Reliance Infrastructure v. Shanghai Electric: Arbitration Award Challenge Based on Alleged Forgery

The Court of Appeal of Singapore dismissed Reliance Infrastructure Limited's appeal against a decision of the Singapore International Commercial Court (SICC), which had refused to set aside an arbitral award in favor of Shanghai Electric Group Co Ltd. The dispute arose from a Letter of Guarantee related to a construction project in India. Reliance Infrastructure argued that the Guarantee Letter was a forgery and that the arbitral tribunal lacked jurisdiction. The SICC found that Reliance Infrastructure had waived its right to object to the tribunal's jurisdiction and that the alleged forgery was not proven. The Court of Appeal upheld the SICC's decision.

1. Case Overview

1.1 Court

Court of Appeal of the Republic of Singapore

1.2 Outcome

Appeal Dismissed

1.3 Case Type

Arbitration

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Singapore court dismisses Reliance Infrastructure's appeal to set aside an arbitration award, finding waiver of jurisdictional objections regarding an alleged forged guarantee letter.

1.7 Decision Date

2. Parties and Outcomes

3. Judges

Judge NameTitleDelivered Judgment
Sundaresh MenonChief JusticeNo
Steven ChongJustice of the Court of AppealNo
Robert FrenchInternational JudgeYes

4. Counsels

4. Facts

  1. RINFRA argued an arbitral award against it should be set aside due to a forged Guarantee Letter.
  2. RINFRA did not object to the tribunal's jurisdiction based on forgery during arbitration.
  3. RINFRA explicitly stated it was not alleging forgery in its opening submissions to the tribunal.
  4. RINFRA sought to introduce fresh evidence of forgery in the SICC.
  5. The SICC found RINFRA had waived its objection to jurisdiction.
  6. The SICC also found that there was no forgery on the evidence presented.
  7. Mr. Agrawal was described as an 'Authorized Signatory' for RINFRA in a letter dated 4 July 2008.

5. Formal Citations

  1. Reliance Infrastructure Ltd v Shanghai Electric Group Co Ltd, Civil Appeal No 1 of 2024, [2024] SGCA(I) 10

6. Timeline

DateEvent
Mr Agrawal requested deletion of parent company guarantee clause.
Reliance UK entered into a contract with Sasan Power Ltd.
Reliance UK and SEC entered into the Supply Contract.
Guarantee Letter purportedly executed by RINFRA.
Mr Agrawal sent a letter to SEC's Vice President.
Mr Agrawal emailed SEC regarding RIL Guarantee Letter.
Arbitration commenced.
RINFRA made clear it was not alleging forgery in Opening Submissions to the Tribunal.
Oral closing submissions in arbitration.
SEC's counsel clarified details of the Guarantee Letter to the Tribunal.
RINFRA's legal representative sent an email to the Tribunal regarding the Guarantee Letter.
RINFRA updated its Summary Schedule of Issues in the arbitration.
Tribunal inquired about specific findings regarding the Guarantee Letter.
RINFRA's legal representatives stated the Tribunal should declare the Guarantee Letter invalid.
Witnesses cross-examined at SICC hearing.
Court dismissed the appeal against the SICC decision.
Reasons for dismissing the appeal published.

7. Legal Issues

  1. Waiver of Jurisdictional Objection
    • Outcome: The court held that RINFRA had waived its right to challenge the award on the grounds of forgery and want of authority.
    • Category: Procedural
    • Sub-Issues:
      • Actual knowledge of facts underlying jurisdictional objection
      • Failure to raise objection in a timely manner
  2. Validity of Arbitration Agreement
    • Outcome: The court found that the arbitration agreement was valid, as RINFRA had failed to prove forgery and Mr. Agrawal had apparent authority.
    • Category: Substantive
    • Sub-Issues:
      • Forgery of Guarantee Letter
      • Lack of authority to execute arbitration agreement
  3. Public Policy Exception to Arbitration Award Finality
    • Outcome: The court held that the public policy exception did not apply, as RINFRA had disavowed the issue of forgery before the tribunal.
    • Category: Substantive
    • Sub-Issues:
      • Fraud affecting the award
      • Violation of fundamental principles of morality and justice

8. Remedies Sought

  1. Setting Aside of Arbitral Award

9. Cause of Actions

  • Breach of Contract
  • Enforcement of Guarantee

10. Practice Areas

  • Arbitration
  • Commercial Litigation

11. Industries

  • Construction
  • Energy

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Reliance Infrastructure Limited v Shanghai Electric Group Co LtdSingapore International Commercial CourtYes[2024] SGHC(I) 3SingaporeThe current judgment is an appeal of this case. The SICC decision is discussed extensively and ultimately affirmed.
Deutsche Telekom AG v The Republic of IndiaHigh CourtYes[2023] SGHC(I) 7SingaporeCited for the principle of waiver of jurisdictional objections in arbitration, specifically regarding the requirement of actual knowledge of the underlying facts.
BAZ v BBAHigh CourtYes[2020] 5 SLR 266SingaporeCited regarding the use of the doctrine of waiver to preclude a public policy objection.
DFM v DFLCourt of AppealYes[2024] SGCA 41SingaporeCited for the principle that a party cannot stake a certain position before the Tribunal, and then completely change course subsequently when the award is not to its liking.
China Machine New Energy Corp v Jaguar Energy Guatemala LLC and anotherHigh CourtYes[2020] 1 SLR 695SingaporeCited for the principle that a party cannot stake a certain position before the Tribunal, and then completely change course subsequently when the award is not to its liking.
Freeman and Lockyer (a firm) v Buckhurst Park Properties (Mangal) Ltd and anotherQueen's BenchYes[1964] 2 QB 480England and WalesApplied to determine the question of apparent authority to conclude an arbitration agreement.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
UNCITRAL Model Law on International Commercial ArbitrationInternational

15. Key Terms and Keywords

15.1 Key Terms

  • Guarantee Letter
  • Arbitration Award
  • Jurisdictional Objection
  • Waiver
  • Forgery
  • Apparent Authority
  • UNCITRAL Model Law
  • Public Policy
  • SIAC
  • SICC

15.2 Keywords

  • arbitration
  • forgery
  • waiver
  • jurisdiction
  • guarantee
  • singapore
  • construction
  • contract

17. Areas of Law

16. Subjects

  • Arbitration
  • Contract Law
  • Civil Procedure