RDC Concrete v Sato Kogyo: Termination of Contract for Failure to Supply Concrete Meeting LTA Requirements
RDC Concrete Pte Ltd appealed against the High Court's decision regarding its contract with Sato Kogyo (S) Pte Ltd for supplying ready-mixed concrete for the Lorong Chuan Station project. The Court of Appeal addressed issues including whether the contract was exclusive, the applicability of force majeure clauses, and the entitlement to terminate the contract due to non-supply and failure to meet Land Transport Authority (LTA) requirements. The court allowed the appeal in part, finding RDC Concrete liable for cost differentials incurred by Sato Kogyo due to RDC's failure to supply concrete and meet LTA standards, but upheld Sato Kogyo's right to suspend supply due to non-payment.
1. Case Overview
1.1 Court
Court of Appeal1.2 Outcome
Appeal allowed in part
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
RDC Concrete's appeal against Sato Kogyo's termination of contract for failing to supply concrete meeting LTA requirements was dismissed.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Sato Kogyo (S) Pte Ltd | Respondent, Plaintiff | Corporation | Appeal allowed in part | Partial | |
RDC Concrete Pte Ltd | Appellant, Defendant | Corporation | Appeal dismissed in part | Partial |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Chan Sek Keong | Chief Justice | No |
Andrew Phang Boon Leong | Justice of the Court of Appeal | Yes |
V K Rajah | Justice of the Court of Appeal | No |
4. Counsels
4. Facts
- Sato Kogyo contracted with RDC Concrete for concrete supply for the Lorong Chuan Station project.
- RDC Concrete was to supply approximately 70,000m3 of concrete between September 2003 and June 2006.
- Cube tests in May and June 2004 revealed unacceptable concrete strength, leading to LTA suspension.
- RDC Concrete failed to supply concrete on 42 occasions after the suspension was lifted.
- Sato Kogyo terminated the contract on May 30, 2005, due to persistent supply failures and non-compliance with LTA requirements.
- The LTA required concrete to pass strength tests at 28 days and at a peak core temperature below 70°C.
- RDC Concrete suspended supply on April 5, 2005, due to non-payment by Sato Kogyo.
5. Formal Citations
- RDC Concrete Pte Ltd v Sato Kogyo (S) Pte Ltd and Another Appeal, CA 151/2006, 152/2006, [2007] SGCA 39
6. Timeline
Date | Event |
---|---|
Sato Kogyo appointed as main contractor for Lorong Chuan Station project. | |
RDC Concrete's revised quotation for concrete supply. | |
Sato Kogyo's letter of intent, forming the contract with RDC Concrete. | |
Contract period for concrete supply begins. | |
Tests conducted on concrete supplied by RDC Concrete. | |
Tests conducted on concrete supplied by RDC Concrete. | |
LTA instructs Sato Kogyo to suspend RDC Concrete's concrete supply for structural elements. | |
Sato Kogyo notifies RDC Concrete it will charge for cost differentials of obtaining concrete from alternative suppliers. | |
Suspension of RDC Concrete's supply begins. | |
Sato Kogyo notifies RDC Concrete it will charge for cost differentials of obtaining concrete from alternative suppliers. | |
LTA approves Sato Kogyo's request to allow RDC Concrete to resume concrete supply from Kaki Bukit plant. | |
RDC Concrete resumes concrete supply. | |
RDC Concrete suspends supply of concrete. | |
Sato Kogyo sends letter imposing 6% administrative charge. | |
Sato Kogyo terminates the contract with RDC Concrete. | |
Writ filed. | |
Contract between Plaintiff and Island Concrete Pte Ltd. | |
Defendant files defence and counterclaim. | |
Original contract period for concrete supply ends. | |
Civil Appeal No 151 of 2006 and Civil Appeal No 152 of 2006 | |
Judgment reserved. |
7. Legal Issues
- Breach of Contract
- Outcome: The court found that RDC Concrete breached the contract by failing to supply concrete and meet LTA requirements, entitling Sato Kogyo to terminate the contract.
- Category: Substantive
- Sub-Issues:
- Failure to supply concrete
- Failure to meet LTA requirements
- Force Majeure
- Outcome: The court held that the force majeure clauses did not exempt RDC Concrete from liability for non-supply due to market raw material shortages or plant breakdowns.
- Category: Substantive
- Sub-Issues:
- Market raw material shortages
- Unforeseen plant breakdowns
- Termination of Contract
- Outcome: The court upheld Sato Kogyo's right to terminate the contract due to RDC Concrete's persistent failure to supply and failure to comply with LTA requirements.
