Construction of Contract
Construction of Contract is a specialized practice area in Singapore's legal system. This area encompasses 35 cases from 2001 to 2023.
Leading Law Firms
Analysis of law firms specializing in Construction of Contract, ranked by case volume and success rates.
Law Firm | Cases |
---|---|
Drew & Napier LLC16.67% success rate | 6 cases17.1% of area |
Allen & Gledhill LLP20.00% success rate | 5 cases14.3% of area |
Rajah & Tann Singapore LLP25.00% success rate | 4 cases11.4% of area |
WongPartnership LLP66.67% success rate | 3 cases8.6% of area |
Rajah & Tann LLP66.67% success rate | 3 cases8.6% of area |
MPillay100.00% success rate | 3 cases8.6% of area |
Bih Li & Lee50.00% success rate | 2 cases5.7% of area |
UniLegal LLC50.00% success rate | 2 cases5.7% of area |
CTLC Law Corporation50.00% success rate | 2 cases5.7% of area |
Wong Partnership100.00% success rate | 2 cases5.7% of area |
Notable Lawyers
Leading lawyers practicing in Construction of Contract, ranked by case volume and success rates.
Lawyer | Cases |
---|---|
Koh Kok Kwang50.00% success rate | 2 cases5.7% of area |
Toh Jia Yi0.00% success rate | 2 cases5.7% of area |
Gan Kam Yuin50.00% success rate | 2 cases5.7% of area |
Bernard Yee100.00% success rate | 2 cases5.7% of area |
Ng Shu Wen100.00% success rate | 1 cases2.9% of area |
Nandakumar Ponniya Servai100.00% success rate | 1 cases2.9% of area |
Dhillon Dinesh Singh0.00% success rate | 1 cases2.9% of area |
Chua Sui Tong100.00% success rate | 1 cases2.9% of area |
Quek Seng Soon Winston0.00% success rate | 1 cases2.9% of area |
Darrell Low Kim Boon0.00% success rate | 1 cases2.9% of area |
Recent Judgments
Displaying 35 most recent judgments out of 35 total cases
No. | Title | Court | Decision Date | Outcomes |
---|---|---|---|---|
1 | CZO v CZP: Setting Aside Arbitration Award for Breach of Natural Justice | General Division of the High Court of the Republic of Singapore | 27 Aug 2023 | Application dismissed with costs. |
2 | Carlsberg South Asia Pte Ltd v Pawan Kumar Jagetia: Breach of Employment Contract & Implied Terms | Appellate Division of the High Court | 23 Aug 2023 | Appeal allowed in part. |
3 | ICOP Construction v. Tiong Seng: Microtunnelling Dispute over Contract Termination and Delay Claims | General Division of the High Court of the Republic of Singapore | 11 Oct 2022 | Judgment partially for Plaintiff, ICOP Construction, and partially for Defendant, Tiong Seng Civil Engineering; Quantum Hearing ordered. |
4 | Shanghai Xinan v Great Wall: Enforcing Foreign Arbitral Award & Arbitration Agreement Validity | General Division of the High Court | 17 Mar 2022 | Great Wall’s application to set aside the Order is dismissed. |
5 | Nambu PVD v UBTS: Exclusion Clauses & Contractual Terms in Machine Transport | Court of Appeal of the Republic of Singapore | 19 Oct 2021 | Both appeals dismissed. |
6 | CJM v CJT: Recourse Against Arbitration Award for Dismissal of Earn-Out Payment Claim | SINGAPORE INTERNATIONAL COMMERCIAL COURT | 14 Jun 2021 | Plaintiffs' Originating Summons to set aside two paragraphs in the Award is dismissed. The plaintiffs’ application to amend their Originating Summons to set aside two further paragraphs is likewise dismissed. |
7 | CJY v CJZ: Stay of Court Proceedings Pending Arbitration Over Wrongful Performance Bond Calls and Construction Defects | General Division of the High Court | 22 Mar 2021 | Case management stay granted, suit stayed pending the determination of the arbitration. |
8 | CBS v CBP: Setting Aside Arbitral Award for Breach of Natural Justice | Court of Appeal of the Republic of Singapore | 19 Jan 2021 | Appeal Dismissed |
9 | Ramo Industries v DLE Solutions: Structural Steel Contract Dispute | High Court of the Republic of Singapore | 06 Jan 2020 | Judgment for Plaintiff in part; Counterclaim allowed in part. |
10 | BRQ v BRS: Setting Aside Arbitral Award for Cost Overrun & BPTA Charges | High Court of the Republic of Singapore | 17 Nov 2019 | Both applications dismissed, thereby leaving the award intact. |
11 | DNKH Logistics Pte Ltd v Liberty Insurance Pte Ltd: Fire Insurance Policy Coverage Dispute | High Court of Singapore | 23 Aug 2018 | No order made on the Application |
12 | Didwania v Hauslab: Enforcing Adjudication & Standard of Proof for Novation in Construction | Court of Appeal of the Republic of Singapore | 16 Mar 2017 | Appeal Dismissed |
