CAA Technologies v Newcon Builders: Termination of Sub-Contract & Compensation for Delays in Construction Project
CAA Technologies Pte Ltd appealed against the High Court's decision in favor of Newcon Builders Pte Ltd, regarding the termination of a sub-contract for the design, production, and installation of pre-cast concrete hollow core slabs for a medical technology hub project. The Court of Appeal, with Judges Judith Prakash JA, Tay Yong Kwang JA, and Steven Chong JA, found that Newcon was justified in terminating the sub-contract due to CAA's breaches of contract. However, the court allowed the appeal in part, setting aside the order for CAA to pay $407,000 to Newcon for liquidated damages paid to JTC.
1. Case Overview
1.1 Court
Court of Appeal of the Republic of Singapore1.2 Outcome
Appeal allowed in part. The order for CAA to pay $407,000 to Newcon for liquidated damages paid to JTC was set aside.
1.3 Case Type
Civil
1.4 Judgment Type
Judgment
1.5 Jurisdiction
Singapore
1.6 Description
Appeal regarding termination of a sub-contract for pre-cast concrete hollow core slabs. The court examined breaches of contract terms and damages.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
CAA Technologies Pte Ltd | Appellant | Corporation | Appeal allowed in part | Partial | Edwin Lee Peng Khoon, Jennifer Fong Lee Cheng, Irving Choh Thian Chee, Christine Chuah Hui Fen, Kor Wan Wen Melissa |
Newcon Builders Pte Ltd | Respondent | Corporation | Partial Win | Partial | Lok Vi Ming, Joseph Lee Sien Liang, Tang Jin Sheng |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Judith Prakash | Judge of Appeal | No |
Tay Yong Kwang | Judge of Appeal | No |
Steven Chong | Judge of Appeal | Yes |
4. Counsels
Counsel Name | Organization |
---|---|
Edwin Lee Peng Khoon | Eldan Law LLP |
Jennifer Fong Lee Cheng | Eldan Law LLP |
Irving Choh Thian Chee | Optimus Chambers LLC |
Christine Chuah Hui Fen | Optimus Chambers LLC |
Kor Wan Wen Melissa | Optimus Chambers LLC |
Lok Vi Ming | LVM Law Chambers LLC |
Joseph Lee Sien Liang | LVM Law Chambers LLC |
Tang Jin Sheng | LVM Law Chambers LLC |
4. Facts
- Newcon was the main contractor for a medical technology hub project in Jurong.
- Newcon sub-contracted the production and delivery of HCS to CAA via a Letter of Intent.
- The Letter of Intent required CAA to follow the site progress and revisions to the construction programme schedule.
- A Letter of Acceptance was sent to CAA but never signed.
- CAA failed to meet the initial delivery schedules for the HCS.
- Newcon issued revised delivery schedules, but CAA still failed to comply.
- Newcon terminated the sub-contract with CAA due to the delays.
5. Formal Citations
- CAA Technologies Pte Ltd v Newcon Builders Pte Ltd, Civil Appeal No 63 of 2016, [2017] SGCA 53
6. Timeline
Date | Event |
---|---|
Letter of Intent signed between Newcon and CAA. | |
CAA signed and returned the Letter of Intent. | |
Newcon sent the Letter of Acceptance to CAA for signature. | |
Newcon asked CAA to submit items before commencing production of HCS. | |
First casting of the HCS took place. | |
Newcon sent CAA an email containing a revised schedule for the delivery of the HCS. | |
Delivery of the HCS commenced. | |
HCS for area 2a were delivered. | |
Newcon sent CAA another email containing a proposed delivery schedule. | |
Meeting took place between Newcon and CAA. | |
Newcon sent CAA an email to put CAA on notice that Newcon was ready to receive the HCS at area 2a but that CAA had failed to deliver. | |
Newcon emailed CAA a letter of termination. | |
CAA commenced Suit No 1063 of 2013 against Newcon. | |
Interim final payment certificate No 9 issued by Jurong Consultants Pte Ltd to Newcon. | |
Judgment reserved. | |
Judgment delivered. |
7. Legal Issues
- Breach of Contract
- Outcome: The court found that CAA breached clause 2 of the Letter of Intent and that this breach deprived Newcon of substantially the whole benefit of the Sub-Contract.
