Zhong Kai Construction v Diamond Glass: Liquidated Damages & SOPA Dispute
In Zhong Kai Construction Co Pte Ltd v Diamond Glass Enterprise Pte Ltd, the General Division of the High Court of Singapore heard a case involving a claim by Zhong Kai Construction against Diamond Glass for liquidated damages due to delays, costs for replacement and rectification works, and to overturn an adjudicated amount under the Building and Construction Industry Security of Payment Act (SOPA). Diamond Glass counterclaimed for payments due under variation orders, unpaid sums under the subcontract, and legal costs associated with the adjudication determination. The court allowed Zhong Kai's claims for liquidated damages and replacement/rectification works in part, set aside three of the variation orders, allowed one of Diamond Glass's claims for a variation order, and dismissed Diamond Glass's other claims.
1. Case Overview
1.1 Court
General Division of the High Court1.2 Outcome
Plaintiff's claims for liquidated damages and replacement/rectification works allowed in part; three variation orders in the adjudication determination set aside; one of the defendant's claim for variation order allowed; defendant's other claims dismissed.
1.3 Case Type
Civil
1.4 Judgment Type
Judgment
1.5 Jurisdiction
Singapore
1.6 Description
Singapore High Court case involving Zhong Kai Construction and Diamond Glass over liquidated damages, rectification works, and SOPA adjudication.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Diamond Glass Enterprise Pte Ltd | Defendant, Plaintiff in counterclaim | Corporation | Counterclaim Allowed in Part | Partial | |
Zhong Kai Construction Co Pte Ltd | Plaintiff, Defendant in counterclaim | Corporation | Appeal Allowed in Part | Partial |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Kwek Mean Luck | Judicial Commissioner | Yes |
4. Counsels
4. Facts
- Zhong Kai Construction engaged Diamond Glass as a subcontractor for aluminium cladding works at Changi Airport.
- The Subcontract Sum was a Provisional Sum of $558,055 excluding GST.
- Diamond Glass abandoned the worksite around 6 June 2018 due to payment disputes.
- Zhong Kai Construction claimed liquidated damages for Diamond Glass's delays and costs for replacement/rectification works.
- Diamond Glass counterclaimed for payments due under variation orders and unpaid sums under the Subcontract.
- An Adjudication Determination was issued on 15 November 2019, awarding $197,522.83 to Diamond Glass under SOPA.
- Zhong Kai Construction commenced Suit No 1282 of 2019 to overturn the adjudicated amount.
5. Formal Citations
- Zhong Kai Construction Co Pte Ltd v Diamond Glass Enterprise Pte Ltd, Suit No 1282 of 2019, [2021] SGHC 277
- Diamond Glass Enterprise Pte Ltd v Zhong Kai Construction Co Pte Ltd, , [2021] SGCA 61
6. Timeline
Date | Event |
---|---|
Subcontract signed between Zhong Kai Construction and Diamond Glass | |
Zhong Kai Construction noted delays in Diamond Glass meeting the schedule | |
SCB Building Construction sent email regarding Diamond Glass not placing order for cabin glass | |
Diamond Glass sent letter cancelling purchase order for cabin glass | |
Diamond Glass demanded payment of $149,436.99 by 5 June 2018 | |
Diamond Glass abandoned the worksite | |
Diamond Glass sent letter terminating the contract | |
Diamond Glass served a progress claim on Zhong Kai Construction | |
Zhong Kai Construction commenced Suit No 917 of 2019 | |
Diamond Glass commenced Adjudication Application No 339 of 2019 under SOPA | |
Adjudication Determination issued | |
Zhong Kai Construction commenced Suit No 1282 of 2019 | |
Diamond Glass obtained a court order to enforce the AD as a judgment debt | |
Diamond Glass served a statutory demand on Zhong Kai Construction | |
Diamond Glass commenced Companies Winding Up Originating Summons No 95 of 2020 | |
Court of Appeal upheld the decision to stay CWU 95 in Diamond Glass Enterprise Pte Ltd v Zhong Kai Construction Co Pte Ltd [2021] SGCA 61 | |
Judgment reserved |
7. Legal Issues
- Liquidated Damages
- Outcome: The court found that the completion dates in clause 6 of the Subcontract applied for the purposes of the liquidated damages clause. The court found that there were no justifiable reasons for reducing the period of delay. The court found that the liquidated damages quantum in clause 6 of the Subcontract was not a penalty.
