Chip Hup Hup Kee Construction v Ssangyong: Setting Aside Adjudication Determination Under SOP Act

In Chip Hup Hup Kee Construction Pte Ltd v Ssangyong Engineering & Construction Co Ltd, the High Court of Singapore addressed the validity of an adjudication determination under the Building and Construction Industry Security of Payment Act (SOP Act). Chip Hup Hup Kee Construction sought to enforce an unsigned adjudication determination, while Ssangyong Engineering & Construction Co Ltd applied to set it aside, arguing it was a draft, unsigned, and served late. The court, Ho May Kim AR, dismissed Ssangyong's application, holding that the delay in service by the Singapore Mediation Centre (SMC) and the lack of a signature did not invalidate the determination. The court considered the purpose of the SOP Act and the roles of the adjudicator and SMC, finding that the determination was valid despite the procedural issues. The claim was related to a payment dispute arising from RC Structural Works Sub-Contract for Tower 1 of the Marina Bay Sands Integrated Resort Project.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Application to set aside the Unsigned Adjudication Determination dismissed.

1.3 Case Type

Building and Construction Law

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

The High Court considered whether a delay in service and lack of signature invalidated an adjudication determination under the SOP Act. The court dismissed the application to set aside.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Chip Hup Hup Kee Construction Pte LtdClaimant, ApplicantCorporationApplication to set aside the Unsigned Adjudication Determination dismissedWonMelvin Chan, Jonathan Yang
Ssangyong Engineering & Construction Co LtdRespondentCorporationApplication to set aside the Unsigned Adjudication Determination dismissedLostSoh Lip San, Sim Chee Siong, Paul Lie

3. Judges

Judge NameTitleDelivered Judgment
Ho May KimAssistant RegistrarYes

4. Counsels

Counsel NameOrganization
Melvin ChanTSMP Law Corporation
Jonathan YangTSMP Law Corporation
Soh Lip SanRajah & Tann LLP
Sim Chee SiongRajah & Tann LLP
Paul LieRajah & Tann LLP

4. Facts

  1. Ssangyong engaged Chip Hup Hup Kee Construction as the RC Structural Works Sub-Contractor.
  2. A payment dispute arose from Progress Claim No.7.
  3. Chip Hup Hup Kee Construction invoked the adjudication process under the SOP Act.
  4. The SMC served the Unsigned Adjudication Determination 18 days after receiving it.
  5. The Adjudicator produced a Signed Adjudication Determination subsequent to the Unsigned Adjudication Determination.
  6. The Signed and Unsigned Adjudication Determinations differed in respect of the cost of sharing of the conference room and the extension of time.
  7. Chip Hup Hup Kee Construction sought to rely solely on the Unsigned Adjudication Determination.

5. Formal Citations

  1. Chip Hup Hup Kee Construction Pte Ltd v Ssangyong Engineering & Construction Co Ltd, OS 976/2009, SUM 5184/2009, [2009] SGHC 269

6. Timeline

DateEvent
Letter of acceptance issued by Ssangyong to Chip Hup Hup Kee Construction.
Chip Hup Hup Kee Construction invoked the adjudication process.
Chip Hup Hup Kee Construction lodged an adjudication application with the SMC.
SMC notified the parties that Ms Lim Ee Ping had been appointed the adjudicator.
Ssangyong submitted its adjudication response.
Parties attended an adjudication conference with the Adjudicator.
Parties submitted their written submissions to the Adjudicator.
Adjudicator requested the Parties to extend the deadline.
Parties extended the deadline to 8 October 2008.
SMC received the Unsigned Adjudication Determination from the Adjudicator.
Adjudicator sent an email to the Parties regarding the cost of the room.
Chip Hup Hup Kee Construction replied to the Adjudicator's email.
Ssangyong replied to the Adjudicator's email.
Adjudicator sent the Signed Adjudication Determination to the SMC.
SMC served the Signed Adjudication Determination on the Parties.
Ssangyong's solicitors wrote to the SMC enquiring when the Signed Adjudication Determination was received.
SMC served the Unsigned Adjudication Determination on the Parties.
Chip Hup Hup Kee Construction was granted leave of Court to enforce the Unsigned Adjudication Determination.
Ssangyong filed a summons seeking to set aside the Unsigned Adjudication Determination.
Judgment reserved.