- Category: Substantive
- Sub-Issues:
- Persistent failure to supply
- Failure to comply with LTA requirements
- Damages for Breach of Contract
- Outcome: The court found RDC Concrete liable for the cost differentials incurred by Sato Kogyo due to RDC's failure to supply concrete and meet LTA standards.
- Category: Substantive
- Sub-Issues:
- Direct costs
- Cost differentials
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Commercial Litigation
- Construction Law
- Contract Disputes
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Sato Kogyo (S) Pte Ltd v RDC Concrete Pte Ltd | High Court | Yes | [2006] SGHC 213 | Singapore | Cited for the trial judge's findings on the period of suspension. |
Forefront Medical Technology (Pte) Ltd v Modern-Pak Pte Ltd | High Court | Yes | [2006] 1 SLR 927 | Singapore | Cited for the principle of implying terms into a contract. |
Nam Kee Asphalt Pte Ltd v Chew Eu Hock Construction Co Pte Ltd | High Court | Yes | [2000] SGHC 45 | Singapore | Cited for the principle that an estimated quantity in a supply contract does not imply an exclusive supply agreement. |
Raineri v Miles | House of Lords | Yes | [1981] AC 1050 | England | Cited for the principle that an innocent party is entitled to claim damages for breach of contract even if they do not terminate the contract. |
Singapore Telecommunications Ltd v Starhub Cable Vision Ltd | Court of Appeal | Yes | [2006] 2 SLR 195 | Singapore | Cited for the definition of direct loss in contract law. |
Saint Line Limited v Richardsons, Westgarth & Co, Limited | English High Court | Yes | [1940] 2 KB 99 | England | Cited for the definition of direct loss in contract law. |
Hadley v Baxendale | Court of Exchequer | Yes | (1854) 9 Exch 341; 156 ER 145 | England | Cited for the test for remoteness of damages in contract law. |
C Czarnikow Ltd v Koufos, The Heron II | House of Lords | Yes | [1969] 1 AC 350 | England | Cited for the principle of imputed knowledge in determining direct loss. |
CHS CPO GmbH v Vikas Goel | High Court | Yes | [2005] 3 SLR 202 | Singapore | Cited for the principle of imputed knowledge in determining direct loss. |
Glahe International Expo AG v ACS Computer Pte Ltd | Court of Appeal | Yes | [1999] 2 SLR 620 | Singapore | Cited for the distinction between force majeure clauses and the doctrine of frustration. |
Magenta Resources (S) Pte Ltd v China Resources (S) Pte Ltd | High Court | Yes | [1996] 3 SLR 62 | Singapore | Cited for the interpretation of force majeure clauses as contractual terms dealing with situations beyond the parties' control. |
China Resources (S) Pte Ltd v Magenta Resources (S) Pte Ltd | Court of Appeal | Yes | [1997] 1 SLR 707 | Singapore | Affirmed the High Court decision in Magenta Resources (S) Pte Ltd v China Resources (S) Pte Ltd. |
Davis Contractors Ltd v Fareham Urban District Council | House of Lords | Yes | [1956] AC 696 | England | Cited for the definition of frustration of contract. |
The Kriti Rex | English High Court | Yes | [1996] 2 Lloyd’s Rep 171 | England | Cited for the presumption that force majeure is restricted to supervening events arising without the fault of either party. |
Metropolitan Water Board v Dick, Kerr and Company, Limited | House of Lords | Yes | [1918] AC 119 | England | Cited for the principle that courts construe force majeure clauses strictly. |
Bank Line, Limited v Arthur Capel and Company | House of Lords | Yes | [1919] AC 435 | England | Cited for the principle that courts construe force majeure clauses strictly. |
Channel Island Ferries Ltd v Sealink UK Ltd | English Court of Appeal | Yes | [1988] 1 Lloyd’s Rep 323 | England | Cited for the principle that a party relying on a force majeure clause must show they took reasonable steps to avoid its operation. |
Continental Grain Export Corporation v STM Grain Ltd | English High Court | Yes | [1979] 2 Lloyd’s Rep 460 | England | Cited for the principle that a party invoking a force majeure clause must prove no goods were available and they could not obtain them by reasonable means. |
Andre & Cie SA v Tradax Export SA | English Court of Appeal | Yes | [1983] 1 Lloyd’s Rep 254 | England | Approved the principles in Continental Grain Export Corporation v STM Grain Ltd. |
Janagi v Ong Boon Kiat | Malaysian High Court | Yes | [1971] 2 MLJ 196 | Malaysia | Cited for the principle that the court is not entitled to make a decision on an issue which has not been raised by the parties in their pleadings. |
