DBL v DBM: Appeal against setting aside arbitral award for breach of natural justice in steel trading dispute

DBL appealed against the High Court's decision in DBL v DBM [2023] SGHC 267, which dismissed DBL's application to set aside an arbitral award. The dispute arose from a steel trading contract between DBL and DBM. DBL argued that the arbitral tribunal breached natural justice by considering a demonstration by DBM's counsel and failing to consider two of DBL's defenses. The Court of Appeal dismissed the appeal on 28 March 2024, finding no breach of natural justice that prejudiced DBL.

1. Case Overview

1.1 Court

Court of Appeal of the Republic of Singapore

1.2 Outcome

Appeal Dismissed

1.3 Case Type

Arbitration

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Appeal against High Court's decision to set aside an arbitral award. The Court of Appeal dismissed the appeal, finding no breach of natural justice.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
DBLAppellantCorporationAppeal DismissedLost
DBMRespondentCorporationAppeal DismissedWon

3. Judges

Judge NameTitleDelivered Judgment
Sundaresh MenonChief JusticeYes
Steven ChongJustice of the Court of AppealNo
Judith PrakashSenior JudgeNo

4. Counsels

4. Facts

  1. DBL and DBM were engaged in the business of steel trading.
  2. DBL agreed to sell 19,600 mt of prime steel slabs to DBM under a sales contract.
  3. The sales contract required the steel slabs to be loaded at any port from KSA.
  4. The prime steel slabs were loaded onto the vessel M/V [FP].
  5. The bill of lading stated that 21,430.136 mt of prime steel slabs were loaded on 19 September 2013 at the Dammam Port in the KSA.
  6. DBL issued an invoice to DBM for USD 9,922,152.97.
  7. [FD] Bank notified DBM that it had received information that the Goods had been loaded at Bandar Abbas, Iran.
  8. DBM sought an indemnity from DBL.
  9. DBM informed DBL that it was cancelling the Sales Contract and asked DBL to refund the Purchase Price.
  10. DBL paid a net sum of USD 499,975 to DBM on 7 November 2013.
  11. DBM commenced arbitral proceedings on 24 July 2020.

5. Formal Citations

  1. DBL v DBM, Civil Appeal No 27 of 2023, [2024] SGCA 19
  2. DBL v DBM, , [2023] SGHC 267

6. Timeline

DateEvent
Goods loaded onto the vessel M/V [FP] at Dammam Port in KSA
Appellant issued an invoice to the respondent for USD 9,922,152.97
[FD] Bank notified the respondent that the Goods had been loaded at Bandar Abbas, Iran
Respondent sought an indemnity from the appellant
Appellant provided the respondent with a signed document titled “Indemnity Bond” backdated to 8 September 2013
Respondent informed the appellant that it was cancelling the Sales Contract
Appellant wrote to the respondent stating that it was awaiting payment of the proceeds from the sale of the Goods to another buyer
Appellant paid a net sum of USD 499,975 to the respondent
Respondent commenced arbitral proceedings
Deadline for disclosing demonstrative exhibits
Hearing took place
Hearing took place
Respondent’s counsel carried out the Searoutes Demonstration
Issuance of the Corrected Award
Decision of the High Court judge in DBL v DBM [2023] SGHC 267
Appeal dismissed
Grounds of decision furnished

7. Legal Issues

  1. Breach of Natural Justice
    • Outcome: The court held that there was no breach of natural justice that warranted setting aside the arbitral award.
    • Category: Procedural
    • Sub-Issues:
      • Failure to afford reasonable opportunity to address evidence
      • Failure to consider defenses
    • Related Cases:
      • [2020] 1 SLR 695
      • [2010] 1 SLR 733
      • [2013] 4 SLR 972
      • [2015] 3 SLR 488
      • [2007] 3 SLR(R) 86
      • [2021] 1 SLR 935
      • [2013] 1 SLR 125
  2. Limitation
    • Outcome: The court held that the claims were not time-barred because the acknowledgments given by the appellant extended the time for the running of any applicable limitations period.
    • Category: Substantive
  3. Enforceability of Bond
    • Outcome: The court did not rule on the enforceability of the bond, finding that even if the bond was unenforceable, the outcome of the arbitral proceedings would not have been different.
    • Category: Substantive

8. Remedies Sought

  1. Refund of Purchase Price
  2. Indemnity against losses, costs and penalties
  3. Damages

9. Cause of Actions

  • Breach of Contract
  • Unjust Enrichment

10. Practice Areas

  • Arbitration
  • Commercial Litigation

11. Industries

  • Steel Trading

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
DBL v DBMHigh CourtYes[2023] SGHC 267SingaporeThe High Court decision that was appealed against in this case.
China Machine New Energy Corp v Jaguar Energy Guatemala LLC and anotherCourt of AppealYes[2020] 1 SLR 695SingaporeCited for the principle that a party cannot 'reserve' its position until after the award and only pursue a point if the outcome of the award turns out to be unpalatable to it.
SEF Construction Pte Ltd v Skoy Connected Pte LtdHigh CourtYes[2010] 1 SLR 733SingaporeCited for the principle that natural justice requires that the parties should be heard; it does not require that they be given responses to all submissions made.
TMM Division Maritima SA de CV v Pacific Richfield Marine Pte LtdHigh CourtYes[2013] 4 SLR 972SingaporeCited for the principle that a tribunal is not obliged to deal with every argument as that would be neither practical nor realistic; rather, a tribunal is only required to deal with the essential issues.
AKN and another v ALC and others and other appealsCourt of AppealYes[2015] 3 SLR 488SingaporeCited for the principle that an aggrieved party needed to show that a clear and virtually inescapable inference could be drawn that a tribunal had failed to consider an important pleaded issue before such a finding would be made.
Soh Beng Tee & Co Pte Ltd v Fairmount Development Pte LtdCourt of AppealYes[2007] 3 SLR(R) 86SingaporeCited for the principle that curial intervention would only be justified where an aggrieved party is able to show that there was actual or real prejudice caused by the breach.
CBS v CBPCourt of AppealYes[2021] 1 SLR 935SingaporeCited for the principle that an applicant seeking relief must demonstrate that a different outcome would necessarily have followed but for the breach of natural justice.
L W Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd and another appealCourt of AppealYes[2013] 1 SLR 125SingaporeCited for the principle that the central question is whether, as a result of the breach, the tribunal was denied the benefit of arguments or evidence that had a real as opposed to fanciful chance of making a meaningful difference to the outcome of the arbitral proceedings.
Phoenixfin Pte Ltd and others v Convexity LtdCourt of AppealYes[2022] 2 SLR 23SingaporeCited in support of the position that a more generous approach may be taken towards pleadings in arbitral proceedings, and that pleadings in arbitral proceedings are not determinative in the same way that they might be in court litigation.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
International Arbitration Act 1994Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Arbitral Award
  • Breach of Natural Justice
  • Sales Contract
  • Prime Steel Slabs
  • Dammam Port
  • Indemnity Bond
  • Purchase Price
  • Searoutes Demonstration
  • Limitation Defence
  • Unenforceable Bond Defence

15.2 Keywords

  • arbitration
  • steel trading
  • breach of contract
  • natural justice
  • Singapore

17. Areas of Law

16. Subjects

  • Arbitration
  • Contract Law
  • International Trade