BZV v BZW: Setting Aside Arbitration Award for Breach of Natural Justice

In BZV v BZW, the General Division of the High Court of Singapore heard an application by BZV to set aside an arbitration award that dismissed its claims against BZW for delay in delivering a vessel and breach of contract regarding generator specifications. The court, presided over by Justice Vinodh Coomaraswamy, allowed BZV's application, setting aside the award to the extent it dismissed BZV's claims, finding a breach of natural justice in the tribunal's reasoning.

1. Case Overview

1.1 Court

GENERAL DIVISION OF THE HIGH court of the republic of singapore

1.2 Outcome

Application allowed and the award set aside in so far as it dismisses the plaintiff's claim.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Singapore court sets aside arbitration award dismissing BZV's claims against BZW for breach of contract due to a breach of natural justice.

1.7 Decision Date

2. Parties and Outcomes

3. Judges

Judge NameTitleDelivered Judgment
Vinodh CoomaraswamyJudgeYes

4. Counsels

4. Facts

  1. Plaintiff and defendants were claimant and respondents in an arbitration.
  2. The arbitration arose from a shipbuilding contract between the plaintiff as the vessel’s buyer and the defendants as the vessel’s builders.
  3. The plaintiff advanced two claims against the defendants: delay in delivering the vessel and breach of contract by delivering the vessel with generators which failed to meet contractual specifications.
  4. The defendants denied the plaintiff’s claims and brought a counterclaim.
  5. The tribunal dismissed the plaintiff’s claims as well as the defendants’ counterclaim.
  6. The plaintiff applied to set aside the award, save only for that part of the award which has dismissed the defendants’ counterclaim.
  7. The court allowed the plaintiff’s application and set aside the award in so far as it dismisses the plaintiff’s claim.

5. Formal Citations

  1. BZV v BZW, Originating Summons No 488 of 2019, [2021] SGHC 60

6. Timeline

DateEvent
Contract signed
Original delivery date of vessel
Meetings between End-Buyer, Plaintiff, and Defendants
ABS conducted tests on the vessel
Defendants served written notice of completion
Meetings between End-Buyer, Plaintiff, and Defendants
Second supplemental agreement (SA2) entered
Third supplemental agreement entered
Extended delivery date per SA2
Cancelling date per SA2
Plaintiff put defendants on notice for failure to deliver vessel
ABS issued interim class certificate for the vessel
ModuSpec carried out inspection of the vessel
ABS issued interim class certificate for the vessel
Fourth supplemental agreement (SA4) entered
Defendants delivered the vessel to the plaintiff
Plaintiff commenced arbitration against the defendants
Tribunal constituted
Plaintiff filed statement of claim in the arbitration
Defendants filed statement of defence and counterclaim
Evidential hearing in the arbitration took place
Tribunal delivered its award
SIAC forwarded the award to the parties
Plaintiff requested the tribunal to correct the award
Tribunal disposed of the plaintiff’s request by issuing an addendum to the award
Plaintiff requested the tribunal to interpret the award
Tribunal rejected the plaintiff’s further request
Plaintiff filed originating summons
Plaintiff filed the affidavit in support
Plaintiff effected service on the defendants
Judgment issued

7. Legal Issues

  1. Breach of Natural Justice
    • Outcome: The court found that the tribunal breached the fair hearing rule, a breach of natural justice.
    • Category: Substantive
    • Sub-Issues:
      • Failure to apply mind to essential issues
      • Defective chain of reasoning
  2. Setting Aside Arbitration Award
    • Outcome: The court allowed the application to set aside the arbitration award in part.
    • Category: Procedural

8. Remedies Sought

  1. Setting aside of arbitration award

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Commercial Litigation
  • Arbitration
  • Construction Law

