Vim Engineering v Deluge Fire Protection: Construction Contract Dispute over Variation Works and Back-Charges

Vim Engineering Pte Ltd appealed against the High Court's decision in a dispute with Deluge Fire Protection (S.E.A.) Pte Ltd concerning a construction project at 5 Shenton Way. Vim, the appellant, claimed for variation works, while Deluge, the respondent, counterclaimed for rectification works and back-charges. The High Court had ruled against Vim on the variation works claim and largely in favor of Deluge on its counterclaims. The Appellate Division allowed the appeal in part, upholding Vim's claim for variation works, dismissing Deluge's claim for rectification works, and reducing Deluge's claim for back-charges. The court found Deluge liable to Vim for a net sum of $800,552.14.

1. Case Overview

1.1 Court

Appellate Division of the High Court

1.2 Outcome

Appeal Allowed in Part

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Construction dispute over subcontract for plumbing works. Appeal concerns variation works, rectification costs, and back-charges. Judgment partly allowed the appeal.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Vim Engineering Pte LtdAppellant, PlaintiffCorporationAppeal Allowed in PartPartial
Deluge Fire Protection (S.E.A.) Pte LtdRespondent, DefendantCorporationCounterclaim Partially AllowedPartial

3. Judges

Judge NameTitleDelivered Judgment
Woo Bih LiJudge of the Appellate DivisionNo
See Kee OonJudge of the High CourtNo
Quentin LohSenior JudgeYes

4. Counsels

4. Facts

  1. UIC Investments engaged Samsung as the main contractor for a building redevelopment project.
  2. Samsung engaged Deluge as a subcontractor for plumbing, sanitary, and gas work.
  3. Samsung complained of delays in Deluge's work.
  4. Deluge engaged Vim to carry out a limited scope of plumbing works.
  5. Vim and Deluge entered into a subcontract for specified plumbing and sanitary works.
  6. Disagreements arose, and Vim left the project site before completing all work.
  7. Deluge claimed costs for completing Vim's work and rectifying defects.

5. Formal Citations

  1. Vim Engineering Pte Ltd v Deluge Fire Protection (S.E.A.) Pte Ltd, Civil Appeal No 29 of 2021, [2023] SGHC(A) 2

6. Timeline

DateEvent
Samsung engaged Deluge as a subcontractor.
Samsung complained of severe schedule delay in Deluge’s work.
Deluge engaged Vim to carry out a limited scope of plumbing works.
Purchase Order (No. P020017880) issued.
Tender Clarifications were dated.
Vim's Quotation (VIM/QU/1408/Rev 3) was dated.
Subcontract was dated.
Temporary occupation permit obtained.
Vim left the project site.
Defects liability period expired.
Arguments heard.
Arguments heard.
Judgment reserved.

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found that both parties had breached the contract to varying degrees.
    • Category: Substantive
    • Sub-Issues:
      • Failure to comply with contractual requirements
      • Defective workmanship
      • Delays in project completion
  2. Variation Works
    • Outcome: The court allowed Vim's claim for variation works, finding that Deluge had waived the requirement of written notice.
    • Category: Substantive
    • Sub-Issues:
      • Requirement of written instructions
      • Waiver of contractual terms
      • Scope of original contract
  3. Back-Charges
    • Outcome: The court significantly reduced Deluge's claim for back-charges, finding insufficient evidence to support many of the charges.
    • Category: Substantive
    • Sub-Issues:
      • Defective workmanship
      • Delays in project completion
      • Notice requirements
  4. Rectification Works
    • Outcome: The court dismissed Deluge's claim for rectification works, finding insufficient evidence to support the claim.
    • Category: Substantive
    • Sub-Issues:
      • Defect liability period
      • Notice requirements
      • Proof of expenses
  5. Waiver
    • Outcome: The court found that Deluge had waived the requirement of written notice for variation works.
    • Category: Substantive
    • Sub-Issues:
      • Waiver by election
      • Authority to waive contractual terms
  6. Condition Precedent
    • Outcome: The court held that the written notice requirement in clause 16 was not a strict condition precedent.
    • Category: Substantive
    • Sub-Issues:
      • Written notice
      • Strict compliance
  7. Evidentiary Burden
    • Outcome: The court emphasized the importance of the evidentiary burden in establishing claims for back-charges and rectification works.
    • Category: Procedural
    • Sub-Issues:
      • Burden of proof
      • Sufficiency of evidence

8. Remedies Sought

  1. Monetary Damages

9. Cause of Actions

  • Breach of Contract
  • Quantum Meruit

10. Practice Areas

  • Construction Contracts
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Comfort Management v OGSP Engineering Pte LtdCourt of AppealNo[2018] 1 SLR 979SingaporeCited for the principle that the absence of writing does not invariably disentitle a party from claiming payment for variation works.
Mansource Interior Pte Ltd v CSG Group Pte LtdHigh CourtNo[2017] 5 SLR 203SingaporeCited as an example of a case where a strict construction of a written notice requirement was applied to disallow a variation claim.
GIB Automation Pte Ltd v Deluge Fire Protection (SEA) Pte LtdHigh CourtYes[2007] 2 SLR(R) 918SingaporeCited for the principle that a 'back-to-back' provision is not a term of art and must be construed in light of the factual matrix known to the parties.
Audi Construction v Kian Hiap ConstructionCourt of AppealYes[2018] 1 SLR 317SingaporeCited for the requirements for waiver by election, where a party unequivocally chooses not to exercise one of two inconsistent rights.
V Nithia (co-administratrix of the estate of Ponnusamy Sivapakiam, deceased) v Buthmanaban s/o Vaithilingam and anotherCourt of AppealYes[2015] 5 SLR 1422SingaporeCited for the general rule that parties are bound by their pleadings and the court is precluded from deciding on a matter that the parties themselves had decided not to put into issue.
Myers v SarlN/ANo[1860] 3 E. & E. 306N/ACited as an example of an unsigned sketch made by an architect’s assistant which was argued unsuccessfully to be a “direction” by the architect’s hand in writing.
Pearce and High v BaxterN/AYes[1999] BLR 101N/ACited for the principle that in the absence of clear and express words, the employer’s right to damages in respect of the cost of repairs is not extinguished.
Management Corporation Strata Title Plan No 1933 v Liang Huat Aluminium LtdN/AYes[2001] 2 SLRI 91SingaporeCited for the principle that in the absence of clear and express words, the employer’s right to damages in respect of the cost of repairs is not extinguished.
Longyuan-Arrk (Macao) Pte Ltd v Show and Tell Productions Pte Ltd and another suitHigh CourtYes[2013] SGHC 160SingaporeCited for the principle that the burden of proof was on the claimant to provide sufficient evidence to establish its claim.
Impact Painting Ltd v. Man-Shield (Alta) Construction IncN/AYes[2018] AWLD 582N/ACited for the principle that the onus is on the party claiming a back charge to prove that the back charge is for an expense actually, necessarily and reasonably incurred.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Evidence Act (Cap 97, 1997 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Variation Works
  • Back-Charges
  • Rectification Works
  • Subcontract
  • Written Notice
  • Condition Precedent
  • Defects Liability Period
  • Main Works
  • Plumbing Works
  • Sanitary Works

15.2 Keywords

  • construction contract
  • variation works
  • back-charges
  • rectification costs
  • plumbing
  • subcontractor
  • Singapore law

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Contract Law
  • Subcontracting
  • Appeals