AMZ v AXX: Breach of Contract, Repudiatory Breach, and Damages in Oil Supply Agreement Arbitration

In AMZ v AXX, the Singapore High Court addressed an application by AMZ to set aside an arbitration award. AMZ, the claimant, sought damages for AXX's alleged repudiatory breach of a contract to supply Dar Blend crude oil. The tribunal found one breach related to the letter of credit, but dismissed the claim, as it did not amount to a repudiatory breach and AMZ did not pursue an alternative claim for damages. Coomaraswamy J. dismissed AMZ's application, finding no procedural defects or prejudice, and AMZ's appeal to the Court of Appeal was dismissed.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Claimant's application to set aside the tribunal's award was dismissed with costs.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Singapore High Court case concerning a breach of contract claim in an oil supply agreement, focusing on repudiatory breach and damages.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
AMZPlaintiff, ApplicantCorporationApplication dismissedLost
AXXDefendant, RespondentCorporationApplication dismissedWon

3. Judges

Judge NameTitleDelivered Judgment
Vinodh CoomaraswamyJudgeYes

4. Counsels

4. Facts

  1. AMZ and AXX entered into a Supply Contract for the sale of Dar Blend crude oil.
  2. The Supply Contract stipulated a delivery window between 10 January 2011 and 20 January 2011.
  3. AXX was obligated to open an irrevocable letter of credit by 16 December 2010.
  4. AXX failed to secure a crude oil import licence before the delivery window.
  5. AMZ chartered the Tantive IV to transport the Dar Blend but held it in Alderaan.
  6. AMZ claimed AXX's breaches amounted to a repudiatory breach of contract.
  7. The Tribunal found AXX breached the contract by failing to issue a letter of credit.

5. Formal Citations

  1. AMZ v AXX, , [2015] SGHC 283

6. Timeline

DateEvent
Supply Contract signed
Owen sent a chaser to the defendant’s representative inquiring about the status of the Supply Contract
Defendant returned the signed execution pages of the Supply Contract to the plaintiff
Deadline for defendant to open a letter of credit
Dar Blend loaded onto the Tantive IV at Port Sudan
Dar Blend loaded onto the Tantive IV at Port Sudan
Tantive IV arrived in Alderaan
Defendant confirmed failure to secure crude oil import licence
Start of delivery window
Plaintiff put the defendant on notice that the plaintiff considered the defendant to be in repudiatory breach of the Supply Contract
End of delivery window
Plaintiff notified defendant it had not found another buyer
Plaintiff sold the Dar Blend to a company
Plaintiff demanded that the defendant pay within one week the sum of US$10.17m as compensation for the defendant’s breach of the Supply Contract
Plaintiff commenced arbitration against the defendant
Tribunal was duly constituted
Jurisdictional hearing took place
Jurisdictional hearing took place
Tribunal notified the parties that it was disinclined at that stage to accept the defendant’s jurisdictional objection
Hearing on the merits took place
Hearing on the merits took place
Hearing on the merits took place
Tribunal issued its award
Decision Date

7. Legal Issues

  1. Breach of Contract
    • Outcome: The Tribunal found one breach of contract to have been established but found that the other two alleged breaches are not breaches at all.
    • Category: Substantive
    • Sub-Issues:
      • Failure to provide letter of credit
      • Failure to obtain crude import licence
      • Failure to take delivery of consignment
  2. Repudiatory Breach
    • Outcome: The tribunal held that the claimant was unable to rely on the lone breach of contract as being a repudiatory breach of contract.
    • Category: Substantive
  3. Setting Aside Arbitration Award
    • Outcome: The court dismissed the claimant's application to set aside the tribunal's award.
    • Category: Procedural
    • Sub-Issues:
      • Breach of natural justice
      • Dealing with matters outside the scope of submission to arbitration
      • Procedure not in accordance with parties’ agreement
    • Related Cases:
      • John Holland Pty Ltd (formerly known as John Holland Construction & Engineering Pty Ltd) v Toyo Engineering Corp (Japan) [2001] 1 SLR(R) 443
      • Soh Beng Tee & Co v Fairmont Development Pte Ltd [2007] 3 SLR(R) 86
      • L W Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd and another appeal [2013] 1 SLR 125
      • Jeyaretnam Joshua Benjamin v Lee Kuan Yew [1992] 1 SLR(R) 791
      • Re Shankar Alan s/o Anant Kulkarni [2007] 1 SLR(R) 85
      • Zermalt Holdings SA v Nu-Life Upholstery Repairs Ltd [1985] 2 EGLR 14
      • Interbulk Ltd v Aiden Shipping Co Ltd (The Vimeira) [1984] 2 Lloyd’s Rep 66
      • Koh Brothers Building and Civil Engineering Contractor Pte Ltd v Scotts Development (Saraca) Pte Ltd [2002] 2 SLR(R) 1063
      • Front Row Investment Holdings (Singapore) Pte Ltd v Daimler South East Asia Pte Ltd [2010] SGHC 80
      • Laing O’Rourke Australia Construction Pty Ltd v H&M Engineering & Construction Pty Ltd [2010] NSWSC 818
      • CRW Joint Operation v PT Perusahaan Gas Negara (Persero) TBK [2011] 4 SLR 305
      • PT Asuransi Jasa Indonesia (Persero) v Dexia Bank SA [2007] 1 SLR(R) 597