- Category: Substantive
- Sub-Issues:
- Applicability of completion dates
- Justifiable reasons for reducing delay period
- Penalty clause
- Repudiatory Breach
- Outcome: The court found that the defendant wrongfully terminated the Subcontract and that there was no basis for the defendant to reduce the period of delay on account of alleged repudiatory breach by the plaintiff.
- Category: Substantive
- Sub-Issues:
- Non-payment
- Delay of payment
- Replacement and Rectification of Defective Works
- Outcome: The court allowed some of the claims for replacement and rectification of defective works, finding that the invoices fell within the exception under s 32(1)(b) of the Evidence Act. The court found that the defendant did not discharge the burden of proving that losses have not been mitigated properly.
- Category: Substantive
- Sub-Issues:
- Mitigation of losses
- Administration charge
- Adjudication Determination under SOPA
- Outcome: The court set aside three of the variation orders in the adjudication determination, finding that there was no agreement from CAAS or SJ as required under clause 2 of the Subcontract. The court dismissed the plaintiff’s claim for overturning the main works allowed by the adjudicator in the AD.
- Category: Procedural
- Sub-Issues:
- Variation orders
- Agreement by principal
8. Remedies Sought
- Monetary Damages
- Setting Aside Adjudication Determination
9. Cause of Actions
- Breach of Contract
- Recovery of Debt
10. Practice Areas
- Construction Disputes
- Commercial Litigation
- Arbitration
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Diamond Glass Enterprise Pte Ltd v Zhong Kai Construction Co Pte Ltd | Court of Appeal | Yes | [2021] SGCA 61 | Singapore | Upheld the decision to stay the winding-up application, adding the condition that the plaintiff pay a sum into court as security. Cited for legal principles on when payment delays amount to repudiation of a contract. |
Hewlett-Packard Singapore (Sales) Pte Ltd v Chin Shu Hwa Corinna | Court of Appeal | No | [2016] 2 SLR 1083 | Singapore | Cited for the principle that the contra proferentem rule applies only if the contract contains ambiguity that cannot be resolved by ordinary interpretation. |
The “Asia Star” | N/A | No | [2010] 2 SLR 1154 | N/A | Cited for the principle that a plaintiff must take all reasonable steps to mitigate losses arising from a breach. |
Jia Min Building Construction Pte Ltd v Ann Lee Pte Ltd | N/A | Yes | [2004] 3 SLR(R) 288 | N/A | Cited for the principle that a contractor/subcontractor has no general right at common law to suspend work unless this is expressly agreed upon, even if payment is wrongly withheld. Also cited for principles on mitigation of losses. |
Lian Soon Construction Pte Ltd Guan Qian Realty Pte Ltd | N/A | No | [1999] 3 SLR(R) 518 | N/A | Cited for the principle that SCB and the plaintiff committed “acts of prevention” which prevented the defendant from completing the works on time. |
Denka Advantech Pte Ltd and another v Seraya Energy Pte Ltd and another and other appeals | Court of Appeal | Yes | [2021] 1 SLR 631 | Singapore | Cited for the principle that a clause will be a penalty if the sum stipulated for is extravagant and unconscionable in comparison with the greatest loss that could conceivably be proved to have followed from the breach, such that the sum stipulated for is not a genuine pre-estimate of the likely loss. |
AL Stainless Industries Pte Ltd v Wei Sin Construction Pte Ltd | High Court | No | [2001] SGHC 243 | Singapore | Cited for the principle that there may be instances in which a persistent course of payment delays, or a protracted delay in the payment of a very substantial sum amounts to a repudiation of the contract. |
GA Engineering Pte Ltd v Sun Moon Construction Pte Ltd | High Court | No | [2020] SGHC 167 | Singapore | Cited for the principle that Section 30(4) of SOPA allows a party in principle to recover the costs of an adjudication application as damages. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) | Singapore |
Evidence Act (Cap 97, 1997 Rev Ed) s 32(1)(b) | Singapore |
SOPA s 30(4) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Liquidated Damages
- Subcontract
- Variation Order
- Adjudication Determination
- Repudiatory Breach
- SOPA
- Retention Sum
- Cabin Glass
- Rockwool
- BCA Submission
15.2 Keywords
- construction
- liquidated damages
- SOPA
- adjudication
- breach of contract
- Singapore
17. Areas of Law
16. Subjects
- Construction Dispute
- Contract Law
- Arbitration
- Building and Construction Law