Crescendas Bionics v Jurong Primewide: Building & Construction Delay, Loss of Chance, Damages

Crescendas Bionics Pte Ltd, a property developer, sued Jurong Primewide Pte Ltd, a building contractor, in the Appellate Division of the High Court of Singapore, regarding delays in the construction of Biopolis 3. The court, comprising Woo Bih Li JAD, Hoo Sheau Peng J, and Quentin Loh SJ, heard appeals concerning the assessment of damages, pre-judgment interest, and costs. The court allowed the appeal in part, finding Jurong Primewide liable for $4,185,802.60 in net rental revenue loss and $1,061,285.86 in Holding Costs. The court dismissed the appeal regarding pre-judgment interest.

1. Case Overview

1.1 Court

Appellate Division of the High Court

1.2 Outcome

Appeal Allowed in Part

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Crescendas Bionics sued Jurong Primewide for construction delay. The court addressed causation, remoteness, and damages, awarding Crescendas $4,185,802.60.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Crescendas Bionics Pte LtdAppellant, Plaintiff, Defendant in counterclaimCorporationAppeal Allowed in PartPartial
Jurong Primewide Pte LtdRespondent, Defendant, Plaintiff in counterclaimCorporationAppeal Dismissed in PartPartial

3. Judges

Judge NameTitleDelivered Judgment
Woo Bih LiJudge of the Appellate DivisionYes
Hoo Sheau PengJudge of the High CourtNo
Quentin LohSenior JudgeNo

4. Counsels

4. Facts

  1. Crescendas is a property developer.
  2. Jurong Primewide is a general building contractor.
  3. Parties signed a Letter of Intent on 30 June 2008 for Jurong Primewide to build Biopolis 3.
  4. Biopolis 3 is a seven-storey multi-tenanted business park development.
  5. Jurong Primewide was obliged to complete Biopolis 3 by 22 January 2010.
  6. Temporary Occupation Permit was obtained on 12 January 2011.
  7. Crescendas commenced the Suit against Jurong Primewide due to the delay.

5. Formal Citations

  1. Crescendas Bionics Pte Ltd v Jurong Primewide Pte Ltd and other appeals, Civil Appeals Nos 87, 88 and 128 of 2021, [2023] SGHC(A) 9

6. Timeline

DateEvent
Letter of Intent signed
Parties signed Letter of Intent
Crescendas responsible for delay
Crescendas responsible for delay
Crescendas responsible for delay
Crescendas responsible for delay
Memorandum of understanding signed
Philip Morris informed Crescendas that the exclusivity period had expired
Contractual completion date
Reasonable date of completion
Crescendas responsible for delay
Crescendas responsible for delay
BCA directed the Superintending Officer to apply for the Temporary Occupation Permit
Temporary Occupation Permit obtained
Crescendas commenced Suit No 477 of 2015
Jurong Primewide filed counterclaim
HC/ORC 1483/2018 in HC/SUM 401/2018
Liability Judgment (HC) delivered
Liability Judgment (CA) delivered
Damages Judgment (HC) delivered
Crescendas filed CA 128
Oral hearing
Judgment reserved

7. Legal Issues

  1. Causation
    • Outcome: Causation was established between the delay attributable to Jurong Primewide and the loss suffered by Crescendas, except for the loss of PetNet as a tenant.
    • Category: Substantive
    • Sub-Issues:
      • Uncertainty in causation
      • Whether the Combined Delay caused Crescendas to lose Philip Morris and/or PetNet as pre-commitment tenants
    • Related Cases:
      • [2007] 3 SLR(R) 782
      • 1 Exch 850
      • 1 All ER 1033
      • [2005] EWHC 181 (TCC)
      • [2020] 3 SLR 1234
      • [2022] 1 SLR 302
  2. Remoteness of Damage
    • Outcome: Crescendas’ entire claim for loss of net rental revenue comes within the First Limb of Hadley v Baxendale and is not too remote to be recoverable.
    • Category: Substantive
    • Related Cases:
      • 9 Exch 341
      • [2013] 2 SLR 363
      • [2008] 2 SLR(R) 623
      • [2017] 2 SLR 129
      • (1992) 33 NSWLR 504
  3. Quantification of Damages
    • Outcome: The Multi-Year Model should be used to quantify Crescendas' loss of net rental revenue. The applicable discount rate is 8% on a compounded basis. The loss should be apportioned based on 161 out of 355 days.
    • Category: Substantive
    • Sub-Issues:
      • Single-Year Model vs Multi-Year Model
      • Applicable discount rate
      • Apportionment of loss
    • Related Cases:
      • [2011] 1 SLR 150
      • [2010] 1 SLR 1104
      • [2007] BCSC 1780
  4. Holding Costs
    • Outcome: Crescendas is entitled to claim Holding Costs incurred during the 90-day rent-free period.
    • Category: Substantive
    • Sub-Issues:
      • Rent-free fitting-out period
    • Related Cases:
      • [2016] 2 SLR 1056
      • [2020] 3 SLR 1234
      • [2010] 2 SLR 1154
  5. Pre-judgment Interest
    • Outcome: The date from which pre-judgment interest in respect of the Shared Savings should run is the date of Crescendas’ writ.
    • Category: Procedural

