COT v COU: Setting Aside Arbitral Award for Lack of Jurisdiction and Breach of Natural Justice

The Singapore Court of Appeal heard appeals by COT, COV, and COW against COU, challenging an arbitral award. The appellants sought to set aside the award, arguing the arbitral tribunal lacked jurisdiction due to the absence of a valid arbitration agreement, exceeded its jurisdiction, and breached natural justice. The court dismissed the appeals, finding a valid arbitration agreement existed and the tribunal did not exceed its jurisdiction or breach natural justice. The court emphasized the policy of minimal curial intervention in arbitral proceedings.

1. Case Overview

1.1 Court

Court of Appeal of the Republic of Singapore

1.2 Outcome

Appeals dismissed.

1.3 Case Type

Civil

1.4 Judgment Type

Judgment

1.5 Jurisdiction

Singapore

1.6 Description

Singapore Court of Appeal addresses setting aside an arbitral award due to jurisdictional challenges and breach of natural justice, emphasizing minimal curial intervention.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
COTAppellant, Defendant, PlaintiffCorporationAppeal DismissedLost
COURespondent, Plaintiff, DefendantCorporationSuccessful Defense of AppealWon
COVAppellant, Defendant, PlaintiffCorporationAppeal DismissedLost
COWAppellant, Defendant, PlaintiffCorporationAppeal DismissedLost

3. Judges

Judge NameTitleDelivered Judgment
Judith PrakashJustice of the Court of AppealNo
Tay Yong KwangJustice of the Court of AppealNo
Steven ChongJustice of the Court of AppealYes

4. Counsels

4. Facts

  1. Claimant was unwilling to deliver remaining Modules due to outstanding invoices.
  2. Project Company was ultimately responsible for payment of invoices.
  3. Project Company required Modules to complete Project and receive payment.
  4. Negotiations occurred to address outstanding invoices and release Modules.
  5. Non-Disposal Undertaking (NDU) was drafted to provide security for payment.
  6. Claimant released Modules after negotiations and agreement on NDU.
  7. EPC Company made part payment of invoices after negotiations.

5. Formal Citations

  1. COT v COU and others and other appeals, , [2023] SGCA 31
  2. COT v COU, Civil Appeal No 12 of 2022, Civil Appeal No 12 of 2022
  3. COT v COU, Originating Summons No 482 of 2021, Originating Summons No 482 of 2021
  4. COV v COU, Civil Appeal No 13 of 2022, Civil Appeal No 13 of 2022
  5. COV v COU, Originating Summons No 489 of 2021, Originating Summons No 489 of 2021
  6. COW v COU, Civil Appeal No 15 of 2022, Civil Appeal No 15 of 2022
  7. COW v COU, Originating Summons No 492 of 2021, Originating Summons No 492 of 2021

6. Timeline

DateEvent
Module Supply Agreement concluded between Claimant and Procurement Company.
Equipment and material supply contract entered into between EPC Company and Project Company.
Claimant indicated it would suspend further deliveries of Modules.
Negotiations commenced between Claimant and Rohan Group.
Claimant released remaining Modules.
EPC Company paid ₴5.06m to Procurement Company.
Procurement Company paid ₴5.06m to Claimant.
Claimant commenced arbitration against appellants.
Judgment reserved.
Judgment delivered.

7. Legal Issues

  1. Jurisdiction of Arbitral Tribunal
    • Outcome: The court found that the arbitral tribunal had jurisdiction because a valid arbitration agreement existed.
    • Category: Jurisdictional
    • Sub-Issues:
      • Absence of valid arbitration agreement
      • Authority to bind parties to contract
    • Related Cases:
      • [2014] 4 SLR 79
      • [2007] 3 SLR(R) 86
      • [2015] 3 SLR 488
      • [2016] 4 SLR 1336
      • [2022] 5 SLR 22
      • [2015] 2 SLR 972
      • [2018] 1 All ER (Comm) 691
  2. Breach of Natural Justice
    • Outcome: The court found that there was no breach of natural justice.
    • Category: Procedural
    • Sub-Issues:
      • Denial of opportunity to present case
      • Failure to decide on matters submitted
    • Related Cases:
      • [2011] 4 SLR 305
  3. Scope of Arbitral Submission
    • Outcome: The court found that the tribunal did not exceed the scope of its jurisdiction.
    • Category: Procedural
    • Sub-Issues:
      • Tribunal exceeding scope of jurisdiction
      • Tribunal dealing with dispute not contemplated by submission
    • Related Cases:
      • [2011] 4 SLR 305
      • [2021] 2 SLR 1279
      • [2021] 2 SLR 235
      • [2022] 2 SLR 1
  4. Contract Formation
    • Outcome: The court found that a binding contract was concluded between the parties.
    • Category: Substantive
    • Sub-Issues:
      • Consensus ad idem
      • Intention to create legal relations
    • Related Cases:
      • [2015] 1 SLR 521
      • [2009] 2 SLR(R) 332
      • [2000] 2 SLR(R) 407
      • [2020] 5 SLR 514
      • [2020] 2 SLR 984

