SH Design & Build Pte Ltd v BD Cranetech Pte Ltd: SOP Act Adjudication & Performance Bond
In SH Design & Build Pte Ltd v BD Cranetech Pte Ltd, the High Court of Singapore heard an application by SH Design & Build Pte Ltd to set aside an adjudication determination made under the Building and Construction Industry Security of Payment Act in favor of BD Cranetech Pte Ltd. The court, presided over by Justice Tan Siong Thye, dismissed the application, holding that the adjudicator had not exceeded his jurisdiction by considering bond proceeds and that the omission of the owner's name and address in the adjudication application was not fatal. The court also dismissed the application for a stay of enforcement of the adjudication determination pending arbitration.
1. Case Overview
1.1 Court
High Court of the Republic of Singapore1.2 Outcome
Application dismissed.
1.3 Case Type
Building and Construction Law
1.4 Judgment Type
Oral Judgment
1.5 Jurisdiction
Singapore
1.6 Description
SH Design & Build's application to set aside an adjudication determination under the SOP Act was dismissed. The court addressed cross-contract set-off and Owner omission.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
SH Design & Build Pte Ltd | Plaintiff | Corporation | Application dismissed | Lost | Chuah Chee Kian Christopher, Koh Swee Yen, Lee Hwai Bin, Tay Bing Wei, Sheryl Ang |
BD Cranetech Pte Ltd | Defendant | Corporation | Judgment for Defendant | Won | Yam Wern-Jhien |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Tan Siong Thye | Judge | Yes |
4. Counsels
Counsel Name | Organization |
---|---|
Chuah Chee Kian Christopher | WongPartnership LLP |
Koh Swee Yen | WongPartnership LLP |
Lee Hwai Bin | WongPartnership LLP |
Tay Bing Wei | WongPartnership LLP |
Sheryl Ang | WongPartnership LLP |
Yam Wern-Jhien | Rajah & Tann Singapore LLP |
4. Facts
- The Plaintiff is the main contractor for the construction of an integrated logistics hub.
- The Defendant is a specialist subcontractor engaged by the Plaintiff for the design, supply, installation and commissioning of overhead cranes.
- The Plaintiff entered into an agreement with the Defendant on 22 February 2013 for the works relating to the Development.
- The Defendant procured an on-demand performance bond dated 21 May 2013 for up to the sum of $1,293,600.
- Pursuant to a deed of assignment dated 22 December 2015, the Plaintiff assigned to the Owner all of its rights, title, interest and benefit under the Subcontract, including the Performance Bond.
- On 23 March 2016, MSIG made full payment of the Bond Proceeds to the Owner.
- On 27 June 2016, the Defendant lodged an Adjudication Application against the Plaintiff based on its purported entitlement to outstanding payment for work done under the Subcontract.
5. Formal Citations
- SH Design & Build Pte Ltd v BD Cranetech Pte Ltd, Originating Summons No 290 of 2018, [2018] SGHC 133
6. Timeline
Date | Event |
---|---|
Owner contracted with Defendant for overhead cranes | |
Plaintiff and Defendant entered into Subcontract | |
Defendant procured Performance Bond | |
Plaintiff assigned rights to Owner | |
Owner terminated Defendant's employment | |
Owner demanded payment of Bond Proceeds from MSIG | |
Owner issued further demand to MSIG | |
Owner commenced proceedings in Suit No 12 of 2016 | |
Defendant filed Originating Summons No 4 of 2016 | |
MSIG paid Bond Proceeds to Owner | |
Defendant served payment claim on Plaintiff | |
Plaintiff provided payment response | |
Defendant lodged Adjudication Application | |
Plaintiff lodged adjudication response | |
Adjudication conference held | |
Adjudicator issued the AD | |
Plaintiff requested amendments to the AD | |
Adjudicator declined to amend the AD | |
Defendant obtained Order of Court to enforce AD | |
Order of Court served on Plaintiff | |
Plaintiff made application in OS 290/2018 to set aside the AD | |
Hearing for OS 290/2018 | |
Oral judgment delivered |
7. Legal Issues
- Exceeding Jurisdiction
- Outcome: The court held that the Adjudicator had not exceeded his jurisdiction.
- Category: Jurisdictional
- Sub-Issues:
- Wrongly taking into account the amount received under the performance bond
- Reversing the decision of Ramesh JC in OS 4/2016
- Allowing the Defendant to rectify the error in the Adjudication Application
- Cross-Contract Set-Off
- Outcome: The court held that accounting for the Bond Proceeds in assessing the Adjudicated Amount was not akin to a cross-contract set-off.
- Category: Substantive
- Validity of Adjudication Application
- Outcome: The court held that the initial omission of the Owner’s name and service address from the Adjudication Application was not sufficient basis for the AD to be set aside.
