UES Holdings v Grouteam: Setting Aside Adjudication Determination for Out-of-Time Payment Claim under SOPA

In UES Holdings Pte Ltd v Grouteam Pte Ltd, the High Court of Singapore considered an application by UES Holdings to set aside an adjudication determination under the Building and Construction Industry Security of Payment Act. UES Holdings, the plaintiff, argued that Grouteam's payment claim was defective and served out of time. The court, presided over by Justice Quentin Loh, found that the payment claim was indeed served out of time, violating a mandatory condition of the Act. Consequently, the court allowed UES Holdings' application and set aside the adjudication determination.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Plaintiff's application allowed and the Adjudication Determination set aside.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

UES Holdings sought to set aside an adjudication determination, arguing Grouteam's payment claim was served out of time. The High Court allowed the application.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
UES Holdings Pte LtdPlaintiffCorporationApplication AllowedWon
GROUTEAM PTE LTDDefendantCorporationAdjudication Determination Set AsideLost

3. Judges

Judge NameTitleDelivered Judgment
Quentin LohJudgeYes

4. Counsels

4. Facts

  1. UES Holdings was engaged as a main contractor by Changi Airport Group for a project.
  2. UES Holdings entered into a sub-contract with Grouteam to carry out civil, structural, and architectural works.
  3. Grouteam served Payment Claim No. 18 on UES Holdings on 20 April 2015.
  4. UES Holdings did not provide a payment response, so Grouteam served a notice of intention to apply for adjudication.
  5. UES Holdings then issued Payment Response No. 18 on 20 May 2015.
  6. The adjudicator ordered UES Holdings to pay Grouteam $2,905,683.89.
  7. UES Holdings applied to set aside the adjudication determination on three grounds.

5. Formal Citations

  1. UES Holdings Pte Ltd v Grouteam Pte Ltd, Originating Summons No 649 of 2015, [2015] SGHC 275

6. Timeline

DateEvent
Sub-contract dated
Defendant served Payment Claim No. 18 on the Plaintiff
Defendant served a notice of intention to apply for adjudication and lodged an adjudication application with the Singapore Mediation Centre
Plaintiff issued Payment Response No. 18
The SMC served a copy of the Adjudication Application on the Plaintiff
Adjudicator rendered his determination
Judgment reserved

7. Legal Issues

  1. Defective Payment Claim
    • Outcome: The court found that the payment claim was served out of time, violating section 10(2)(a) of the Building and Construction Industry Security of Payment Act.
    • Category: Substantive
    • Sub-Issues:
      • Service of payment claim out of time
  2. Defective Notice of Intention and Adjudication Application
    • Outcome: The court found that the Notice of Intention and Adjudication Application were served out of time.
    • Category: Procedural
    • Sub-Issues:
      • Service of notice of intention out of time
      • Service of adjudication application out of time
  3. Defective Adjudication Application
    • Outcome: The court found that the Defendant did not fail to provide extracts of the terms or conditions of the contract that are relevant to the payment claim dispute as required under 13(3)(c) of the Act read with reg 7(2)(d) of the Regulations.
    • Category: Procedural
    • Sub-Issues:
      • Failure to include relevant extracts of contract terms

8. Remedies Sought

  1. Setting aside of Adjudication Determination

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Construction Litigation
  • Commercial Litigation
  • Adjudication

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Jurong Engineering Ltd v Paccan Building Technology Pte LtdHigh CourtYes[1999] 2 SLR(R) 849SingaporeCited for the principle that a document may be incorporated into a contract mutatis mutandis without express use of the words 'mutatis mutandis'.
Lee Wee Lick Terence (alias Li Weili Terence) v Chua Say Eng (formerly trading as Weng Fatt Construction Engineering) and another appealCourt of AppealYes[2013] 1 SLR 401SingaporeCited for the principle that the court may set aside an adjudication determination if the claimant has not complied with a mandatory provision of the Act.
Lau Fook Hoong Adam v GTH Engineering & Construction Pte LtdHigh CourtYes[2015] SGHC 141SingaporeCited for the view that section 10(2)(a) of the Act is framed in mandatory terms and must be observed strictly.
W Y Steel Construction Pte Ltd v Osko Pte LtdCourt of AppealYes[2013] 3 SLR 380SingaporeCited for the principle that parties enter into an expedited dispute resolution process under the Act, with strict deadlines for payment claims and responses.
Citiwall Safety Glass Pte Ltd v Mansource Interior Pte LtdCourt of AppealYes[2015] SGCA 42SingaporeCited for reaffirming the view that timelines under the SOPA have to be strictly complied with.
Newcon Builders v Sino New Steel Pte LtdHigh CourtYes[2015] SGHC 226SingaporeCited for highlighting that if a party wishes to avail itself of the statutory scheme for speedy payment, it has to ensure that the timelines, which is a key feature of the scheme, must be complied with.
Chin Ivan v H P Construction & Engineering Pte LtdCourt of AppealYes[2015] SGCA 14SingaporeCited for the principle that litigation and arbitration are still available even if the statutory scheme cannot be invoked.
Chai Cher Watt (trading as Chuang Aik Engineering Works) v SDL Technologies Pte Ltd and another appealCourt of AppealYes[2012] 1 SLR 152SingaporeCited for the principle of what amounts to an unequivocal representation that a party will not insist upon its legal rights.
YTL Construction (S) Pte Ltd v Balanced Engineering & Construction Pte LtdHigh CourtYes[2014] SGHC 142SingaporeCited as an example where the Adjudication Determination was set aside because the Notice of Intention and Adjudication Application had been served out of time.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)Singapore
Building and Construction Industry Security of Payment Act, s 10(2)(a)Singapore
Building and Construction Industry Security of Payment Act, s 12(5)Singapore
Building and Construction Industry Security of Payment Act, s 13(3)(c)Singapore
Goods and Services Tax Act (Cap 117A, 2005 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Adjudication Determination
  • Payment Claim
  • Payment Response
  • Sub-contract
  • Main Contract
  • Security of Payment Act
  • PSSCOC
  • SOCN
  • Preliminaries

15.2 Keywords

  • Construction
  • Adjudication
  • Payment Claim
  • Security of Payment Act
  • Singapore

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Adjudication
  • Contract Law