Burwill Trading Pte Ltd v Panwah Steel Pte Ltd: Dispute over Steel Bar Supply Contracts

In a suit before the High Court of Singapore on 27 December 2005, Burwill Trading Pte Ltd sued Panwah Steel Pte Ltd for $1,400,403.54 for the supply of reinforcing steel bars under three contracts. Panwah Steel admitted liability for $1,394,953.65 but counterclaimed against Burwill Trading for non-delivery of rebars under four contracts. Justice Woo Bih Li ruled in favor of Burwill Trading, granting judgment for $1,394,953.65 and dismissing Panwah Steel's counterclaim.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Judgment for Plaintiff; Defendant's Counterclaim Dismissed

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Burwill Trading sued Panwah Steel for payment of steel bars. Panwah counterclaimed for non-delivery. The court ruled in favor of Burwill, dismissing Panwah's counterclaim.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Panwah Steel Pte LtdDefendantCorporationCounterclaim DismissedLost
Burwill Trading Pte LtdPlaintiffCorporationJudgment for PlaintiffWon

3. Judges

Judge NameTitleDelivered Judgment
Woo Bih LiJudgeYes

4. Counsels

4. Facts

  1. Burwill agreed to sell rebars to Panwah for the Changi Water Reclamation Plant project.
  2. The Changi Agreement was extended to 30 June 2004 with a condition that supply would be as per the progress requirement of the site.
  3. Burwill ceased delivery on 25 June 2004, claiming Panwah's orders were not in line with site progress.
  4. Koh Brothers had a surplus of rebars from another site and deployed them to the C3A site.
  5. Panwah exceeded its credit limit with Burwill.
  6. Panwah imported rebars from other sources.

5. Formal Citations

  1. Burwill Trading Pte Ltd v Panwah Steel Pte Ltd, Suit 928/2004, [2005] SGHC 234

6. Timeline

DateEvent
Koh Brothers Building & Civil Engineering Contractor (Pte) Ltd and Panwah Steel Pte Ltd KB Agreement dated
Changi Agreement signed
Panwah Steel Pte Ltd signed KB Agreement
Start date of supply under the Changi Agreement
First Term Contract signed
Panwah contracted to import rebars into Singapore
Yung Sheng Agreement signed
Second Term Contract signed
Meeting between Burwill Trading Pte Ltd and Panwah Steel Pte Ltd representatives
Panwah Steel Pte Ltd obtained confirmation from Koh Brothers
Telefax from Panwah Steel Pte Ltd to Burwill Trading Pte Ltd
Telefax from Burwill Trading Pte Ltd to Panwah Steel Pte Ltd
Original end date of supply under the Changi Agreement
Meeting at C3A site between representatives from Burwill Trading Pte Ltd, Panwah Steel Pte Ltd and Koh Brothers
Deliveries ceased under the Yung Sheng Agreement
Total amount owing by Panwah Steel Pte Ltd to Burwill Trading Pte Ltd was $3,749,696.55
Panwah Steel Pte Ltd ordered 13,739mt of rebars between April and June
Leap Hong Construction Co Pte Ltd wound up in May
Burwill Trading Pte Ltd purported to reduce Panwah Steel Pte Ltd’s total credit limit to $1m
Contract signed for importation of rebars by Panwah Steel Pte Ltd
Meeting between Burwill Trading Pte Ltd and Panwah Steel Pte Ltd
Burwill Trading Pte Ltd letter to Panwah Steel Pte Ltd
Burwill Trading Pte Ltd ceased delivery of rebars
Lunch and telephone call between Chang Meng and Mr Lim
Extension of Changi Agreement expired
Formal notification of cessation of delivery of rebars
Second Burmese Agreement signed
Contract signed for importation of rebars by Panwah Steel Pte Ltd
Meeting on 7 July 2004
Panwah Steel Pte Ltd letter to Burwill Trading Pte Ltd
Burwill Trading Pte Ltd letter to Panwah Steel Pte Ltd
Burwill Trading Pte Ltd letter to terminate the Burmese Agreements
Panwah Steel Pte Ltd reply to Burwill Trading Pte Ltd
Burwill Trading Pte Ltd solicitors letter
Physical importation under contracts signed on 15 June 2004 and 5 July 2004
Date of Writ of Summons
Judgment reserved

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found that Burwill was justified in ceasing supply under the Changi Agreement due to Panwah's failure to meet the condition regarding progress requirements and credit limit.
    • Category: Substantive
    • Sub-Issues:
      • Failure to deliver goods
      • Failure to adhere to credit limit
  2. Interpretation of Contractual Terms
    • Outcome: The court applied the contra proferentem rule to interpret ambiguous clauses against Burwill, the drafter of the terms.
    • Category: Substantive
    • Sub-Issues:
      • Ambiguity in contract language
      • Application of contra proferentem rule

8. Remedies Sought

  1. Monetary Damages
  2. Indemnity

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Commercial Litigation

11. Industries

  • Construction
  • Steel Trading

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
No cited cases

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
No applicable statutes

15. Key Terms and Keywords

15.1 Key Terms

  • Rebars
  • Changi Agreement
  • Credit Limit
  • Progress Requirement
  • Non-Delivery
  • Contra Proferentem
  • Standard Terms and Conditions of Sale

15.2 Keywords

  • steel bars
  • rebars
  • contract
  • breach
  • credit limit
  • construction
  • Singapore
  • Changi Agreement
  • Panwah Steel
  • Burwill Trading

17. Areas of Law

16. Subjects

  • Contract Dispute
  • Sale of Goods
  • Construction Law