8. Remedies Sought

  1. Monetary Damages
  2. General Damages

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Construction Law
  • Commercial Litigation

11. Industries

  • Construction
  • Real Estate

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Crescendas Bionics Pte Ltd v Jurong Primewide Pte LtdHigh CourtYes[2021] SGHC 189SingaporeOriginal decision on damages being appealed.
Crescendas Bionics Pte Ltd v Jurong Primewide Pte LtdHigh CourtYes[2019] SGHC 4SingaporeOriginal decision on liability, affirmed on appeal.
Jurong Primewide Pte Ltd v Crescendas Bionics Pte Ltd and another appealCourt of AppealYes[2019] SGCA 63SingaporeAffirmed the Liability Judgment (HC) save in relation to the arithmetic computation of the days of delay for which JP was responsible and the time taken for capping beams work.
Kwang In Tong Chinese Temple v Fong Choon Hung Construction Pte LtdN/AYes[1997] 1 SLR(R) 907SingaporeCited for the principle that a contractor is obligated to complete the project within a reasonable time and failure to do so will render the defendant liable for general damages.
Sunny Metal & Engineering Pte Ltd v Ng Khim Ming EricCourt of AppealYes[2007] 3 SLR(R) 782SingaporeCited for the principle that a claimant may recover damages for a loss only where the breach of contract was the ‘effective’ or ‘dominant’ cause of that loss.
Robinson v HarmanN/AYes1 Exch 850EnglandCited for the compensatory principle which undergirds the award of damages for a breach of contract.
Asia Hotel Investments Ltd v Starwood Asia Pacific Management Pte Ltd and anotherN/AYes[2005] 1 SLR(R) 661SingaporeCited for the principle that the loss of chance doctrine allows the claimant to avert the difficulty of proving that the claimant would have acquired the favourable outcome, by allowing the claimant to claim that he could (not would) have obtained the favourable outcome but for the breach.
MK Distripark Pte Ltd v Pedder Warehousing & Logistics (S) Pte LtdN/AYes[2013] 3 SLR 433SingaporeCited for the principle that the loss of chance doctrine allows the claimant to avert the difficulty of proving that the claimant would have acquired the favourable outcome, by allowing the claimant to claim that he could (not would) have obtained the favourable outcome but for the breach.
AKM v AKN and another and other mattersN/AYes[2014] 4 SLR 245SingaporeCited for the principle that there is a substantive distinction between the two ways of looking at loss. In a claim for the loss of actual profits, the plaintiff asserts that but for the breach of contract, he would (not could) have earned profits.
AKN and another v ALC and others and other appealsN/AYes[2015] 3 SLR 488SingaporeAppeal from AKM v AKN and another and other matters.
Heskell v Continental Express Ltd and anotherN/AYes1 All ER 1033EnglandCited for the principle that if a breach of contract is one of two causes, both co-operating and both of equal efficacy, it is sufficient to carry judgment for damages.
Great Eastern Hotel Company Ltd v John Laing Construction Ltd and anotherN/AYes[2005] EWHC 181 (TCC)England and WalesCited for the principle that if a breach of contract is one of the causes both co-operating and of equal efficiency in causing loss to the Claimant the party responsible for breach is liable to the Claimant for that loss.
Smile Inc Dental Surgeons Pte Ltd v OP3 International Pte LtdN/AYes[2020] 3 SLR 1234SingaporeCited for the principle that when the breach of a contract is one of two causes, the contract-breaker is liable so long as his breach was an effective cause of the plaintiff’s loss.
iVenture Card Ltd and others v Big Bus Singapore City Sightseeing Pte Ltd and othersCourt of AppealYes[2022] 1 SLR 302SingaporeCited for passages from Heskell and Smile Inc.
Hadley v BaxendaleN/AYes9 Exch 341EnglandCited for the remoteness rule in contract law.