13 | Bunge SA v Indian Bank: Forum Non Conveniens & Breach of Undertaking | High Court | 29 Dec 2015 | Singapore proceedings stayed in favour of India as the more appropriate forum. |
14 | William Jacks v Nelson Honey: Long-Arm Jurisdiction & Forum Non Conveniens | High Court | 15 Sep 2015 | Summons dismissed on the condition that William Jacks abandons proceedings in New Zealand if it fails to dismiss or stay proceedings there. |
15 | Boustead Singapore Ltd v Arab Banking Corp: Fraud, Demand Guarantees & Unconscionability | High Court | 10 Mar 2015 | Judgment for Plaintiff; ABC is injuncted from receiving payment from Boustead under the facility agreement demand and is injuncted from making payment to BCD on BCD’s counter-guarantee demands. The event-of-default notice is invalid. |
16 | JK Integrated v 50 Robinson: Unconscionability in Performance Bond Call & Construction Dispute | High Court | 03 Mar 2015 | Application to set aside ex parte injunction allowed. |
17 | Alliance Concrete v Sato Kogyo: Frustration of Contract & Sand Ban Impact on RMC Supply | Court of Appeal | 29 May 2014 | Appeal allowed with costs. Contracts discharged by frustration. |
18 | Indian Overseas Bank v Svil Agro: Breach of Guarantee & Enforceability of Judgments | High Court | 29 May 2014 | Judgment for Plaintiff |
19 | Fairview v Ong & Ong: Architectural Services Dispute & Wrongful Termination | Court of Appeal | 19 Jan 2014 | Fairview's appeal dismissed; Ong & Ong's appeal allowed. |
20 | Holland Leedon v C & P Transport: Warehouseman Negligence & Liability for Damaged Metal Coils | High Court | 30 Dec 2013 | Judgment for Plaintiff |
21 | China Taiping Insurance v Teoh Cheng Leong: Indemnities, On-Demand Guarantees & Security Bonds | High Court | 02 Jan 2012 | Interlocutory judgment for the Plaintiff with damages to be assessed by the Registrar. |
22 | MovingU v Trans-Cab: Breach of Contract & Mobile Credit Card Reader Dispute | High Court | 27 Nov 2011 | Plaintiff's action is dismissed with costs; remedies prayed for in the Defendant's counterclaim are granted with damages to be assessed by the Registrar. |
23 | Doshion Ltd v Sembawang Engineers: Dispute Over Settlement Agreement and Arbitration Termination | High Court | 27 Feb 2011 | Plaintiff's application dismissed. |
24 | Holcim v Precise Development: Force Majeure & Indonesian Sand Ban Impact on Concrete Supply | Court of Appeal | 18 Jan 2011 | Appeal Allowed |
25 | Anti-Corrosion Pte Ltd v Berger Paints Singapore Pte Ltd: Defective Paint Claim | High Court | 02 Dec 2010 | Plaintiff's action dismissed; Defendant's counterclaim allowed. |
26 | Jiangsu Hantong v Sevan Holding: Stay of Action for Arbitration | High Court | 28 Dec 2009 | Appeal dismissed with costs. |
27 | Jurong Port v Huationg: Indemnity Clauses & Negligence Liability | High Court | 25 Jun 2009 | Appeal Dismissed |
28 | Ong Kai Hian v Tan Hong Suan Cecilia: Amendment of Pleadings & New Cause of Action | High Court | 08 Mar 2009 | Application for amendment of pleadings allowed in part and disallowed in part. |
29 | Travista Development v Tan Kim Swee: Breach of Contract & Estoppel in Property Redevelopment | High Court | 17 Jun 2007 | The plaintiff’s application was dismissed and the defendants’ counterclaim was allowed. The sale and purchase agreement was rescinded, the deposit was forfeited, and the plaintiff was ordered to pay damages. |
30 | Panwah Steel v Koh Brothers: Project-Specific Contract Dispute Over Steel Rebars for Changi Water Reclamation Plant | Court of Appeal of the Republic of Singapore | 17 Sep 2006 | Appeal Allowed |
31 | Burwill Trading Pte Ltd v Panwah Steel Pte Ltd: Dispute over Steel Bar Supply Contracts | High Court | 26 Dec 2005 | Judgment for Plaintiff; Defendant's Counterclaim Dismissed |
32 | - | 03 Mar 2003 | Unknown | |
33 | Ng Huat Engineering v Jurong Town Corp: Extension of Time to Appeal Arbitration Award | High Court | 26 Jan 2003 | The application for an extension of time to apply for leave to appeal was dismissed. |
34 | Li Hwee v Advanced Construction: Wrongful Repudiation of Sub-Contract Dispute | High Court | 02 Dec 2002 | Judgment for Defendant |
35 | Credit Agricole Indosuez v Banque Nationale de Paris: Letter of Credit Construction & UCP Rules | Court of Appeal of the Republic of Singapore | 13 Feb 2001 | Appeal allowed. |