- Category: Substantive
- Sub-Issues:
- Failure to follow site progress
- Failure to adhere to construction programme schedule
- Failure to proceed with due diligence and expedition
- Related Cases:
- [2016] SGHC 246
- [2009] 4 SLR(R) 602
- [2007] 4 SLR(R) 413
- Termination of Contract
- Outcome: The court held that Newcon was justified in terminating the Sub-Contract due to CAA's breaches.
- Category: Substantive
- Sub-Issues:
- Justification for termination
- Effect of notice of termination
- Repudiatory breach
- Related Cases:
- [2009] 4 SLR(R) 602
- [2007] 4 SLR(R) 413
- Implied Terms
- Outcome: The court expressed reservations about implying terms of due diligence and expedition in construction contracts, finding it unnecessary in this case.
- Category: Substantive
- Sub-Issues:
- Due diligence
- Expedition
- Time is of the essence
- Related Cases:
- [2013] 4 SLR 193
- Damages
- Outcome: The court set aside the order for CAA to pay $407,000 in liquidated damages, finding that Newcon had not proven that CAA's breaches were the sole cause of the delay.
- Category: Substantive
- Sub-Issues:
- Causation
- Liquidated damages
- Reliance costs
8. Remedies Sought
- Damages for breach of contract
- Payments accrued up to the date of termination
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Construction Contracts
- Sub-contracts
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
CAA Technologies Pte Ltd v Newcon Builders Pte Ltd | High Court | Yes | [2016] SGHC 246 | Singapore | The appeal arises from the decision of this case. |
Alliance Concrete Singapore Pte Ltd v Comfort Resources Pte Ltd | Court of Appeal | Yes | [2009] 4 SLR(R) 602 | Singapore | Cited for the principle that an innocent party can rely on any existing ground for termination unless waiver/estoppel applies or the breaching party could have rectified the situation. |
RDC Concrete Pte Ltd v Sato Kogyo (S) Pte Ltd | Court of Appeal | Yes | [2007] 4 SLR(R) 413 | Singapore | Cited for the test to determine whether a term is a condition of a contract and for the analysis of repudiatory breach. |
Man Financial (S) Pte Ltd (formerly known as E D & F Man International (S) Pte Ltd) v Wong Bark Chuan David | Court of Appeal | Yes | [2008] 1 SLR(R) 663 | Singapore | Cited for the principle that courts are more likely to classify contractual terms as conditions in mercantile transactions, especially those relating to timing. |
Lim Chin San Contractors Pte Ltd v Sanchoon Builders Pte Ltd | High Court | Yes | [2005] SGHC 227 | Singapore | Cited regarding issues of reasonableness typically arise for determination where the revisions to the construction programme seek to “accelerate” and thereby shorten the original schedule. |
Sembcorp Marine Ltd v PPL Holdings Pte Ltd and another and another appeal | Court of Appeal | Yes | [2013] 4 SLR 193 | Singapore | Cited for the test for implication of terms in Singapore law. |
Leander Construction Ltd v Mullalley and Company Ltd | Technology and Construction Court | Yes | [2011] EWHC 3449 (TCC) | England and Wales | Cited for the discussion on the implication of a term of due diligence and expedition in the construction context. |
Greater London Council v Cleveland Bridge & Engineering Company Ltd | N/A | Yes | (1984) 34 BLR 57 | N/A | The Judge expressly noted that this case did not support the proposition of implying a term of due diligence. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Hollow core slabs
- Letter of Intent
- Letter of Acceptance
- Construction programme schedule
- Delivery schedule
- Termination
- Liquidated damages
- Due diligence
- Expedition
15.2 Keywords
- construction
- contract
- sub-contract
- termination
- damages
- hollow core slabs
- delay
- letter of intent
- letter of acceptance
16. Subjects
- Building and Construction
- Contract Law
- Civil Procedure
17. Areas of Law
- Building and Construction Law
- Contract Law