Compact Metal Industries v PPG Industries: Construction Dispute, Defective Paint & Damages

In a construction dispute before the High Court of Singapore, Compact Metal Industries Ltd (plaintiff) sued PPG Industries (Singapore) Pte Ltd (defendant) for damages arising from defective paint supplied for the refurbishment of the Monetary Authority of Singapore Building. The court dismissed the defendant's appeal and allowed the plaintiff's appeal, holding the defendant liable for damages, including reimbursement for liquidated damages imposed on the plaintiff by the main contractor, Taisei Corporation. The plaintiff's claim included rectification costs and damages arising from delay.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Defendant's appeal dismissed; Plaintiff's appeal allowed.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Construction dispute over defective paint. Court awarded damages to Compact Metal Industries, including liquidated damages reimbursement.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
PPG Industries (Singapore) Pte LtdDefendant, AppellantCorporationAppeal DismissedLost
Compact Metal Industries LtdPlaintiff, RespondentCorporationAppeal Allowed in PartPartial

3. Judges

Judge NameTitleDelivered Judgment
Lai Siu ChiuJudgeYes

4. Counsels

4. Facts

  1. Compact Metal Industries Ltd (plaintiff) was a subcontractor for painting aluminum panels.
  2. PPG Industries (Singapore) Pte Ltd (defendant) supplied customized paint for the project.
  3. The paint initially supplied by the defendant was defective, causing delays.
  4. The project completion was delayed by 273 days due to the paint problem.
  5. Taisei Corporation, the main contractor, imposed liquidated damages on the plaintiff.
  6. The plaintiff incurred rectification costs due to the defective paint.
  7. The paint was a customized paint that was featured in the defendant’s standard colour charts.

5. Formal Citations

  1. Compact Metal Industries Ltd v PPG Industries (Singapore) Pte Ltd, Suit No 442 of 2005 (Registrar's Appeal Nos 43 and 49 of 2010), [2012] SGHC 91

6. Timeline

DateEvent
Refurbishment of the Monetary Authority of Singapore Building commenced.
Original completion date of the project.
Project completed.
Writ issued.
Trial held in two tranches.
Assessment of damages began.
Assessment hearing concluded.
Assistant Registrar delivered first grounds of decision.
Assistant Registrar delivered second grounds of decision.
Plaintiff's application granted to adduce further evidence.
Additional orders granted to the plaintiff.
Hearing before the Assistant Registrar.
Hearing to clarify the issue of interest.
Judgment delivered by Lai Siu Chiu J.

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court held that the defendant breached the contract by supplying defective paint.
    • Category: Substantive
    • Sub-Issues:
      • Defective paint supply
      • Failure to supply paint in accordance with contract conditions
    • Related Cases:
      • (1854) 9 Exch 341
  2. Assessment of Damages
    • Outcome: The court upheld the Assistant Registrar's assessment of damages, with some modifications.
    • Category: Procedural
    • Sub-Issues:
      • Rectification costs
      • Delay damages
      • Site preliminaries
      • Overtime costs
      • Backcharges
  3. Liquidated Damages
    • Outcome: The court held that the defendant was liable to reimburse the plaintiff for liquidated damages imposed by the main contractor.
    • Category: Substantive
    • Sub-Issues:
      • Remoteness of damages
      • Foreseeability of damages
    • Related Cases:
      • (1854) 9 Exch 341

8. Remedies Sought

  1. Monetary Damages
  2. Indemnity

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Commercial Litigation
  • Construction Disputes

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Hong Fok Realty Pte Ltd v Bima Investment Pte LtdHigh CourtYes[1992] 2 SLR(R) 834SingaporeCited regarding the principle of rectification costs.
Hadley v BaxendaleCourt of ExchequerYes(1854) 9 Exch 341EnglandCited for the principles governing the recovery of damages for breach of contract.
Tullio Planeta v Maoro Andrea GCourt of AppealYes[1994] SLR(R) 501SingaporeCited for the general rule that costs follow the event.
In Re Elgindata Ltd (No 2)UK appellate courtYes[1992] 1 WLR 1207United KingdomCited for the general rule that costs should follow the event.
Lassiter Ann Masters v To Keng LamHigh CourtYes[2004] 2 SLR(R) 392SingaporeCited regarding the nature of a Registrar's Appeal as an actual rehearing.
Ladd v MarshallCourt of AppealYes[1954] 1 WLR 1489EnglandCited regarding the principles for admitting new evidence.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Civil Law Act (Cap 43, 1999 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Defective Paint
  • Rectification Costs
  • Liquidated Damages
  • Construction Dispute
  • Delay Damages
  • Site Preliminaries
  • Recoating Costs
  • Abortive Installation
  • Tonality
  • Cladding

15.2 Keywords

  • construction
  • contract
  • paint
  • damages
  • liquidated damages
  • Singapore

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Contract Law
  • Damages