Multi-Pak Singapore Pte Ltd v Intraco Ltd | High Court | Yes | [1992] 2 SLR 793 | Singapore | Cited for the principle that the court is not entitled to make a decision on an issue which has not been raised by the parties in their pleadings. |
Chan Buck Kia v Naga Shipping & Trading Co Ltd | High Court | Yes | [1963] MLJ 159 | Singapore | Cited for reference to s 3(3) of the Frustrated Contracts Act in the context of force majeure clauses. |
Brauer & Co (Gt Britain), Ltd v James Clark (Brush Materials), Ltd | English Court of Appeal | Yes | [1952] 2 Lloyd’s Rep 147 | England | Cited for the principle that a price increase does not constitute force majeure. |
GIB Automation Pte Ltd v Deluge Fire Protection (SEA) Pte Ltd | High Court | Yes | [2007] 2 SLR 918 | Singapore | Cited for a discussion of the situation where a party allegedly renouncing the contract bona fide concludes that it was justified in not proceeding with the contract. |
Woodar Investment Development Ltd v Wimpey Construction UK Ltd | House of Lords | Yes | [1980] 1 WLR 277 | England | Cited for a discussion of the situation where a party allegedly renouncing the contract bona fide concludes that it was justified in not proceeding with the contract. |
Bentsen v Taylor, Sons & Co | English Court of Appeal | Yes | [1893] 2 QB 274 | England | Cited for the classic exposition of the condition-warranty approach. |
Hongkong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha Ltd | English Court of Appeal | Yes | [1962] 2 QB 26 | England | Cited for the Hongkong Fir approach to breach of contract. |
Suisse Atlantique Société d’Armement Maritime SA v NV Rotterdamsche Kolen Centrale | House of Lords | Yes | [1967] 1 AC 361 | England | Cited for the principle that a breach must go to the root of the contract to justify termination. |
Photo Production Ltd v Securicor Transport Ltd | House of Lords | Yes | [1980] AC 827 | England | Cited for the concept of fundamental breach of contract. |
Bunge Corporation, New York v Tradax Export SA, Panama | House of Lords | Yes | [1981] 1 WLR 711 | England | Cited for the 'wait and see' method in the Hongkong Fir approach. |
Bunge Corpn v Tradax SA | Court of Appeal | Yes | [1981] 2 All ER 513 | England | Cited for the observation that a wholesale adoption of the Hongkong Fir approach would result in its complete eclipse of the condition-warranty approach. |
The Ymnos | English High Court | Yes | [1982] 2 Lloyd’s Rep 574 | England | Cited for the observation that the approach adopted would, in effect, result in the concept of the warranty, as we know it, being effectively effaced. |
Torvald Klaveness A/S v Arni Maritime Corporation | House of Lords | Yes | [1994] 1 WLR 1465 | England | Cited for the nomenclature of 'innominate' term. |
Alfred McAlpine Plc v BAI (Run-Off) Ltd | English Court of Appeal | Yes | [2000] 1 Lloyd’s Rep 437 | England | Cited for the nomenclature of 'innominate' term. |
The Seaflower | English Court of Appeal | Yes | [2001] 1 Lloyd’s Rep 341 | England | Cited for the nomenclature of 'innominate' term. |
State Trading Corporation of India Ltd v M Golodetz Ltd | English Court of Appeal | Yes | [1989] 2 Lloyd’s Rep 277 | England | Cited for the legal position applicable to the situation where both of the contracting parties have breached the contract |
Jet Holding Ltd v Cooper Cameron (Singapore) Pte Ltd | Court of Appeal | Yes | [2006] 3 SLR 769 | Singapore | Cited for the legal position applicable to the situation where both of the contracting parties have breached the contract |
Universal Bulk Carriers Ltd v Andre et Cie | English Court of Appeal | Yes | [2001] 2 Lloyd’s Rep 65 | England | Cited for the support in decisions from the House of Lords |
13. Applicable Rules
Rule Name |
---|
Rules of Court |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Sale of Goods Act | Singapore |
Frustrated Contracts Act | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Ready-mixed concrete
- Force majeure
- LTA requirements
- Cost differentials
- Suspension of supply
- Termination of contract
- Cube tests
- Direct cost
- Market raw material shortages
- Plant breakdowns
15.2 Keywords
- Contract
- Concrete
- Force Majeure
- Construction
- Breach
17. Areas of Law
Area Name | Relevance Score |
---|---|
Contract Law | 95 |
Breach of Contract | 90 |
Force Majeure | 85 |
Damages | 75 |
Frustration | 60 |
Construction Contract | 50 |
16. Subjects
- Contract Law
- Construction Law
- Breach of Contract
- Force Majeure