ICOP Construction v Tiong Seng: Construction Dispute over Microtunneling Works
ICOP Construction (SG) Pte Ltd, a subcontractor, appealed a decision in the Appellate Division of the High Court of Singapore against Tiong Seng Civil Engineering (Pte) Ltd, the main contractor, regarding a construction dispute over microtunneling works. The initial trial was bifurcated, and this appeal concerned liability. The lower court ordered Tiong Seng to pay ICOP $1,333,298.52, and ICOP to pay Tiong Seng $402,790.46 for delay damages, also finding ICOP had wrongfully terminated the subcontract. The Appellate Division allowed the appeal in part, adjusting damages and substituting liquidated damages with general damages.
1. Case Overview
1.1 Court
Appellate Division of the High Court of the Republic of Singapore1.2 Outcome
Appeal allowed in part.
1.3 Case Type
Civil
1.4 Judgment Type
Judgment
1.5 Jurisdiction
Singapore
1.6 Description
Construction dispute between ICOP Construction and Tiong Seng Civil Engineering over microtunneling works. Appeal allowed in part.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
ICOP Construction (SG) Pte Ltd | Appellant, Plaintiff | Corporation | Appeal allowed in part | Partial | |
Tiong Seng Civil Engineering (Pte) Ltd | Respondent, Defendant | Corporation | Counterclaim allowed in part | Partial |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Woo Bih Li | Judge of the Appellate Division | No |
Kannan Ramesh | Judge of the Appellate Division | No |
Quentin Loh | Senior Judge | Yes |
4. Counsels
4. Facts
- ICOP was subcontracted by TSCE to perform microtunneling works for a potable water pipeline project.
- The subcontract was awarded via a letter of award and supplemental letter, backdated to April 15, 2017.
- ICOP was to install 124m of DN1200mm pipe and 2229m of DN1600mm pipe using microtunneling.
- The subcontract outlined four sequential drives with tentative commencement and completion dates.
- The actual timeline deviated substantially from the original schedule.
- ICOP terminated the subcontract on March 13, 2019, citing reasons beyond its control.
- TSCE called on the performance bond after ICOP terminated the subcontract.
5. Formal Citations
- ICOP Construction (SG) Pte Ltd v Tiong Seng Civil Engineering (Pte) Ltd, Civil Appeal No 100 of 2022, [2024] SGHC(A) 1
6. Timeline
Date | Event |
---|---|
TSC engaged by the Public Utilities Board to construct a potable water pipeline. | |
Execution of letter of award and supplemental letter for subcontract between TSCE and ICOP (backdated). | |
TSCE subcontracted the microtunnelling works to ICOP. | |
ICOP commenced pipe jacking for Drive 1. | |
Notice to Proceed for Drive 2 issued. | |
TSCE sent an e-mail to One Smart Engineering Pte Ltd, attaching TSCE’s draft design drawing of the headwall and thrust wall and seeking One Smart’s review and endorsement. | |
One Smart returned the drawing to TSCE with Mr Ng’s endorsement. | |
Resident Technical Officer conducted an inspection of the in-progress construction of the headwall and noted that it passed the inspection. | |
Resident Technical Officer conducted another inspection of the headwall and recorded that it also passed the inspection. | |
Mr Ng visited the worksite and observed that the headwall and the thrust wall for Shaft P5-2 had been installed. | |
TSCE informed ICOP that SP Power requested TSCE to keep a 5m clearance between the existing underground 400kV joint bay and the proposed pipeline. | |
TSCE agreed with ICOP’s suggested amendments to resolve the alignment issue and made the necessary adjustments to the tunnel alignment drawing. | |
ICOP accepted the new alignment on condition that ICOP shall not be liable for any kind of damages or delays incurred either directly or indirectly due to the revised alignment. | |
ICOP commenced MTBM launching work. | |
Second sealing test was conducted, but it also failed. | |
TSCE commenced further rectification works, including the casting of further concrete on the outer joints, grouting works, and pumping of foam in the entrance headwall. | |
A third sealing test was conducted, but it also failed. ICOP formally wrote to TSCE recommending TSCE to construct a new headwall. | |
Further sealing tests were conducted, but they all failed. | |
Further sealing tests were conducted, but they all failed. | |
Further sealing tests were conducted, but they all failed. | |
Further sealing tests were conducted, but they all failed. TSCE called for a meeting with One Smart. | |
A meeting took place between representatives from TSCE, ICOP, BTJV and One Smart. ICOP insisted that TSCE rebuild the headwall to resolve the leakage issues. TSCE eventually agreed to build a new headwall. | |
