L & W Building Construction v King Wah Construction: Defective Works Dispute

In L & W Building Construction Pte Ltd v King Wah Construction Pte Ltd, the High Court of Singapore heard an appeal by L & W Building Construction Pte Ltd against the decision of the Assistant Registrar, who had granted summary judgment to King Wah Construction Pte Ltd for $342,350 related to defective works. Woo Bih Li JC allowed the appeal, set aside the Assistant Registrar's decision, and ordered a stay of proceedings pending arbitration, due to an existing arbitration provision in the contract and disputes regarding the alleged defective works.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Appeal Allowed, Stay of Proceedings Ordered Pending Arbitration

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Dispute over defective works in a construction project. The court stayed proceedings pending arbitration, reversing the Assistant Registrar's decision.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
L & W Building Construction Pte LtdAppellant, DefendantCorporationAppeal AllowedWonEdwin Lee
King Wah Construction Pte LtdRespondent, PlaintiffCorporationAppeal DismissedLostRaymond Chan, Spring Tan

3. Judges

Judge NameTitleDelivered Judgment
Woo Bih LiJudicial CommissionerYes

4. Counsels

Counsel NameOrganization
Edwin LeeChong Yeo & Partners
Raymond ChanChan Tan & Partners
Spring TanChan Tan & Partners

4. Facts

  1. L & W Building Construction was the developer of a 4-story factory.
  2. King Wah Construction was the main contractor for the project.
  3. The architect issued a Completion Certificate on 6 November 1998.
  4. A dispute arose regarding outstanding defective works.
  5. The architect called for tenders for rectification works and awarded the works for $342,350.
  6. The architect issued a Final Certificate deducting $342,350 for defective works.
  7. L & W Building Construction paid $199,406.70 to King Wah Construction prior to the hearing.

5. Formal Citations

  1. L & W Building Construction Pte Ltd v King Wah Construction Pte Ltd, Suit 433/2000/K, RA 43/2000 and 44/2000, [2000] SGHC 246

6. Timeline

DateEvent
Contract signed
Completion Certificate issued
Architect called for tenders for rectification works
Certificate of Payment (Final) No 16 issued
Revised Certificate No 16A issued
Judgment issued

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court did not make a definitive ruling on the breach of contract issue, as the proceedings were stayed pending arbitration.
    • Category: Substantive
  2. Validity of Architect's Certificate
    • Outcome: The court found that the architect's certificate was valid for the purpose of determining the sum due, but the deduction for defective works was subject to arbitration.
    • Category: Substantive
  3. Stay of Proceedings Pending Arbitration
    • Outcome: The court allowed the appeal and ordered a stay of proceedings pending arbitration, recognizing the arbitration provision in the contract.
    • Category: Procedural

8. Remedies Sought

  1. Monetary Damages

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Construction Disputes
  • Commercial Litigation
  • Arbitration

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Lojan Properties Pte Ltd v Tropicon Contractors Pte LtdCourt of AppealYes[1991] 2 MLJ 70SingaporeCited regarding the requirements for a valid Certificate of Cost of Other Contractor’s Work (COCW) and the exclusion of the right to set-off.
Lojan Properties Pte Ltd v Tropicon Contractors Pte LtdHigh CourtYes[1989] 3 MLJ 216SingaporeCited for the background facts of the Lojan Properties case and the High Court's initial decision regarding the validity of interim certificates and the costs of rectification works.
James Png Construction Pte Ltd v Tsu Chin Kwan PeterHigh CourtYes[1991] 1 MLJ 449SingaporeCited to distinguish the facts from the present case, noting that the final certificate in that case certified the sum due, unlike the present case.
Kum Leng General Contractor v Hytech Builders Pte LtdHigh CourtYes[1996] 1 SLR 751SingaporeCited to distinguish the facts from the present case, noting that the deductions in that case were made before the issuance of the required architect's certificate.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
No applicable statutes

15. Key Terms and Keywords

15.1 Key Terms

  • Defective Works
  • Final Certificate
  • Arbitration
  • Certificate of Payment
  • Conditions of Contract
  • Rectification Works

15.2 Keywords

  • construction
  • defective works
  • arbitration
  • contract
  • singapore

16. Subjects

  • Construction Dispute
  • Contract Law
  • Arbitration

17. Areas of Law

  • Construction Law
  • Contract Law
  • Arbitration Law
  • Civil Procedure