Logistics Construction Pte Ltd Scheme of Arrangement: Moratorium Application

Logistics Construction Pte Ltd applied to the General Division of the High Court of Singapore on 14 August 2023 for a six-month moratorium under s 64(1) of the Insolvency, Restructuring and Dissolution Act 2018 to restrain legal proceedings while it negotiated with creditors and investors. Goh Yihan JC granted the application but limited the moratorium to three months, finding that the company had demonstrated a genuine attempt to restructure its liabilities and had the support of its largest creditor, OCBC, but that the proposed scheme lacked specific details. The court balanced the interests of the applicant and its creditors in reaching its decision.

1. Case Overview

1.1 Court

General Division of the High Court of the Republic of Singapore

1.2 Outcome

Application allowed in part

1.3 Case Type

Insolvency

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

The High Court granted Logistics Construction Pte Ltd a three-month moratorium to restrain proceedings while it negotiates with creditors and investors.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
DBS Bank LtdRespondentCorporationObjection notedNeutral
Logistics Construction Pte LtdApplicantCorporationMoratorium Granted in PartPartial
Oversea-Chinese Banking Corporation LimitedRespondentCorporationSupport for MoratoriumNeutral
Buildforms Construction (Pte) LtdRespondentCorporationObjection notedNeutral
Maginet Plumbing Contractor Pte LtdRespondentCorporationObjection notedNeutral
Golden Landscape & Construction Pte LtdRespondentCorporationObjection notedNeutral
MKV Engineering and Trading Services Pte LtdRespondentCorporationObjection notedNeutral
Archilite Engineering Pte LtdRespondentCorporationObjection notedNeutral
Chan Kok Yeow of Independent Practitioner
Kandenko Co LtdRespondentCorporationObjection notedNeutral
Hongkong and Shanghai Banking Corporation LtdRespondentCorporationObjection notedNeutral
HYY Engineering (Pte) LtdRespondentCorporationObjection notedNeutral
Vertical Green Pte LtdRespondentCorporationObjection notedNeutral
Darren Neo Eng Jye of Independent Practitioner
SG Façade Engineering Pte LtdRespondentCorporationObjection notedNeutral
Wang Yulong of Independent Practitioner
Wireka Sdn BhdRespondentCorporationObjection notedNeutral
Jeffrey Lee Soon Quan of Independent Practitioner

3. Judges

Judge NameTitleDelivered Judgment
Goh YihanJudicial CommissionerYes

4. Counsels

4. Facts

  1. Logistics Construction Pte Ltd applied for a moratorium under s 64(1) of the IRDA.
  2. The applicant sought a six-month moratorium to negotiate with creditors and investors.
  3. The applicant is a wholly-owned subsidiary of Boldtek Holdings Limited.
  4. Boldtek Holdings Limited faced a trading halt and voluntary suspension due to a qualified opinion from its auditor.
  5. The applicant faced demands for payment and legal proceedings.
  6. The applicant was in discussions with investors for a potential $6m investment.
  7. OCBC, the largest creditor, supported a six-month moratorium.

5. Formal Citations

  1. Re Logistics Construction Pte Ltd, Originating Application No 726 of 2023, [2023] SGHC 231

6. Timeline

DateEvent
Logistics Construction Pte Ltd incorporated in Singapore
Boldtek Holdings Limited listed on the Catalist of the Singapore Exchange
Group awarded construction contracts worth approximately $119.1m
Group's order book stood at about $79.4m
Group awarded construction contracts worth approximately $119.1m
Boldtek Holdings Limited called for a trading halt
Boldtek Holdings Limited converted trading halt into a voluntary suspension
2nd Affidavit of Phua Lam Soon dated
1st Affidavit of Ong Cheng Chuen dated
1st Affidavit of Lim Chuen Yang dated
3rd Affidavit of Phua Lam Soon dated
Hearing before Goh Yihan JC
Application allowed for a three-month moratorium
Judgment Date

7. Legal Issues

  1. Grant of Moratorium
    • Outcome: The court granted a three-month moratorium, finding a reasonable prospect of the scheme working but requiring more specific details.
    • Category: Substantive
    • Sub-Issues:
      • Reasonable prospect of proposed compromise or arrangement working
      • Acceptability of proposed compromise or arrangement to the general run of creditors
      • Good faith of the applicant

8. Remedies Sought

  1. Moratorium on legal proceedings

9. Cause of Actions

  • Application for Moratorium

10. Practice Areas

  • Insolvency
  • Restructuring
  • Corporate Law
  • Commercial Litigation

11. Industries

  • Construction
  • Finance

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Re All Measure Technology (S) Pte Ltd (RHB Bank Bhd, non-party)High CourtYes[2023] SGHC 148SingaporeCited for the principle that cases interpreting s 211B(1) of the Companies Act continue to be applicable in interpreting s 64(1) of the IRDA.
Re Zipmex Co Ltd and other mattersHigh CourtYes[2022] SGHC 196SingaporeCited for the principle that cases interpreting s 211B(1) of the Companies Act continue to be applicable in interpreting s 64(1) of the IRDA.
Re IM Skaugen SE and other mattersHigh CourtYes[2019] 3 SLR 979SingaporeCited for the principle that a moratorium is an extraordinary relief and the court undertakes a balancing exercise between allowing the applicant breathing space and ensuring that the interests of creditors are sufficiently safeguarded.
Pathfinder Strategic Credit LP and another v Empire Capital Resources Pte Ltd and another appealCourt of AppealYes[2019] 2 SLR 77SingaporeCited for the principle that a moratorium application must contain sufficient particulars.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Insolvency, Restructuring and Dissolution Act 2018Singapore
s 64(1) of the Insolvency, Restructuring and Dissolution Act 2018Singapore
Building and Construction Industry Security of Payment Act 2004Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Moratorium
  • Scheme of arrangement
  • Insolvency, Restructuring and Dissolution Act 2018
  • Creditors
  • Restructuring
  • Trading halt
  • Voluntary suspension
  • Qualified opinion
  • Scheme managers

15.2 Keywords

  • moratorium
  • scheme of arrangement
  • insolvency
  • restructuring
  • Logistics Construction Pte Ltd

17. Areas of Law

16. Subjects

  • Insolvency
  • Corporate Restructuring
  • Schemes of Arrangement
  • Moratoriums