Seatrium New Energy v HJ Shipbuilding: Contractual Terms, Warranties & Estoppel
Seatrium New Energy Ltd (formerly known as Keppel FELS Ltd) appealed against the decision of the High Court of Singapore dismissing its claim against HJ Shipbuilding & Construction Co, Ltd (formerly known as Hanjin Heavy Industries and Construction Co Ltd) for defective work carried out by Hanjin pursuant to a subcontract between them in relation to a vessel. The Appellate Division of the High Court dismissed the appeal, holding that Seatrium's claim was precluded by the 5th paragraph of a Letter Agreement and that the warranty period had expired before the defects were discovered. The court also found that Hanjin was not estopped from denying liability and did not owe Seatrium a separate tortious duty of care.
1. Case Overview
1.1 Court
Appellate Division of the High Court of the Republic of Singapore1.2 Outcome
Appeal Dismissed
1.3 Case Type
Civil
1.4 Judgment Type
Ex tempore judgment
1.5 Jurisdiction
Singapore
1.6 Description
Appeal dismissed. The court held that Seatrium's claim was precluded by a contractual term and the warranty period had expired.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Seatrium New Energy Ltd (formerly known as Keppel FELS Ltd) | Appellant | Corporation | Appeal Dismissed | Lost | |
HJ Shipbuilding & Construction Co, Ltd (formerly known as Hanjin Heavy Industries and Construction Co Ltd) | Respondent | Corporation | Appeal Dismissed | Won |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Kannan Ramesh | Judge of the Appellate Division | Yes |
See Kee Oon | Judge of the Appellate Division | No |
Philip Jeyaretnam | Judge of the High Court | No |
4. Counsels
4. Facts
- Seatrium contracted with Floatel to build and deliver an accommodation support vessel.
- Seatrium subcontracted the fabrication, assembly, and erection of the vessel's pontoons and lower columns to Hanjin.
- Hanjin did not meet the original deadline to complete the works.
- Seatrium and Hanjin entered into a Side Letter, effectively a variation of the Sub-Contract.
- Seatrium completed the outstanding works and delivered the Vessel to Floatel on 16 April 2015.
- Floatel notified Seatrium of defects in the Vessel in mid-August 2016.
- Seatrium put Hanjin on notice of the defects on 24 August 2016.
- Hanjin asserted that Seatrium’s claim was subject to the warranty period which had since expired.
5. Formal Citations
- Seatrium New Energy Ltd (formerly known as Keppel FELS Ltd) v HJ Shipbuilding & Construction Co, Ltd (formerly known as Hanjin Heavy Industries and Construction Co Ltd), Civil Appeal No 131 of 2023, [2024] SGHC(A) 26
6. Timeline
Date | Event |
---|---|
Agreement between Seatrium and Floatel International Ltd to build and deliver an accommodation support vessel. | |
Seatrium subcontracted the fabrication, assembly and erection of the pontoons and lower columns of the Vessel to HJ Shipbuilding & Construction Co, Ltd. | |
Original deadline for Hanjin to complete the Works. | |
Parties entered into a Side Letter, effectively a variation of the Sub-Contract. | |
Seatrium completed the outstanding works and delivered the Vessel to Floatel. | |
Floatel notified Seatrium of defects in the Vessel around mid-August 2016. | |
Seatrium put Hanjin on notice of the defects. | |
Hanjin replied that Seatrium’s claim was subject to the expired warranty period. | |
Vessel berthed for inspection in Rotterdam. | |
Inspection of Vessel completed in Rotterdam. | |
Seatrium attempted to discuss defects and repairs with Hanjin. | |
Seatrium attempted to discuss defects and repairs with Hanjin. | |
Seatrium sent a letter to Hanjin stating its position that Hanjin had breached its contractual and tortious duties. | |
Seatrium resolved further defects after another round of inspection and repairs. | |
Judge’s decision reported at Seatrium New Energy Ltd (formerly known as Keppel FELS Ltd) v HJ Shipbuilding & Construction Co, Ltd (formerly known as Hanjin Heavy Industries and Construction Co Ltd) [2023] SGHC 264. | |
Civil Appeal No 131 of 2023 filed. | |
Judgment delivered. |
7. Legal Issues
- Breach of Contract
- Outcome: The court held that Seatrium's claim for breach of contract was precluded by the 5th paragraph of the Letter Agreement, save for a warranty claim under the Sub-Contract.
- Category: Substantive
- Sub-Issues:
- Defective Work
- Failure to Complete Works
- Warranty Obligations
- Outcome: The court held that Hanjin was not liable under its warranty obligations as the warranty had expired before the defects were discovered.
- Category: Substantive
- Sub-Issues:
- Latent Defects
- Warranty Period
- Promissory Estoppel
- Outcome: The court held that Hanjin was not estopped from denying liability for breach of the Sub-Contract.
- Category: Substantive
- Duty of Care in Tort
- Outcome: The court held that Hanjin did not owe Seatrium a separate tortious duty of care that was co-terminous with its contractual duties.
- Category: Substantive
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
- Negligence
10. Practice Areas
- Commercial Litigation
- Construction Disputes
11. Industries
- Construction
- Maritime
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Seatrium New Energy Ltd (formerly known as Keppel FELS Ltd) v HJ Shipbuilding & Construction Co, Ltd (formerly known as Hanjin Heavy Industries and Construction Co Ltd) | High Court | Yes | [2023] SGHC 264 | Singapore | The current appeal is against the decision in this case. |
GTMS Construction Pte Ltd v Ser Kim Koi (Chan Sau Yan (formerly trading as Chan Sau Yan Associates) and another, third parties) | High Court | Yes | [2021] SGHC 9 | Singapore | Cited for the principle that the warrantee may activate or enforce the warranty by calling upon the warrantor to make the necessary repairs or rectifications. |
Management Corporation Strata Title Plan No 3556 (suing on behalf of itself and all subsidiary proprietors of Northstar @ AMK) v Orion-One Development Pte Ltd (in liquidation) and another | High Court | Yes | [2020] 3 SLR 373 | Singapore | Cited for the principle that if defects go unrectified, then the warrantor would be in breach of the warranty, and the warrantee is entitled to seek compensation for the loss caused by the breach. |
Management Corporation Strata Title No 964 v Gordon Industrial Land Pte Ltd and another | High Court | Yes | [1998] SGHC 365 | Singapore | Cited for the principle that if defects go unrectified, then the warrantor would be in breach of the warranty, and the warrantee is entitled to seek compensation for the loss caused by the breach. |
Gorski v General Motors of Canada Ltd | British Columbia Supreme Court | Yes | [1998] BCJ No 3106 | Canada | Cited for the principle that a warranty does not cover latent defects that are brought to the defendant’s attention after the expiration of the warranty period. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Sub-Contract Works
- Warranty Period
- Letter Agreement
- Side Letter
- Outstanding Items
- Latent Defects
- Warranty Obligations
15.2 Keywords
- Contractual Terms
- Warranties
- Promissory Estoppel
- Duty of Care
- Defective Work
- Construction Dispute
17. Areas of Law
Area Name | Relevance Score |
---|---|
Contractual terms | 95 |
Breach of Contract | 90 |
Contracts | 90 |
Equitable Estoppel | 80 |
Torts | 70 |
Negligence | 70 |
Misrepresentation | 60 |
Commercial Disputes | 50 |
Damages Assessment | 40 |
Personal Injury | 30 |
16. Subjects
- Contract Law
- Construction Law
- Warranty
- Estoppel
- Tort