CHL Construction v Yangguang Group: SOPA & Contract Termination

In CHL Construction Pte Ltd v Yangguang Group Pte Ltd, the Singapore High Court addressed whether contractual provisions relating to Security of Payment Act (SOPA) timelines survive the termination of a construction contract. The court heard an application by CHL Construction Pte Ltd to set aside an Amended Adjudication Determination. Justice Chan Seng Onn held that the contractual timelines for payment claims under SOPA must be adhered to even after the contract has been terminated and set aside the adjudication determination.

1. Case Overview

1.1 Court

High Court of the Republic of Singapore

1.2 Outcome

The Amended Adjudication Determination was set aside.

1.3 Case Type

Construction

1.4 Judgment Type

Judgment

1.5 Jurisdiction

Singapore

1.6 Description

Singapore High Court case concerning the Building and Construction Industry Security of Payment Act (SOPA) and the effect of contract termination on payment claim timelines.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
CHL Construction Pte LtdPlaintiffCorporationApplication allowedWon
Yangguang Group Pte LtdDefendantCorporationDetermination set asideLost

3. Judges

Judge NameTitleDelivered Judgment
Chan Seng OnnJudgeYes

4. Counsels

4. Facts

  1. CHL Construction engaged Yangguang Group as a sub-contractor for an "Architectural Wet Trade Works" project for $443,921.87.
  2. The sub-contractor completed the works on 9 July 2018, and a Certificate of Substantial Completion was received on 10 July 2018.
  3. The contract was terminated on 20 July 2018.
  4. On 30 August 2018, the sub-contractor served Progress Claim 10, claiming for works done until 30 August 2018 and for the release of half of the retention monies.
  5. The main contractor disputed the amount claimed, and the sub-contractor submitted an Adjudication Application on 24 September 2018.
  6. The Amended Adjudication Determination released on 22 October 2018 determined that $95,704.37 was payable by the main contractor to the sub-contractor.
  7. Clause 37 of the contract stipulated that the sub-contractor had to withhold its penultimate payment claim until three months after the Certificate of Substantial Completion had been received.

5. Formal Citations

  1. CHL Construction Pte Ltd v Yangguang Group Pte Ltd, Originating Summons No 1465 of 2018, [2019] SGHC 62

6. Timeline

DateEvent
Sub-Contract signed
Sub-Contractor completed the works
Certificate of Substantial Completion received
Contract terminated
Progress Claim 10 served
Adjudication Application submitted
Chua Shueh Er’s 1st Affidavit
Amended Adjudication Determination released
Hearing
Hearing
Judgment reserved

7. Legal Issues

  1. Contravention of section 10(2)(a) of the Building and Construction Industry Security of Payment Act
    • Outcome: The court held that PC10 was served too early, in breach of s 10(2)(a) SOPA, and the AD was invalid.
    • Category: Substantive
    • Related Cases:
      • [2016] 5 SLR 1011
  2. Whether clause 37 is voided by section 36(2) of the Building and Construction Industry Security of Payment Act
    • Outcome: The court held that clause 37 is not voided by s 36(2) SOPA.
    • Category: Substantive
    • Related Cases:
      • [2012] QCA 150

8. Remedies Sought

  1. Setting aside of the Adjudication Determination

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Construction Law
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Grouteam Pte Ltd v UES Holdings Pte LtdHigh CourtYes[2016] 5 SLR 1011SingaporeCited for the principle that breach of a mandatory provision of SOPA renders an adjudication determination invalid.
Tienrui Design & Construction Pte Ltd v G & Y Trading and Manufacturing Pte LtdHigh CourtYes[2015] 5 SLR 852SingaporeCited to explain the dual-track regime for construction claims under SOPA.
AET Pte Ltd v AEU Pte LtdSingapore Court of AppealYes[2010] SCAdjR 771SingaporeCited as a prior decision holding that contractual provisions relating to timelines survive termination for the purposes of claims under SOPA.
Taisei Corp v Doo Ree Engineering & Trading Pte LtdHigh CourtYes[2009] SGHC 156SingaporeCited as a prior decision holding that contractual provisions relating to timelines survive termination for the purposes of claims under SOPA.
John Goss Projects Pty Ltd v Leighton Contractors Pty LtdNew South Wales Supreme CourtYes[2006] 66 NSWLR 707AustraliaCited for the principle of balancing competing considerations when determining whether a contractual clause offends s 36(2) SOPA.
John Holland Pty Ltd v Coastal Dredging & Construction Pty Limited & OrsQueensland Court of AppealNo[2012] QCA 150AustraliaCited to show an example of a clause that was void under Queensland’s equivalent of s 36(2) SOPA.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)Singapore
Building and Construction Industry Security of Payment Act s 10(2)Singapore
Building and Construction Industry Security of Payment Act s 2Singapore
Building and Construction Industry Security of Payment Act s 5Singapore
Building and Construction Industry Security of Payment Act s 36(2)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Building and Construction Industry Security of Payment Act
  • SOPA
  • Progress Claim
  • Payment Claim
  • Adjudication Determination
  • Certificate of Substantial Completion
  • Termination of Contract
  • Penultimate Payment Claim
  • Retention Monies

15.2 Keywords

  • SOPA
  • Security of Payment Act
  • Construction
  • Payment Claim
  • Adjudication
  • Contract Termination

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Arbitration
  • Contract Law