8. Remedies Sought

  1. Monetary Damages

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Arbitration
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
BLC and others v BLB and anotherCourt of AppealYes[2014] 4 SLR 79SingaporeCited for the policy of minimal curial intervention in arbitral proceedings.
Soh Beng Tee & Co Pte Ltd v Fairmount Development Pte LtdCourt of AppealYes[2007] 3 SLR(R) 86SingaporeCited for the principle of respecting and preserving the autonomy of the arbitral process.
AKN and another v ALC and others and other appealsCourt of AppealYes[2015] 3 SLR 488SingaporeCited for the principle that parties are bound by the decisions of their chosen arbitrators.
Tjong Very Sumito and others v Antig Investments Pte LtdCourt of AppealYes[2009] 4 SLR(R) 732SingaporeCited for the desire to support, and not to displace, the arbitral process.
Astro Nusantara International BV and others v PT Ayunda Prima Mitra and othersCourt of AppealYes[2013] 1 SLR 636SingaporeCited for upholding the finality of the arbitration process.
ASG v ASHCourt of AppealYes[2016] 5 SLR 54SingaporeCited for the principle that parties must accept the consequences of choosing arbitration.
CRW Joint Operation v PT Perusahaan Gas Negara (Persero) TBKCourt of AppealYes[2011] 4 SLR 305SingaporeCited in relation to the scope of jurisdiction under Art 34(2)(a)(iii) of the Model Law.
Fiona Trust & Holding Corporation v PrivalovEnglish Court of AppealNo[2007] 2 Lloyd’s Rep 267England and WalesCited for the separability principle, but distinguished as not applicable to contractual formation.
Fiona Trust & Holding Corporation and others v Privalov and othersHouse of LordsNo[2008] 1 Lloyd’s Rep 254United KingdomCited for the separability principle, but distinguished as not applicable to contractual formation.
BCY v BCZCourt of AppealYes[2017] 3 SLR 357SingaporeCited for the principle that the separability principle only applies to questions of contractual validity and not to contractual formation.
DHL Project & Chartering Ltd v Gemini Ocean Shipping Co LtdEnglish CourtYes[2023] 3 All ER 580England and WalesCited for affirming that the separability principle does not apply to the question of contractual formation.
Jiangsu Overseas Group Co Ltd v Concord Energy Pte Ltd and another matterHigh CourtYes[2016] 4 SLR 1336SingaporeCited for the standard of review in setting aside applications based on the absence of a concluded contract.
CUG and others v CUHSingapore International Commercial CourtYes[2022] 5 SLR 22SingaporeCited for following Jiangsu Overseas Group in conducting a de novo review of the tribunal’s ruling on jurisdiction.
AQZ v ARAHigh CourtYes[2015] 2 SLR 972SingaporeCited for a jurisdictional challenge mounted on the basis that no contract was concluded between the parties on account of a “subject to contract” provision.
Hyundai Merchant Marine Company Limited v Americas Bulk Transport LtdHigh CourtNo[2013] 2 All ER (Comm) 649England and WalesCited for the principle that whether there was a binding fixture and/or a binding arbitration agreement stood or fell together.
Erdenet Mining Corporation LLC v ICBC Standard Bank plc and othersHigh CourtYes[2018] 1 All ER (Comm) 691England and WalesCited for the question of where the seat court’s de novo inquiry should end.
PT First Media TBK (formerly known as PT Broadband Multimedia TBK) v Astro Nusantara International BV and others and another appealCourt of AppealYes[2014] 1 SLR 372SingaporeCited for the principle that an application to set aside an award on the basis that no valid arbitration agreement was formed can be brought under Art 34(2)(a)(i) of the Model Law.
R1 International Pte Ltd v Lonstroff AGCourt of AppealYes[2015] 1 SLR 521SingaporeCited for the principle that the court adopts an objective approach towards the question of contractual formation.
Gay Choon Ing v Loh Sze Ti Terence Peter and another appealCourt of AppealYes[2009] 2 SLR(R) 332SingaporeCited for the principle that once the parties have outwardly agreed in the same terms on the same subject matter, then neither can, generally, rely on some unexpressed qualification or reservation to show that he had not in fact agreed to the terms to which he had appeared to have agreed.
