Gammon v JBE Properties: Injunction Against Performance Bond Call Due to Unconscionability

Gammon Pte Limited sought an injunction against JBE Properties Pte Ltd in the High Court of Singapore on April 28, 2010, to prevent JBE from calling on a performance bond issued by BNP Paribas Singapore. Gammon argued that JBE's claim was unconscionable due to grossly inflated costs for rectifying defects. The court, presided over by Chan Seng Onn J, found a strong prima facie case of unconscionability and granted the injunction, ordering Gammon to complete rectification works within six months and reserving costs.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Injunction granted to restrain the defendant from receiving payment from BNP Paribas Singapore on a performance bond until further order.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Gammon sought an injunction to restrain JBE Properties from calling on a performance bond. The court granted the injunction, citing unconscionability due to inflated rectification costs.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
SCDA Architects Pte LtdOtherCorporation
JBE Properties Pte LtdDefendantCorporationInjunction Granted AgainstLost
Gammon Pte LimitedPlaintiffCorporationInjunction GrantedWon
BNP Paribas Singapore BranchOtherCorporation

3. Judges

Judge NameTitleDelivered Judgment
Chan Seng OnnJudgeYes

4. Counsels

4. Facts

  1. The defendant engaged the plaintiff to construct a building for $11,515,000.
  2. SCDA Architects Pte Ltd was engaged as the architect and superintending officer.
  3. Defects in the façade cladding were highlighted to the plaintiff.
  4. The defendant called on the performance bond to fund the completion of rectification work.
  5. The plaintiff alleged that the award to Weng Thai Construction was a sham.
  6. WTC's tender price of S$2.2 million to repair minor cladding defects was considered astronomical.
  7. The court found that there was gross exaggeration of the costs of rectification of outstanding defects.

5. Formal Citations

  1. Gammon Pte Limited v JBE Properties Pte Ltd, Suit No 235 of 2009 (Summons No 1224 of 2009), [2010] SGHC 130

6. Timeline

DateEvent
Letter of award issued to the plaintiff to construct the Building.
Contractual completion date.
Extension of the completion date certified by SCDA.
Defects with the façade cladding of the building were highlighted to the plaintiff through the issuance of superintendent officer instructions.
Defects with the façade cladding of the building were highlighted to the plaintiff through the issuance of superintendent officer instructions.
Plaintiff undertook to rectify defects in its letter.
Completion certificate issued certifying completion on 16 January 2008.
Defendant called on the performance bond.
Defendant called on the performance bond.
Lowest quotation from TLT dated for rectification of non-cladding defects.
Award to Weng Thai Construction for rectification of Cladding Defects.
Interim Certificate No 22/09 dated.
Interim Certificate No 23/09 dated.
Decision Date

7. Legal Issues

  1. Unconscionability
    • Outcome: The court found a strong prima facie case of unconscionability due to the grossly inflated costs for rectifying defects.
    • Category: Substantive
    • Related Cases:
      • [2000] 1 SLR(R) 117
      • [1996] SGHC 136
      • [1999] 3 SLR(R) 44

8. Remedies Sought

  1. Injunctive Relief

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Construction Litigation
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Dauphin Offshore Engineering & Trading Pte Ltd v The Private Office of HRH Sheikh Sultan bin Khalifa bin Zayed Al NahyanCourt of AppealYes[2000] 1 SLR(R) 117SingaporeCited for the principle of unconscionability in relation to calls on performance bonds.
Raymond Construction Pte Ltd v Low Yang Tong & AnorHigh CourtYes[1996] SGHC 136SingaporeCited for the definition of 'unconscionability' involving unfairness and conduct lacking in good faith.
GHL Pte Ltd v Unitrack Building Construction Pte Ltd and anotherCourt of AppealYes[1999] 3 SLR(R) 44SingaporeCited regarding abusive calls on performance bonds and the court's intervention in cases of fraud or unconscionability.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
No applicable statutes

15. Key Terms and Keywords

15.1 Key Terms

  • Performance Bond
  • Unconscionability
  • Rectification Costs
  • Defects
  • Injunction
  • Completion Certificate
  • Superintendent Officer Instructions
  • Cladding

15.2 Keywords

  • performance bond
  • unconscionability
  • injunction
  • construction
  • defects
  • rectification costs

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Contract Law
  • Performance Bonds