Keng & Keong Construction v Swee Hong Engineering: Subcontract Dispute over Termination and Damages
In a dispute between Keng & Keong Construction Pte Ltd (Plaintiff) and Swee Hong Engineering Construction Pte Ltd (Defendant) at the High Court of Singapore on 31 March 2011, the court addressed issues arising from the termination of a subcontract for structural works at the "Garden By The Bay Marina South Singapore" project. The Plaintiff claimed wrongful termination and sought unpaid progress claims, retention sum, and damages. The Defendant counterclaimed for breach of contract. The court dismissed the Plaintiff's action for wrongful termination but allowed recovery of unpaid progress claims, retention sum, and material costs. The Defendant's counterclaim for breach of contract was allowed, but only nominal damages of $100 were awarded due to insufficient evidence of actual loss.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Counterclaim allowed in part; nominal damages awarded.
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Subcontract dispute between Keng & Keong Construction and Swee Hong Engineering regarding contract termination, progress claims, and damages. The court ruled in favor of Swee Hong's counterclaim but awarded nominal damages.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Keng & Keong Construction Pte Ltd | Plaintiff | Corporation | Action dismissed in part | Partial | |
Swee Hong Engineering Construction Pte Ltd | Defendant | Corporation | Counterclaim allowed in part | Partial |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Andrew Ang | Judge | Yes |
4. Counsels
Counsel Name | Organization |
---|---|
Christopher Yap Hock Heng | Christopher Yap & Co |
S Thulasidas | Ling Das & Partners |
4. Facts
- Plaintiff was the subcontractor of the defendant for structural works.
- The defendant alleged the plaintiff was in repudiatory breach of contract.
- The plaintiff claimed the defendant prematurely terminated the contract.
- The plaintiff sought unpaid progress claims, retention sum, and damages.
- The defendant counterclaimed for breach of contract.
- The court found the plaintiff was trying to find a way out of the contract.
- The defendant failed to prove it suffered loss as a result of the plaintiff’s breach.
5. Formal Citations
- Keng & Keong Construction Pte Ltd v Swee Hong Engineering Construction Pte Ltd, Suit No 744 of 2009, [2011] SGHC 78
6. Timeline
Date | Event |
---|---|
Letter of award issued by the defendant to the plaintiff. | |
Plaintiff stated they may need to be replaced due to not meeting requirements. | |
Progress Claim No 17 dated. | |
Plaintiff wrote to defendant regarding delays. | |
Meeting between plaintiff and defendant. | |
Meeting between plaintiff, defendant, and sub-subcontractors. | |
Defendant sent plaintiff an email regarding revised schedule. | |
Plaintiff sent defendant a letter accepting repudiation. | |
Progress Claim No 18 dated. | |
Companion Construction & Engineering Pte Ltd sent quotation to defendant. | |
Defendant made an announcement that the plaintiff had terminated the contract. | |
Plaintiff's delivery order No KKPL 2009/07 dated. | |
Defendant sent letter to plaintiff regarding lack of manpower. | |
Silver Sea Contractor Pte Ltd sent quotation to defendant. | |
Decision Date |
7. Legal Issues
- Breach of Contract
- Outcome: The court found that the plaintiff was in breach of contract.
- Category: Substantive
- Sub-Issues:
- Repudiatory breach of contract
- Wrongful termination
- Damages
- Outcome: The court awarded nominal damages to the defendant due to insufficient evidence of actual loss.
- Category: Substantive
- Sub-Issues:
- Quantification of damages
- Liquidated damages
- Nominal damages
8. Remedies Sought
- Monetary Damages
- Recovery of unpaid progress claims
- Recovery of retention sum
9. Cause of Actions
- Breach of Contract
- Wrongful Termination
10. Practice Areas
- Commercial Litigation
- Construction Disputes
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
No cited cases |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Subcontractor
- Repudiation
- Progress Claims
- Retention Sum
- Access Scaffolding
- Formwork Material
- Nominal Damages
15.2 Keywords
- construction
- contract
- subcontractor
- breach of contract
- damages
- Singapore
17. Areas of Law
Area Name | Relevance Score |
---|---|
Breach of Contract | 90 |
Construction Law | 85 |
Contract Law | 75 |
Damages | 60 |
Building and Construction Contracts | 50 |
Subcontracting | 40 |
16. Subjects
- Construction Dispute
- Contract Law