Liang Huat Aluminium v Hi-Tek Construction: Performance Bond Call Dispute

In a dispute between Liang Huat Aluminium Industries Pte Ltd and Hi-Tek Construction Pte Ltd, the High Court of Singapore, on 8 November 2001, dismissed Liang Huat's application to restrain Hi-Tek from calling on a performance bond. Liang Huat sought the injunction, arguing that Hi-Tek's call on the bond was unconscionable. The court, however, found that Liang Huat failed to establish a strong prima facie case of unconscionability, leading to the dismissal of the application and the discharge of the interim injunction.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Application dismissed and interim injunction order discharged

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

The High Court dismissed Liang Huat's application to restrain Hi-Tek from calling on a performance bond, finding no unconscionability.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Liang Huat Aluminium Industries Pte LtdPlaintiff, ApplicantCorporationApplication dismissedLostGoh Phai Cheng, Cheah Kok Lim
Hi-Tek Construction Pte LtdDefendantCorporationJudgment for DefendantWonChoy Chee Yean, Leo Tan

3. Judges

Judge NameTitleDelivered Judgment
Woo Bih LiJudicial CommissionerYes

4. Counsels

Counsel NameOrganization
Goh Phai ChengAng & Partners
Cheah Kok LimAng & Partners
Choy Chee YeanRajah & Tann
Leo TanRajah & Tann

4. Facts

  1. Hi-Tek was the main contractor for an office extension at Amara Hotel and Shopping Centre.
  2. Liang Huat was the nominated sub-contractor for the design, supply, and installation of aluminium cladding, windows, and glazing.
  3. Liang Huat procured a Performance Bond for $538,000 in favour of Hi-Tek.
  4. Hi-Tek made a call on the Bond on 20 September 2001.
  5. Liang Huat commenced a Writ action on 25 July 2001 and applied for summary judgment on 17 September 2001 for payment on interim certificates.
  6. A completion certificate for the main contract had been issued.

5. Formal Citations

  1. Liang Huat Aluminium Industries Pte Ltd v Hi-Tek Construction Pte Ltd, OS 601411/2001, SIC 602171/2001, [2001] SGHC 334

6. Timeline

DateEvent
Performance Bond issued by The Nanyang Insurance Company Limited in favour of Hi-Tek
Delay certificate issued in respect of Phase 4 of the main contract
Completion certificate for the main contract issued
Liang Huat submitted Application for Payment No 35
Quantity Surveyor's valuation as at this date
Interim Certificate No 30 for the main contract issued
Liang Huat commenced a Writ action
Sub-contract delay certificate issued to Liang Huat in respect of Phase 4
Interim certificate No 31 issued
Certificate of Payment of Main Contractor issued by the Architects
Liang Huat applied for summary judgment
Hi-Tek made a call on the Bond
Interim injunction order granted pending further arguments
Arguments presented
Application dismissed and interim injunction order discharged
Decision Date

7. Legal Issues

  1. Unconscionability
    • Outcome: The court found that Liang Huat had failed to establish a strong prima facie case of unconscionability.
    • Category: Substantive
  2. Call on Performance Bond
    • Outcome: The court allowed Hi-Tek to call on the performance bond.
    • Category: Substantive

8. Remedies Sought

  1. Declaration that Hi-Tek shall not be entitled to call on or demand payment under the Bond
  2. Injunction to restrain Hi-Tek from calling or demanding payment under the Bond

9. Cause of Actions

  • Injunction to restrain calling on performance bond

10. Practice Areas

  • Construction Litigation
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Dauphin caseN/AYes[2000] 1 SLR 657SingaporeCited for the legal principle that a beneficiary of a performance bond may be restrained from calling for payment if it would be unconscionable to do so, and that the applicant seeking such relief must establish a strong prima facie case of unconscionability.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
No applicable statutes

15. Key Terms and Keywords

15.1 Key Terms

  • Performance Bond
  • On-demand bond
  • Unconscionability
  • Interim Certificates
  • Retention Monies
  • Sub-Contract Works
  • Delay Damages
  • Completion Certificate

15.2 Keywords

  • Performance Bond
  • Construction
  • Injunction
  • Unconscionability
  • Singapore
  • High Court

16. Subjects

  • Construction Dispute
  • Performance Bonds
  • Contract Law

17. Areas of Law

  • Construction Law
  • Contract Law
  • Injunctions
  • Performance Bonds