8. Remedies Sought

  1. Monetary Damages
  2. Setting Aside of Arbitral Award

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Commercial Arbitration
  • Commercial Litigation

11. Industries

  • Oil and Gas

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Hadley v BaxendaleN/AYesHadley v Baxendale (1854) 9 Exch 341; 156 ER 145N/ACited for the principle of recoverability of hedging losses as damages.
John Holland Pty Ltd (formerly known as John Holland Construction & Engineering Pty Ltd) v Toyo Engineering Corp (Japan)N/AYesJohn Holland Pty Ltd (formerly known as John Holland Construction & Engineering Pty Ltd) v Toyo Engineering Corp (Japan) [2001] 1 SLR(R) 443SingaporeCited for the requirements to set aside an arbitral tribunal award under s 24(b) of the International Arbitration Act.
Soh Beng Tee & Co v Fairmont Development Pte LtdN/AYesSoh Beng Tee & Co v Fairmont Development Pte Ltd [2007] 3 SLR(R) 86SingaporeCited for the requirements to set aside an arbitral tribunal award under s 24(b) of the Act and the test of actual prejudice.
L W Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd and another appealN/AYesL W Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd and another appeal [2013] 1 SLR 125SingaporeCited for the requirements to set aside an arbitral tribunal award under s 24(b) of the Act and the test of actual prejudice.
Jeyaretnam Joshua Benjamin v Lee Kuan YewN/AYesJeyaretnam Joshua Benjamin v Lee Kuan Yew [1992] 1 SLR(R) 791SingaporeCited for the rule against bias and apparent bias.
Re Shankar Alan s/o Anant KulkarniN/AYesRe Shankar Alan s/o Anant Kulkarni [2007] 1 SLR(R) 85SingaporeCited for the rule against bias and apparent bias.
Zermalt Holdings SA v Nu-Life Upholstery Repairs LtdN/AYesZermalt Holdings SA v Nu-Life Upholstery Repairs Ltd [1985] 2 EGLR 14N/ACited for the principle that a tribunal should not base its decision on a point not submitted to it or a matter not argued before it.
Interbulk Ltd v Aiden Shipping Co Ltd (The Vimeira)N/AYesInterbulk Ltd v Aiden Shipping Co Ltd (The Vimeira) [1984] 2 Lloyd’s Rep 66N/ACited for the principle that a tribunal should not base its decision on a point not submitted to it or a matter not argued before it.
Koh Brothers Building and Civil Engineering Contractor Pte Ltd v Scotts Development (Saraca) Pte LtdN/AYesKoh Brothers Building and Civil Engineering Contractor Pte Ltd v Scotts Development (Saraca) Pte Ltd [2002] 2 SLR(R) 1063SingaporeCited for the principle that a tribunal should not base its decision on a point not submitted to it or a matter not argued before it.
Front Row Investment Holdings (Singapore) Pte Ltd v Daimler South East Asia Pte LtdHigh Court of SingaporeYesFront Row Investment Holdings (Singapore) Pte Ltd v Daimler South East Asia Pte Ltd [2010] SGHC 80SingaporeCited for the principle that a tribunal cannot disregard an argument or a submission made by a party without directing its judicial mind to the merits of that argument or submission through an active process of intellectual reasoning.
Laing O’Rourke Australia Construction Pty Ltd v H&M Engineering & Construction Pty LtdSupreme Court of New South WalesYesLaing O’Rourke Australia Construction Pty Ltd v H&M Engineering & Construction Pty Ltd [2010] NSWSC 818AustraliaCited for the principle that a tribunal cannot disregard an argument or a submission made by a party without directing its judicial mind to the merits of that argument or submission through an active process of intellectual reasoning.
CRW Joint Operation v PT Perusahaan Gas Negara (Persero) TBKN/AYesCRW Joint Operation v PT Perusahaan Gas Negara (Persero) TBK [2011] 4 SLR 305SingaporeCited for the principle that a tribunal is not required to refer every issue which falls for decision to the parties for submissions.
PT Asuransi Jasa Indonesia (Persero) v Dexia Bank SAN/AYesPT Asuransi Jasa Indonesia (Persero) v Dexia Bank SA [2007] 1 SLR(R) 597SingaporeCited for the two questions the Court must consider when considering whether to set aside an award under Article 34(2)(a)(iii) of the Model Law.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
International Arbitration Act (Cap 143A, 2002 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Dar Blend
  • Supply Contract
  • Buy-back Contract
  • Letter of Credit
  • Repudiatory Breach
  • Crude Oil Import Licence
  • Tantive IV
  • Hedging Losses
  • Ex Ship
  • Payment Undertaking

15.2 Keywords

  • arbitration
  • breach of contract
  • oil supply
  • repudiatory breach
  • damages
  • Singapore High Court

17. Areas of Law

16. Subjects

  • Arbitration
  • Contract Law
  • International Trade
  • Oil and Gas