Tienrui Design v G & Y Trading: Setting Aside Adjudication Determination under SOP Act

In Tienrui Design & Construction Pte Ltd v G & Y Trading and Manufacturing Pte Ltd, the High Court of Singapore heard an application by Tienrui Design to set aside an adjudication determination made pursuant to the Building and Construction Industry Security of Payment Act (SOP Act). The court, presided over by Lee Seiu Kin J, dismissed the application, finding that the adjudication application had not been filed prematurely. The underlying dispute concerned a sub-contract for the supply and installation of timber doors in a building project. The court awarded costs to G & Y Trading and Manufacturing Pte Ltd.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Application dismissed.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

The High Court dismissed Tienrui Design's application to set aside an adjudication determination, finding the application was not premature under the SOP Act.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Tienrui Design & Construction Pte LtdPlaintiffCorporationApplication DismissedLost
G & Y Trading and Manufacturing Pte LtdDefendantCorporationCosts AwardedWon

3. Judges

Judge NameTitleDelivered Judgment
Lee Seiu KinJudgeYes

4. Counsels

4. Facts

  1. The plaintiff was the main contractor for a project to convert an office building into a hotel.
  2. The plaintiff engaged the defendant as a sub-contractor to supply and install timber doors.
  3. The contract sum was $399,280.00.
  4. The plaintiff complained about the defendant's sub-par performance.
  5. The plaintiff agreed to increase the frequency of payments to help the defendant's financial issues.
  6. The contract was terminated on 28 August 2014.
  7. The defendant served payment claim no 1 for work done between March 2013 and July 2014.

5. Formal Citations

  1. Tienrui Design & Construction Pte Ltd v G & Y Trading and Manufacturing Pte Ltd, Originating Summons No 1005 of 2014, [2015] SGHC 243

6. Timeline

DateEvent
Contract signed
Variation Agreement evidenced in plaintiff's email
Payment Claim served
Payment Response served
Contract terminated
Notification of intention to apply for adjudication
Adjudication application lodged with Singapore Mediation Centre
Adjudicator appointed by SMC
Adjudication Determination rendered
Application dismissed

7. Legal Issues

  1. Premature Adjudication Application
    • Outcome: The court held that the adjudication application was not premature.
    • Category: Procedural
    • Related Cases:
      • [2013] 1 SLR 401
      • [2013] SGHCR 4
      • [2014] SGHC 142
  2. Interpretation of Contractual Terms
    • Outcome: The court found that the timelines stipulated in the Agreements did not apply to payment claims and responses under the SOP Act.
    • Category: Substantive
    • Related Cases:
      • [1935] AC 96
      • [1997] AC 749
  3. Dispute Settlement Period
    • Outcome: The court held that the dispute settlement period was only set in motion after the due date of the payment response.
    • Category: Procedural
    • Related Cases:
      • [2014] SGHCR 10
      • [2015] 1 SLR 648

8. Remedies Sought

  1. Setting aside of adjudication determination

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Construction Litigation
  • Commercial Litigation
  • Arbitration

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Lee Wee Lick Terence (alias Li Weili Terence) v Chua Say Eng (formerly trading as Weng Fatt Construction Engineering) and another appealCourt of AppealYes[2013] 1 SLR 401SingaporeLeft open the question of whether section 13(3)(a) of SOP Act operated as a mandatory condition.
Shin Khai Construction Pte Ltd v FL Wong Construction Pte LtdHigh CourtYes[2013] SGHCR 4SingaporeHeld that section 13(3)(a) of SOP Act constituted a mandatory condition under the Act.
YTL Construction (S) Pte Ltd v Balanced Engineering & Construction Pte LtdHigh CourtYes[2014] SGHC 142SingaporeEndorsed the decision in Shin Khai Construction that the 7-day timeline in s 13(3)(a) must be strictly observed.
W Y Steel Construction Pte Ltd v Osko Pte LtdHigh CourtYes[2013] 3 SLR 380SingaporeCited for the principle that timelines under the SOP Act are tight to facilitate cash flow.
Chase Oyster Bar v Hamo IndustriesNew South Wales Court of AppealYes[2010] NSWCA 190AustraliaCited for the importance of observing tight timelines under the Security of Payment Act.
TransGrid v Siemens and anorSupreme Court of New South WalesYes[2004] NSWSC 87AustraliaCited for the principle of a dual railroad track system consisting of the statutory regime under the SOP Act which operates concurrently with, but is quite distinct from, the contractual regime.
The Commissioners of Inland Revenue v Raphael and othersHouse of LordsYes[1935] AC 96United KingdomCited for the cardinal rule of contractual interpretation that the court must give effect to the intention of the parties as expressed.
Mannai Investment Co Ltd v Eagle Star Life Assurance Co LtdHouse of LordsYes[1997] AC 749United KingdomCited for the principle that contractual interpretation extends to the relevant background against which the words were used.
LH Aluminium Industries Pte Ltd v Newcon Builders Pte LtdHigh CourtYes[2014] SGHCR 10SingaporeDiscussed the dispute settlement period and whether it could commence after the payment response was served.
LH Aluminium Industries Pte Ltd v Newcon Builders Pte LtdHigh CourtYes[2015] 1 SLR 648SingaporeAddressed the issue of the dispute settlement period obliquely.
Zurich Insurance (Singapore) Pte Ltd v B-Gold Interior Design & Construction Pte LtdCourt of AppealYes[2008] 3 SLR(R) 1029SingaporeDiscussed the admissibility of subsequent conduct in ascertaining contractual intention.
Leong Hin Chuee v Citra Group Pte Ltd and othersHigh CourtYes[2015] 2 SLR 603SingaporeHeld that the subsequent conduct of parties could be considered to determine their common intentions if such conduct was evidentially probative.
Jia Min Building Construction Pte Ltd v Ann Lee Pte LtdHigh CourtYes[2004] 3 SLR(R) 288SingaporeCited for the principle that parties that do not take care to properly incorporate their intentions in their contracts have to accept the vagaries of litigation.
Chase Oyster Bar Pty Ltd v Hamo Industries Pty LtdNew South Wales Court of AppealYes[2010] NSWCA 190AustraliaExplained the importance of certainty in the time provisions of the SOP Act.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 2Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 5Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 10Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 10(3)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 11Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 11(1)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 11(3)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 12Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 12(5)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 13Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 13(3)(a)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Adjudication Determination
  • Building and Construction Industry Security of Payment Act
  • Payment Claim
  • Payment Response
  • Dispute Settlement Period
  • Interim Certificate
  • Progress Payment
  • Variation Agreement

15.2 Keywords

  • adjudication
  • SOP Act
  • construction
  • payment claim
  • payment response
  • dispute settlement period
  • Singapore

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Security of Payment
  • Adjudication
  • Contractual Interpretation