11. Industries

  • Construction
  • Shipping

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
ABC Co v XYZ Co LtdHigh CourtYes[2003] 3 SLR(R) 546SingaporeCited to show that the Model Law leaves it to each Model Law jurisdiction to prescribe the procedure for “making” an “application” to set aside an award.
John Holland Pty Ltd v Toyo Engineering Corp (Japan)High CourtYes[2001] 1 SLR(R) 443SingaporeCited for the elements a plaintiff must establish to succeed in setting aside an award under s 24(b) of the Act.
Soh Beng Tee & Co Pte Ltd v Fairmount Development Pte LtdCourt of AppealYes[2007] 3 SLR(R) 86SingaporeCited for the fair hearing rule requiring each party to be given adequate notice of the case it must meet and a fair opportunity to be heard.
TMM Division Maritima SA de CV v Pacific Richfield Marine Pte LtdCourt of AppealYes[2013] 4 SLR 972SingaporeCited for principles of law to be applied when determining the plaintiff's application.
BLC v BLBHigh CourtYes[2014] 4 SLR 79SingaporeCited for the principle that if a fair reading of the award shows that the tribunal did apply its mind to the essential issues but failed to comprehend the submissions or comprehended them erroneously, and thereby came to a decision which may fall to be characterised as inexplicable, that will be simply an error of fact or law and the award will not be set aside.
ASG v ASHHigh CourtYes[2016] 5 SLR 54SingaporeCited for the principle that the fact that an award fails to address one of the parties’ arguments expressly does not, in itself, mean that the tribunal failed to apply its mind to that argument.
AKN v ALCHigh CourtYes[2015] 3 SLR 488SingaporeCited for the principle that an award will not be set aside on the ground that the tribunal failed to apply its mind to an essential issue arising from the parties’ arguments unless the failure is a clear and virtually inescapable inference from the award.
JVL Agro Industries Ltd v Agritrade International Pte LtdCourt of AppealYes[2016] 4 SLR 768SingaporeCited for the principle that to comply with the fair hearing rule, the tribunal’s chain of reasoning must be: (i) one which the parties had reasonable notice that the tribunal could adopt; and (ii) one which has a sufficient nexus to the parties’ arguments.
BXS v BXTHigh CourtYes[2019] 4 SLR 390SingaporeCited to show that Art 5 of the Model Law is so weighty as to exclude the court’s general substantive power in paragraph 7 of the First Schedule of the Supreme Court of Judicature Act to extend the three-month period in Art 34(3) of the Model Law.
Trollope & Colls Ltd v North West Metropolitan Regional Hospital BoardHouse of LordsYes[1973] 1 WLR 601England and WalesCited for the principle that an act of prevention may be quite legitimate conduct and does not have to amount to a breach of contract.
LW Infrastructure Ltd v Lim Chin San Contractors Pte LtdHigh CourtYes[2013] 1 SLR 125SingaporeCited for the principle that a breach of natural justice causes a party to suffer actual or real prejudice if complying with the rules of natural justice could reasonably have made a difference to the outcome of the arbitration.
AKN v ALCCourt of AppealYes[2016] 1 SLR 966SingaporeCited for the principle that the principle of limited curial intervention militates against its exercise rather than in favour of it.
Secretary of State for the Home Department v Raytheon Systems LtdCommercial CourtYes[2015] 1 Lloyd’s Rep 495England and WalesCited for the principle that there is no allegation of apparent bias, let alone a finding of actual bias.
Lovell Partnerships (Northern) Ltd v AW Construction plcTechnology and Construction CourtYes(1997) 81 BLR 83England and WalesCited for the principle that there is no allegation of apparent bias, let alone a finding of actual bias.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
International Arbitration Act (Cap 143A, 2002 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Arbitration
  • Setting aside
  • Breach of natural justice
  • Shipbuilding contract
  • Delay claim
  • IP44 claim
  • Model Law
  • International Arbitration Act
  • Fair hearing rule
  • Prevention principle

15.2 Keywords

  • arbitration
  • setting aside
  • breach of contract
  • natural justice
  • shipbuilding

17. Areas of Law

16. Subjects

  • Arbitration
  • Contract Law
  • Construction Dispute