Samwoh Asphalt v Sum Cheong Piling: Unconscionability in Performance Guarantee Call
Samwoh Asphalt Premix Pte Ltd (Samwoh) appealed a High Court decision allowing Sum Cheong Piling Private Ltd (SC Piling) to discharge an interim injunction that restrained SC Piling from calling on a performance guarantee issued by ECICS-COFACE Guarantee Company (Singapore) Ltd (ECICS). The Court of Appeal found that SC Piling acted unconscionably in calling on the performance guarantee, as the call was not based on a bona fide claim but rather used as a bargaining chip. The court allowed the appeal, ordering SC Piling to repay the amount received under the guarantee and restoring the injunction.
1. Case Overview
1.1 Court
Court of Appeal1.2 Outcome
Appeal allowed.
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Appeal regarding an interim injunction restraining Sum Cheong Piling from calling on a performance guarantee. The court found Sum Cheong Piling's conduct unconscionable.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Samwoh Asphalt Premix Pte Ltd | Appellant | Corporation | Appeal Allowed | Won | |
Sum Cheong Piling Private Limited | Respondent | Corporation | Appeal Dismissed | Lost | |
ECICS-COFACE Guarantee Company (Singapore) Ltd | Respondent | Corporation | Neutral | Neutral |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Chao Hick Tin | Judge of Appeal | Yes |
L P Thean | Judge of Appeal | No |
4. Counsels
4. Facts
- SC Piling were the main contractors for the construction of a runway at Changi East.
- Samwoh was the nominated sub-contractor for runway pavement works.
- Samwoh furnished a performance guarantee for S$500,000 in favor of SC Piling.
- The runway experienced excessive water content in the sub-soil, impeding Samwoh's work.
- Samwoh terminated the subsidiary sub-contract due to Gim Chuan's failure to rectify the water problem.
- SC Piling and Samwoh negotiated a new contract, but negotiations failed.
- SC Piling called on the performance guarantee after negotiations failed and without making a claim for damages.
5. Formal Citations
- Samwoh Asphalt Premix Pte Ltd v Sum Cheong Piling Private Limited and Another, CA 600052/2001, [2001] SGCA 79
6. Timeline
Date | Event |
---|---|
Performance guarantee issued by ECICS in favor of SC Piling for Samwoh's account. | |
Runway flooded, impeding Samwoh's work. | |
Samwoh raised concerns about excessive water content with SC Piling and Gim Chuan. | |
Site discussion held regarding the wetness problem. | |
Samwoh terminated the subsidiary sub-contract with Gim Chuan. | |
SC Piling wrote to PWD Consultants regarding the water content problem. | |
PWD Consultants responded to SC Piling's letter. | |
Representatives from Samwoh and SC Piling met at SC Piling's office. | |
Samwoh wrote to SC Piling regarding site drainage problems. | |
SC Piling wrote to Samwoh requesting mobilization of a paving team. | |
Further meeting between Samwoh and SC Piling representatives. | |
Samwoh wrote to SC Piling outlining conditions for mobilization. | |
Samwoh mobilized a paving team to the site. | |
Samwoh wrote to SC Piling clarifying conditions for continued presence at the site and discontinued their work. | |
SC Piling made a demand on ECICS for payment under the performance guarantee. | |
Samwoh obtained an interim injunction restraining ECICS from paying SC Piling. | |
The judge allowed SC Piling's application and set aside the interim injunction. | |
Court of Appeal allowed the appeal. |
7. Legal Issues
- Unconscionability
- Outcome: The court found that SC Piling acted unconscionably in calling on the performance guarantee.
- Category: Substantive
- Sub-Issues:
- Abusive call on performance guarantee
- Bargaining chip
- Related Cases:
- [1995] 2 SLR 733
- [1999] 2 SLR 368
- [1999] 4 SLR 604
- [2000] 1 SLR 657
8. Remedies Sought
- Injunctive Relief
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Commercial Litigation
- Construction Law
- Performance Bonds
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Bocotra Construction Pte Ltd and Ors v A-G (No 2) | N/A | Yes | [1995] 2 SLR 733 | Singapore | Cited as precedent for unconscionability being a separate ground from fraud for seeking injunctive relief in performance guarantee cases. |
Min Thai Holdings Pte Ltd v Sunlabel Pte Ltd & Anor | N/A | Yes | [1999] 2 SLR 368 | Singapore | Cited as precedent for unconscionability being a separate ground from fraud for seeking injunctive relief in performance guarantee cases. |
GHL Pte Ltd v Unitrack Building Construction Pte Ltd & Anor | N/A | Yes | [1999] 4 SLR 604 | Singapore | Cited as precedent for unconscionability being a separate ground from fraud for seeking injunctive relief in performance guarantee cases. |
Dauphin Offshore Engineering & Trading Pte Ltd v The Private Office of HRH Sheikh Sultan bin Khalifa bin Zayed Al Nahyan | N/A | Yes | [2000] 1 SLR 657 | Singapore | Cited as precedent for unconscionability being a separate ground from fraud for seeking injunctive relief in performance guarantee cases. |
Kvaerner Singapore Pte Ltd v UDL Shipbuilding (Singapore) Pte Ltd | N/A | Yes | [1993] 3 SLR 350 | Singapore | Cited for the principle that a demand under a performance guarantee can only be made when the seller has failed or refused to fulfill his obligations under the contract. |
Credit Agricole Indosuez v Banque Nationale de Paris (No 2) | N/A | Yes | [2001] 2 SLR 301 | Singapore | Cited as authority for awarding interest. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Performance guarantee
- Unconscionability
- Interim injunction
- Subsidiary sub-contract
- Excessive water content
- Bona fide claim
- Bargaining chip
15.2 Keywords
- performance guarantee
- unconscionability
- injunction
- construction
- contract
17. Areas of Law
Area Name | Relevance Score |
---|---|
Unconscionability | 98 |
Performance Bond | 95 |
Contract Law | 90 |
Injunctions | 80 |
Erinford Injunction | 60 |
Construction | 50 |
Commercial Disputes | 40 |
16. Subjects
- Contract Law
- Construction Law
- Performance Bonds
- Injunctions