- Category: Procedural
- Sub-Issues:
- Omission of Owner's name and service address
- Power to allow amendments to Adjudication Application
8. Remedies Sought
- Setting aside of adjudication determination
- Stay of enforcement of adjudication determination
9. Cause of Actions
- Outstanding payment for work done under the Subcontract
10. Practice Areas
- Construction Law
- Commercial Litigation
- Arbitration
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Civil Tech Pte Ltd v Hua Rong Engineering Pte Ltd | Court of Appeal | Yes | [2018] 1 SLR 584 | Singapore | Cited for the principle that each adjudication under the SOP Act should relate only to the contract upon which the payment claim is founded, and should not take into account cross-claims from other contracts. |
Hua Rong Engineering Pte Ltd v Civil Tech Pte Ltd | High Court | Yes | [2018] 3 SLR 778 | Singapore | Cited for the reasoning that the spirit and purpose of the SOP Act would militate against allowing cross-contract claims to be considered in an adjudication. |
Comfort Management Pte Ltd v OGSP Engineering Pte Ltd | Court of Appeal | Yes | [2018] SGCA 19 | Singapore | Cited for the principle that s 17(3) of the SOP Act imposes a mandatory obligation on the adjudicator to consider all matters listed in that provision. |
Rong Shun Engineering & Construction Pte Ltd v CP Ong Construction Pte Ltd | High Court | Yes | [2017] 4 SLR 359 | Singapore | Cited for the proposition that an adjudicator can only award sums that were specifically included in the payment claim, but distinguished because a payment response was lodged in the present case. |
Cargill International S.A. and Another v Bangladesh Sugar and Food Industries Corporation | Unknown | Yes | [1996] 4 All ER 563 | England | Cited for the principle that a performance bond is a form of security and the issuance of such a bond does not mean that the holder of the bond has an absolute right to keep the proceeds from the bond permanently. |
Comdel Commodities Ltd v Siporex Trade SA | English Court of Appeal | Yes | [1997] 1 Lloyd’s Rep 424 | England | Cited for approving the analysis in Cargill, stating that if the amount of the bond is more than enough to satisfy the seller’s claim for damages, the buyer can recover from the seller the amount of the bond which exceeds the seller’s damages. |
Pun Serge v Joy Head Investments Ltd | High Court | Yes | [2010] 4 SLR 478 | Singapore | Cited for approving the principle in Cargill. |
W Y Steel Construction Pte Ltd v Osko Pte Ltd | Court of Appeal | Yes | [2013] 3 SLR 380 | Singapore | Cited for the principle that adjudications under the SOP Act are meant to provide parties only with temporary finality. |
Bocotra Construction Pte Ltd and others v Attorney-General | Unknown | Yes | [1995] 2 SLR(R) 262 | Singapore | Cited for the principle that the court may only grant an injunction to restrain the calling of an otherwise unconditional performance bond where there is fraud or unconscionability. |
SEF Construction Pte Ltd v Skoy Connected Pte Ltd | High Court | Yes | [2010] 1 SLR 733 | Singapore | Cited for setting out the basic requirements that must exist for an adjudication determination to be valid. |
Kingsford Construction Pte Ltd v A Deli Construction Pte Ltd | High Court | Yes | [2017] SGHC 174 | Singapore | Cited for the principle that when striking a balance between the claimant’s entitlement to receive quick payment and the respondent’s entitlement to recover the money upon subsequent dispute resolution, the overall objective of the SOP Act, which is to ensure cash flow in the construction industry, should ultimately be given more weight. |
Erinford Properties Ltd and Another v Cheshire County Council | Unknown | Yes | [1974] 2 WLR 749 | England | Cited for the principle that where the application is for an injunction pending an appeal, the question is whether the judgment that has been given is one upon which the successful party ought to be free to act despite the pendency of an appeal. |
Tan Soo Leng David v Wee, Satku & Kumar Pte Ltd and another | Unknown | Yes | [1993] 2 SLR(R) 741 | Singapore | Cited as accepting the Erinford principle as good law in Singapore. |
Sin Herh Construction Pte Ltd v Hyundai Engineering & Construction Co Ltd and another | High Court | Yes | [2017] SGHC 3 | Singapore | Cited as accepting the Erinford principle as good law in Singapore. |
13. Applicable Rules
Rule Name |
---|
Rules of Court (Cap 322, R 5, 2014 Rev Ed) |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Adjudication Determination
- Building and Construction Industry Security of Payment Act
- Performance Bond
- Payment Claim
- Payment Response
- Adjudicated Amount
- Subcontract
- Deed of Assignment
- Originating Summons
- Arbitration
15.2 Keywords
- adjudication
- SOP Act
- performance bond
- construction
- payment
- security of payment
16. Subjects
- Construction Dispute
- Adjudication
- Security of Payment
- Performance Bonds
17. Areas of Law
- Building and Construction Law
- Contract Law
- Civil Procedure
- Arbitration Law