Aircharter World Pte Ltd v Kontena Nasional BhdCourt of AppealYes[1999] 2 SLR(R) 440SingaporeCited for the principle that once the parties have outwardly agreed in the same terms on the same subject matter, then neither can, generally, rely on some unexpressed qualification or reservation to show that he had not in fact agreed to the terms to which he had appeared to have agreed.
Chia Ee Lin Evelyn v Teh Guek Ngor Engelin née Tan and othersCourt of AppealYes[2004] 4 SLR(R) 330SingaporeCited for the principle that the intention which courts will attribute to a person is always that which that person’s conduct and words amount to when reasonably construed by a person in the position of the offeree, and not necessarily that which was present in the offeror’s mind.
Tribune Investment Trust Inc v Soosan Trading Co LtdCourt of AppealYes[2000] 2 SLR(R) 407SingaporeCited for the principle that when inferring parties’ assent in circumstances of protracted negotiations, the court must ensure that the reasonable expectations of honest men are not disappointed.
Day, Ashley Francis v Yeo Chin Huat Anthony and othersCourt of AppealYes[2020] 5 SLR 514SingaporeCited for the principle that the court will consider the entire course of negotiations to determine whether there was a single point in time when the requisite consensus ad idem was reached.
China Coal Solution (Singapore) Pte Ltd v Avra Commodities Pte LtdCourt of AppealYes[2020] 2 SLR 984SingaporeCited for the principle that the whole course of the parties’ negotiations, both before and after the alleged date of contracting, must be considered when determining whether a contract was formed.
Simpson Marine (SEA) Pte Ltd v Jiacipto JiaravanonCourt of AppealYes[2019] 1 SLR 696SingaporeCited for the principle that evidence of subsequent conduct has traditionally been regarded as admissible and relevant to determine whether a contract has been formed.
TTMI Sarl v Statoil ASA (The Sibohelle)High CourtYes[2011] 2 All ER (Comm) 647England and WalesCited for the principle that the facts that services were rendered, work undertaken, or payment made are relevant factors in deciding whether a binding contract was concluded.
RTS Flexible Systems Ltd v Molkerei Alois Müller GmbH & Co KGSupreme CourtYes[2010] 1 WLR 753United KingdomCited for the principle that the facts that services were rendered, work undertaken, or payment made are relevant factors in deciding whether a binding contract was concluded.
Bloomberry Resorts and Hotels Inc and another v Global Gaming Philippines LLC and anotherCourt of AppealYes[2021] 2 SLR 1279SingaporeCited for the two-stage enquiry that applies when determining a challenge brought under Art 34(2)(a)(iii) of the Model Law.
CDM and another v CDPCourt of AppealYes[2021] 2 SLR 235SingaporeCited for the principle that the scope of the submission is determined with reference to five sources: the parties’ pleadings, agreed list of issues, opening statements, evidence adduced, and closing submissions.
CKH v CKG and another matterCourt of AppealYes[2022] 2 SLR 1SingaporeCited for the principle that the exercise of determining whether a matter falls or has come within the scope of the agreed reference is a holistic one.
Gol Linhas Aereas SA (formerly VRG Linhas Aereas SA) v MatlinPatterson Global Opportunities Partners (Cayman) II LP and othersHigh CourtYes[2022] 2 All ER (Comm) 841England and WalesCited for the principle that terms of reference must be given a liberal construction in keeping with the purpose of arbitration to provide a flexible and effective means of resolving disputes and providing redress.
COT v COU and others and other mattersHigh CourtYes[2023] SGHC 69SingaporeThe decision below being appealed.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
International Arbitration Act 1994Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Arbitral Award
  • Setting Aside
  • Jurisdictional Challenge
  • Curial Intervention
  • Arbitration Agreement
  • Non-Disposal Undertaking
  • Modules Delivery Agreement
  • Consensus ad idem
  • Back-to-back contracts
  • Ultra petita
  • Infra petita
  • Natural justice

15.2 Keywords

  • arbitration
  • contract
  • jurisdiction
  • setting aside
  • natural justice

17. Areas of Law

16. Subjects

  • Arbitration
  • Contract Law
  • Civil Procedure