Contractors v Sanchoon Builders: Breach of Subcontract & Wrongful Termination
In a construction dispute before the High Court of Singapore on 23 December 2005, Lim Chin San Contractors Pte Ltd (LCS Contractors) sued Sanchoon Builders Pte Ltd (Sanchoon) for breach of contract and wrongful termination of a subcontract for marine works. Sanchoon counterclaimed for damages, alleging LCS Contractors repudiated the subcontract. Justice Judith Prakash found that Sanchoon's termination was wrongful, entitling LCS Contractors to judgment for $219,912 and damages to be assessed. The court found LCS Contractors in breach of contract for failing to obtain approvals from specified government authorities, entitling Sanchoon to damages to be assessed. The court awarded 95% of the costs of the claim and the Defence to the Counterclaim to LCS Contractors.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Judgment for Plaintiff
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Construction dispute over marine works. LCS Contractors sued Sanchoon Builders for wrongful termination of a subcontract. Court found Sanchoon's termination wrongful.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Lim Chin San Contractors Pte Ltd | Plaintiff | Corporation | Judgment for Plaintiff | Won | Kelvin Chia |
Sanchoon Builders Pte Ltd | Defendant | Corporation | Damages to be assessed | Partial | Joseph Liow |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Judith Prakash | Judge | Yes |
4. Counsels
Counsel Name | Organization |
---|---|
Kelvin Chia | Balkenende Chew and Chia |
Joseph Liow | Straits Law Practice LLC |
4. Facts
- Sanchoon was the main contractor for the construction of a Police Coast Guard Sub-Base.
- Sanchoon appointed LCS Contractors as its subcontractor for certain bored piling and marine works.
- LCS Contractors' tender was based on the earth bund method, which was cheaper than the barge method.
- CPG Consultants required a method statement for the construction of the bund.
- CPG was not satisfied with the initial method statement submitted by LCS Contractors.
- Sanchoon engaged Prof Tan to assist LCS Contractors in putting up calculations to satisfy CPG.
- Sanchoon terminated the subcontract, alleging LCS Contractors had repudiated the agreement.
5. Formal Citations
- Lim Chin San Contractors Pte Ltd v Sanchoon Builders Pte Ltd, Suit 393/2004, [2005] SGHC 227
6. Timeline
Date | Event |
---|---|
LCS Contractors submitted quotation | |
Meeting held between LCS Contractors, Sanchoon, and CPG Consultants | |
Sanchoon issued letter of intent to LCS Contractors | |
Sanchoon issued Original Marine Works Programme | |
LCS Contractors signed subcontract document | |
Sanchoon issued Revised Marine Works Programme | |
LCS Contractors forwarded method statement to Sanchoon | |
SH Ng sent letter to Sanchoon | |
SH Ng supplied Sanchoon with Slope Analysis of Bund Wall | |
Prof Tan produced analysis indicating bund suitable if sand used | |
LCS Contractors requested particulars of delay | |
CPG sent letter to Sanchoon regarding statutory submissions and approvals | |
LCS Contractors sent letter of demand to Sanchoon | |
Sanchoon produced draft settlement agreement | |
Sanchoon terminated the subcontract | |
Action commenced | |
Judgment reserved |
7. Legal Issues
- Breach of Subcontract
- Outcome: The court found that LCS Contractors breached the subcontract by failing to obtain approvals from specified government authorities, but did not breach the subcontract for failing to follow instructions of consultants or failing to carry out works with reasonable diligence.
- Category: Substantive
- Sub-Issues:
- Failure to follow instructions of consultants
- Failure to carry out works with reasonable diligence
- Wrongful Termination
- Outcome: The court held that Sanchoon's termination of the subcontract was wrongful.
- Category: Substantive
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
- Wrongful Termination
10. Practice Areas
- Commercial Litigation
- Construction Disputes
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
N/A | N/A | No | N/A | N/A | N/A |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Subcontract
- Marine works
- Earth bund method
- Method statement
- Wrongful termination
- Repudiation
- Revised Programme
- Original Programme
15.2 Keywords
- construction
- contract
- subcontract
- marine works
- breach
- termination
- Singapore
16. Subjects
- Construction Dispute
- Contract Law
- Subcontracts
- Marine Works
17. Areas of Law
- Contract Law
- Construction Law
- Breach of Contract