ICOP removed its jacking equipment and demobilised from Shaft P5-2. | |
Shaft P5-2 was handed back to TSCE for TSCE to rebuild the headwall. | |
TSCE completed the reconstruction of the headwall and returned Shaft P5-2 to ICOP. | |
A further sealing test of the rebuilt headwall was conducted successfully. | |
ICOP commenced pipe jacking works from Shaft P5-2 to Shaft P5-1. | |
TSCE informed ICOP that the site’s noise levels exceeded the applicable limits. | |
TSCE’s project manager, Mr Jesse Jung Jae Hun, informed ICOP’s Mr Alberini that there might be some problems regarding the exit wall and the recovery of the MTBM in Shaft P5-1. | |
TSCE’s Site Engineer, Mr Peter Castillo informed ICOP’s Mr Alberini that after superimposing the receiving cradle and pipe jacking machine in the as-built layout plan for the Shaft P5-1, Mr Castillo found that the cutter head of the MTBM would collide with the end valve after the MTBM fully breaks through Shaft P5-1. | |
ICOP stated in a letter that as per Appendix F of the Subcontract, the minimum wall to wall distance required for Shaft P5-1 should be 7.5m. | |
The recovery of the MTBM was completed. ICOP demobilised the MTBM and dispatched the MTBM to Malaysia. | |
ICOP terminated the Subcontract. | |
Judgment reserved. | |
Hearing date. | |
Judgment date. |
7. Legal Issues
- Breach of Contract
- Outcome: The court found that ICOP had wrongfully terminated the Subcontract. The court also found that both ICOP and TSCE had breached the contract, leading to delay damages.
- Category: Substantive
- Sub-Issues:
- Wrongful Termination
- Delay Damages
- Failure to comply with noise restrictions
- Failure to supply sufficient pipes
- Supply of poor-quality pipes
- Failure to timeously carry out waste disposal
- Delay Damages
- Outcome: The court found both ICOP and TSCE liable for delay damages, adjusting the amounts and substituting liquidated damages with general damages.
- Category: Substantive
- Sub-Issues:
- Critical Delay
- Concurrent Delay
- Liquidated Damages
- General Damages
- Performance Bond
- Outcome: The court found that TSCE's call on the performance bond was justified because ICOP had breached the Subcontract.
- Category: Substantive
8. Remedies Sought
- Monetary Damages
- Return of Performance Bond Amount
9. Cause of Actions
- Breach of Contract
- Wrongful Termination
10. Practice Areas
- Construction Law
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
ICOP Construction (SG) Pte Ltd v Tiong Seng Civil Engineering Pte Ltd | High Court | No | [2022] SGHC 257 | Singapore | Cited for the Judge's detailed explanation of the microtunnelling process. |
Sembcorp Marine Ltd v PPL Holdings Pte Ltd and another and another appeal | Court of Appeal | Yes | [2013] 4 SLR 193 | Singapore | Cited for the requirements for the implication of terms in a contract. |
V Nithia (co-administratrix of the estate of Ponnusamy Sivapakiam, deceased) v Buthmanaban s/o Vaithilingam and another | Court of Appeal | Yes | [2015] 5 SLR 1422 | Singapore | Cited for the general rule that parties are bound by their pleadings. |
Saga Cruises BDF Ltd and another v Fincantieri SPA (formerly Fincantieri Cantieri Navali Italiani SPA) | High Court of Justice | No | [2016] EWHC 1875 (Comm) | England and Wales | Cited for the proposition that where there are concurrent causes of delay, any critical delay is caused by the event which is first in time. |
Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester) Ltd | Technology and Construction Court | No | (1999) 70 ConLR 32 | England and Wales | Cited for the principle that where there are concurrent causes for a delay, the contractor is entitled to an extension of time, but cannot recover damages for the delay. |
Walter Lilly & Company Ltd v Mackay | High Court of Justice | No | [2012] EWHC 1773 | England and Wales | Cited for the principle that where there are concurrent causes for a delay, the contractor is entitled to an extension of time, but cannot recover damages for the delay. |
Hadley v Baxendale | Court of Exchequer | Yes | (1854) 9 Ex 341 | England and Wales | Cited for the rules on causation, mitigation and remoteness of damage. |
Crescendas Bionics Pte Ltd v Jurong Primewide Pte Ltd | Court of Appeal | Yes | [2023] 1 SLR 536 | Singapore | Cited for the principle that delay damages can sound in reliance loss. |
Crescendas Bionics Pte Ltd v Jurong Primewide Pte Ltd | High Court | Yes | [2019] SGHC 4 | Singapore | Cited for the principle that in the absence of an extension of time clause, an act of prevention by the contractor would set time at large and the subcontractor’s obligation is to complete the project within a reasonable time. |