Out of the Box Pte Ltd v Wanin Industries Pte LtdN/AYes[2013] 2 SLR 363SingaporeCited for the two limbs of the remoteness rule in Hadley v Baxendale.
Robertson Quay Investment Pte Ltd v Steen Consultants Pte Ltd and anotherN/AYes[2008] 2 SLR(R) 623SingaporeCited for the two limbs of the remoteness rule in Hadley v Baxendale.
PH Hydraulics & Engineering Pte Ltd v Airtrust (Hong Kong) Ltd and another appealCourt of AppealYes[2017] 2 SLR 129SingaporeCited to support the proposition that courts have recognised that loss of revenue or profits falls under the Second Limb of Hadley v Baxendale.
Multiplex Constructions Pty Ltd v Abgarus Pty LtdN/AYes(1992) 33 NSWLR 504AustraliaCited to support the proposition that courts have recognised that loss of revenue or profits falls under the Second Limb of Hadley v Baxendale.
MFM Restaurants Pte Ltd and another v Fish & Co Restaurants Pte Ltd and another appealCourt of AppealYes[2011] 1 SLR 150SingaporeCited as an example where courts had awarded damages for revenue loss suffered over a period of time following a contractual breach, despite the uncertainty in projecting the expected revenue which could have been earned if there had been no breach.
Fish & Co Restaurants Pte Ltd v MFM Restaurants Pte Ltd and anotherN/AYes[2010] 1 SLR 1104SingaporeCited for the assessment of damages for loss of profits.
Grandison v NovaGold Resources IncN/AYes[2007] BCSC 1780CanadaCited to support the argument that the court should not adopt a method of assessment where too many variables are at play.
Alvin Nicholas Nathan v Raffles Assets (Singapore) Pte LtdCourt of AppealYes[2016] 2 SLR 1056SingaporeCited for the principle that reliance loss is the costs and expenses the claimant incurred in reliance on the defendant’s contracted-for performance, but which were wasted because of the breach of contract.
The “Asia Star”Court of AppealYes[2010] 2 SLR 1154SingaporeCited for the rule that the aggrieved party who goes beyond what the law requires of it and avoids incurring any loss at all will not be entitled to recover any damages.
Turf Club Auto Emporium Pte Ltd and others v Yeo Boong Hua and others and another appealN/AYes[2018] 2 SLR 655SingaporeCited for the principle that if the fact of damage is shown but no evidence is given as to its amount such that it is virtually impossible to assess damages, this will generally permit only an award of nominal damages.
Experience Hendrix LLC v PPX Enterprises IncN/AYes[2003] 1 All ER (Comm) 830EnglandCited for the principle that if the fact of damage is shown but no evidence is given as to its amount such that it is virtually impossible to assess damages, this will generally permit only an award of nominal damages.
Lim Chong Poon v Chiang Sing JeongCourt of AppealYes[2020] SGCA 27SingaporeCited for the principle that where it is clear that substantial loss has been incurred, the fact that an assessment is difficult because of the nature of the loss is no reason for awarding no damages or merely nominal damages.
Recovery Vehicle 1 Pte Ltd v Industries Chimiques Du Senegal and another appeal and another matterN/AYes[2021] 1 SLR 342SingaporeCited for the doctrine of approbation and reprobation bars a claimant from running a case on appeal that is inconsistent with its case in the proceedings below, if that claimant had in fact obtained some benefit from its chosen course in the proceedings below.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Civil Law Act 1909Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Biopolis 3
  • Net Lettable Area
  • Temporary Occupation Permit
  • Combined Delay
  • Holding Costs
  • Site Staff Costs
  • Loss of Chance
  • Multi-Year Model
  • Single-Year Model
  • Stabilised Occupancy
  • Pre-commitment Tenants

15.2 Keywords

  • construction delay
  • damages
  • loss of chance
  • net rental revenue
  • holding costs
  • building contractor
  • property developer

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Contract Law
  • Damages Assessment