7. Legal Issues

  1. Validity of Adjudication Determination
    • Outcome: The court held that the delay in service and lack of signature did not invalidate the adjudication determination.
    • Category: Substantive
    • Sub-Issues:
      • Delay in service of adjudication determination
      • Lack of signature on adjudication determination
    • Related Cases:
      • [2009] SGHC 257
      • [2004] NSWCA 394
      • [2004] NSWCA 395
      • [2005] NSWSC 77
      • [2003] SLT 740
      • [2003] EWHC 3100
      • [2006] EWHC 3413
      • [2007] EWHC 1055
      • [2007] EWHC 2420

8. Remedies Sought

  1. Setting aside the Unsigned Adjudication Determination
  2. Setting aside the Order of Court granting leave to enforce the Unsigned Adjudication Determination

9. Cause of Actions

  • Enforcement of Adjudication Determination
  • Setting Aside of Adjudication Determination

10. Practice Areas

  • Construction Law
  • Adjudication

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
SEF Construction Pte Ltd v Skoy Connected Pte LtdHigh CourtYes[2009] SGHC 257SingaporeApplied the principles for setting aside an adjudication determination under the SOP Act, focusing on basic requirements for a valid determination.
Brodyn v DavenportNew South Wales Court of AppealYes[2004] NSWCA 394AustraliaCited for the view that an adjudicator's determination must satisfy essential conditions laid down by the relevant Act to have legal effect.
Transgrid v Siemens Ltd & AnorNew South Wales Court of AppealYes[2004] NSWCA 395AustraliaCited for the principle that review is available only where the determination is not a determination within the meaning of the Act.
Coordinated Construction Co v J M Hargreaves and OrsNew South Wales Supreme CourtYes[2005] NSWSC 77AustraliaCited for the view that factors considered in determining whether a determination was reviewable were anterior rather than interior.
St. Andrews Bay Development Ltd v HBG Management LtdScottish CourtYes[2003] SLT 740ScotlandDiscussed the duty to communicate the decision to the parties, even if the statute is silent on the communication of the decision.
Barnes & Elliot Ltd v Taylor Woodrow Holdings LtdEnglish High CourtYes[2003] EWHC 3100EnglandDiscussed the importance of timely communication of the decision and the consequences of delay.
Cubitt Building & Interiors Ltd v Fleetglade LtdEnglish High CourtYes[2006] EWHC 3413EnglandCited for the tolerance of a one-day delay in the service of an adjudication determination.
Mott MacDonald Limited v London & Regional Properties LimitedEnglish High CourtYes[2007] EWHC 1055EnglandCited for the view that a signature was not a necessary step that had to be taken for a decision to be reached.
Treasure & Son Limited v Martin DawesEnglish High CourtYes[2007] EWHC 2420EnglandCited for the view that a signature was not required and not necessary on any commercial or practicable basis for the adjudicator to reach a determination.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 27(5)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 17(8)Singapore
Interpretation Act (Cap 1, 2002 Rev Ed)Singapore
Interpretation Act (Cap 1, 2002 Rev Ed) s 9ASingapore
Building and Construction Industry Security of Payment Act s 4Singapore
Building and Construction Industry Security of Payment Act s 10Singapore
Building and Construction Industry Security of Payment Act s 13Singapore
Building and Construction Industry Security of Payment Act s 14Singapore
Building and Construction Industry Security of Payment Act ss 17(1) and (2)Singapore
Building and Construction Industry Security of Payment Act s 16(3)Singapore
Building and Construction Industry Security of Payment Act s 28 (4) (a)Singapore
Building and Construction Industry Security of Payment Act s 13(1)Singapore
Building and Construction Industry Security of Payment Act s 13(4)Singapore
Building and Construction Industry Security of Payment Act s 14(1)Singapore
Building and Construction Industry Security of Payment Act s 14(3)Singapore
Building and Construction Industry Security of Payment Act s 15(4)Singapore
Building and Construction Industry Security of Payment Act s 18(5)Singapore
Building and Construction Industry Security of Payment Act s 18(6)Singapore
Building and Construction Industry Security of Payment Act s 28 (4)Singapore
Building and Construction Industry Security of Payment Act s 22(1)(a)Singapore
Building and Construction Industry Security of Payment Act s 22(2)(a)Singapore
Building and Construction Industry Security of Payment Act s 18(2)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Adjudication Determination
  • Security of Payment Act
  • Singapore Mediation Centre
  • Unsigned Adjudication Determination
  • Signed Adjudication Determination
  • Service of Adjudication Determination
  • Authorised Nominating Body

15.2 Keywords

  • Adjudication
  • SOP Act
  • Construction
  • Payment Dispute
  • Singapore
  • Building and Construction Industry Security of Payment Act

16. Subjects

  • Construction Dispute
  • Adjudication
  • Contract Law

17. Areas of Law

  • Building and Construction Law
  • Dispute Resolution
  • Alternative Dispute Resolution