Fongsoon Engineering (S) Pte Ltd v Kensteel Engineering Pte Ltd | High Court | Yes | [2011] SGHC 82 | Singapore | Cited for the principle that even though time for completion is at large, the contractor has to complete the works within a reasonable period. |
Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd | Court of Appeal | Yes | (1970) 1 BLR 114 | England and Wales | Cited for the principle that even though time for completion is at large, the contractor has to complete the works within a reasonable period. |
Balfour Beatty Construction Ltd v London Borough of Lambeth | Court of Appeal | Yes | [2002] 1 BLR 288 | England and Wales | Cited for the principle that even though time for completion is at large, the contractor has to complete the works within a reasonable period. |
V Nithia (co-administratrix of the estate of Ponnusamy Sivapakiam, deceased) v Buthmanaban s/o Vaithilingam and another | Court of Appeal | Yes | [2015] 5 SLR 1422 | Singapore | Cited for the general rule that parties are bound by their pleadings. |
Wei Ho-Hung v Lyu Jun | Court of Appeal | Yes | [2022] 2 SLR 1066 | Singapore | Cited for the principle that a party cannot mount a new case on appeal. |
Diamond Glass Enterprise Pte Ltd v Zhong Kai Construction Co Pte Ltd | High Court | Yes | [2022] SGHC(A) 44 | Singapore | Cited for the principle that a party can justify its termination on non-payment. |
RDC Concrete Pte Ltd v Sato Kogyo (S) Pte Ltd and another appeal | Court of Appeal | Yes | [2007] 4 SLR(R) 413 | Singapore | Cited for the principle that a party can terminate the contract if the contract clearly and unambiguously states that, in the event of a certain event of events occurring, the innocent party will be entitled to terminate the contract. |
Jia Min Building Construction Pte Ltd v Ann Lee Pte Ltd | High Court | Yes | [2004] 3 SLR(R) 288 | Singapore | Cited for the principle that a temporary slowdown in the progress of works will not invariably be viewed as contractual repudiation. |
Chattan Developments Ltd v Reigill Civil Engineering Contractors Ltd | Technology and Construction Court | Yes | [2007] EWHC 305 (TCC) | England and Wales | Cited for the principle that a liquidated damages clause excludes unliquidated damages. |
Biffa Waste Services Ltd v Maschinenfabrik Ernst Hese GmbH | Technology and Construction Court | Yes | [2008] EWHC 6 (TCC) | England and Wales | Cited for the principle that a liquidated damages clause excludes unliquidated damages. |
Alliance Concrete Singapore Pte Ltd v Comfort Resources Pte Ltd | Court of Appeal | Yes | [2009] 4 SLR(R) 602 | Singapore | Cited for the principle that a breach by A would only assist B if it was still continuing when A purported to treat B as having repudiated the contract and if the effect of A’s subsisting breach was such as to preclude A from claiming that B had committed a repudiatory breach. |
Jet Holding Ltd v Cooper Cameron (Singapore) Pte Ltd | Court of Appeal | Yes | [2006] 3 SLR(R) 769 | Singapore | Cited for the principle that a breach by A would only assist B if it was still continuing when A purported to treat B as having repudiated the contract and if the effect of A’s subsisting breach was such as to preclude A from claiming that B had committed a repudiatory breach. |
Cheng Poh Building Construction Pte Ltd v First City Builders Pte Ltd | Court of Appeal | Yes | [2003] 2 SLR(R) 170 | Singapore | Cited for the principle that a stay on the execution of sums awarded in ICOP’s claims pending the second tranche of the Suit is warranted. |
UBQ v UBR and another matter | High Court | Yes | [2023] SGHC(A) 10 | Singapore | Cited for the principle that an appellate court would generally be slow to criticise a trial court’s findings on expert evidence, unless it entertains doubts as to whether the evidence has been satisfactorily sifted or assessed by the trial court. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Evidence Act 1893 | Singapore |
Environmental Protection and Management Act 1999 | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Microtunneling
- Subcontract
- Headwall
- MTBM
- Performance Bond
- Delay Damages
- Critical Delay
- Liquidated Damages
- General Damages
- Authorities’ Approvals
- Noise Restrictions
15.2 Keywords
- construction
- microtunneling
- breach of contract
- delay damages
- performance bond
- Singapore
17. Areas of Law
Area Name | Relevance Score |
---|---|
Construction Law | 85 |
Performance Bond | 75 |
Contract Law | 70 |
Termination | 60 |
Damages | 50 |
Remedies | 30 |
Evidence | 25 |
Banking and Finance | 20 |
Arbitration | 15 |
Civil Procedure | 10 |
16. Subjects
- Construction Dispute
- Contract Law
- Civil Procedure
- Performance Bonds