Permasteelisa v Hyundai: Arbitration Award Recourse & Misconduct Claim
In Permasteelisa Pacific Holdings Ltd v Hyundai Engineering and Construction Co Ltd, the Singapore High Court heard an application by Permasteelisa (PISA) against Hyundai, seeking to set aside or appeal an arbitration award related to a sub-contract for curtain-walling and glazing works. PISA alleged arbitrator misconduct and sought leave to appeal on questions of law. The High Court allowed the application in part, remitting certain matters to the arbitrator for reconsideration, including the apportionment of liquidated damages, the claim for additional preliminaries, the balance of work done, and the claim for the cost of replacement of original stayarms.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Application allowed in part. Certain matters remitted to the arbitrator for reconsideration.
1.3 Case Type
Arbitration
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
High Court case regarding recourse against an arbitration award. PISA sought to set aside the award based on arbitrator misconduct.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Permasteelisa Pacific Holdings Ltd | Applicant | Corporation | Application allowed in part | Partial | |
Hyundai Engineering and Construction Co Ltd | Respondent | Corporation | Application dismissed in part | Partial |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Judith Prakash | Judge | Yes |
4. Counsels
Counsel Name | Organization |
---|---|
Monica Neo | ChanTan LLC |
George Tan | ChanTan LLC |
Tan Liam Beng | Drew and Napier LLC |
4. Facts
- Hyundai was the main contractor for a construction project.
- PISA was engaged as the nominated sub-contractor for curtain-walling and glazing.
- Disputes arose between PISA and Hyundai regarding the sub-contract works.
- PISA claimed the works were completed by November 15, 2000.
- Hyundai alleged the works were incomplete due to scratched glass panels.
- An arbitrator was appointed to resolve the disputes.
- The arbitrator awarded Hyundai $1,463,481.55 on its counterclaim.
5. Formal Citations
- Permasteelisa Pacific Holdings Ltd v Hyundai Engineering and Construction Co Ltd, OM 5/2004, [2005] SGHC 33
6. Timeline
Date | Event |
---|---|
Sub-contract works commencement date | |
Sub-contract dated | |
Original completion date for main contract works | |
PISA claimed sub-contract works completed | |
PISA gave notice to Hyundai of intention to refer disputes to arbitration | |
President of the SIA appointed Mr Johnny Tan Cheng Hye as the sole arbitrator | |
Architect granted extension of time for the Sub-Contract Completion Date to 31 July 2001 | |
Arbitration hearing began | |
Arbitration hearing concluded | |
Arbitrator delivered the Award | |
PISA filed proceedings seeking to set aside the Award | |
Arbitrator corrected the Award | |
Judgment reserved |
7. Legal Issues
- Misconduct of Arbitration Proceedings
- Outcome: The court found that the arbitrator had misconducted the proceedings in certain instances, including the apportionment of liquidated damages and the failure to make an award for the balance of work done.
- Category: Procedural
- Sub-Issues:
- Failure to consider relevant evidence
- Reliance on inadmissible evidence
- Failure to provide opportunity to rebut evidence
- Interpretation of Contract Clauses
- Outcome: The court granted leave to appeal on the question of whether it was necessary for a sub-contractor to object to the classification of the architect’s instructions or directions before the arbitrator was entitled to review a claim made by the sub-contractor for variations.
- Category: Substantive
- Sub-Issues:
- Interpretation of completion certificate clause
- Interpretation of temporary protection clause
- Interaction of sub-contract and main contract conditions
- Leave to Appeal on Questions of Law
- Outcome: The court granted leave to appeal on one question of law and denied leave to appeal on other questions of law.
- Category: Procedural
- Sub-Issues:
- Determination of a question of law
- Substantial effect on the rights of the parties
- Clarity and certainty of Singapore law
- Causation of Delay
- Outcome: The court remitted the matter to the arbitrator to determine the extent to which PISA's delay caused or contributed to the overall project delay.
- Category: Substantive
- Sub-Issues:
- Contribution to overall project delay
- Apportionment of liquidated damages
8. Remedies Sought
- Setting aside of arbitration award
- Leave to appeal on questions of law
- Remission of matter to arbitrator
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Arbitration
- Construction Disputes
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Pioneer Shipping Ltd v BTP Tioxide Ltd | N/A | Yes | [1982] AC 724 | N/A | Cited for principles to be applied regarding leave to appeal to the court under s 28 of the Act. |
Hong Huat Development Co (Pte) Ltd v Hiap Hong & Co Pte Ltd | Court of Appeal | Yes | [2000] 2 SLR 609 | Singapore | Cited for principles to be applied regarding leave to appeal to the court under s 28 of the Act. |
Northern Elevator Manufacturing Sdn Bhd v United Engineers (Singapore) Pte Ltd (No 2) | Court of Appeal | Yes | [2004] 2 SLR 494 | Singapore | Cited for principles to be applied regarding leave to appeal to the court under s 28 of the Act and clarification of what constitutes a 'question of law'. |
Ahong Construction (S) Pte Ltd v United Boulevard Pte Ltd | N/A | Yes | [2000] 1 SLR 749 | Singapore | Cited for the definition of a 'question of law' in the context of arbitration appeals. |
Italmare Shipping Co v Ocean Tanker Co Inc (The Rio Sun) | N/A | Yes | [1981] 2 Lloyd’s Rep 489 | N/A | Cited to show a rejected view that the application of law to facts can raise a question of law even if there is no dispute as to the general law. |
L & M Airconditioning & Refrigeration (Pte) Ltd v SA Shee & Co (Pte) Ltd | N/A | Yes | [1993] 3 SLR 482 | Singapore | Cited for the proposition that a sub-contractor can be liable for liquidated damages the main contractor has been made to pay if the sub-contractor caused or contributed to the delay. |
Goh Kian Swee v Keng Seng Builders (Pte) Ltd | High Court | Yes | [1992] SGHC 26 | Singapore | Cited for the principle that a claim for damages may be disallowed if the main contractor cannot identify what part of the delay was caused by the sub-contractor. |
Modern Engineering (Bristol) Ltd v C Miskin & Sons Ltd | N/A | Yes | [1981] 1 Lloyd’s Rep 135 | N/A | Cited for the principle that making an award before one party’s submissions on a point had been heard was equivalent to hearing evidence in the absence of a party. |
Mooney v Henry Boot Construction Ltd | N/A | Yes | Mooney v Henry Boot Construction Ltd (1995) 53 Con LR 120 | N/A | Cited for the principle that an arbitrator had failed to give a party any proper opportunity of dealing with the method he adopted to assess the disputed items in the Scott Schedule. |
Montrose Canned Foods, Ltd v Eric Wells (Merchants), Ltd | N/A | Yes | [1965] 1 Lloyd’s Rep 597 | N/A | Cited for the principle that an arbitrator should not make findings based on the evidence of one party that had not been seen by the other. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Arbitration Act (Cap 10, 1985 Rev Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Arbitration
- Sub-contract
- Liquidated damages
- Completion certificate
- Misconduct
- Extension of time
- Variation works
- Defective works
- Apportionment
- Delay
15.2 Keywords
- arbitration award
- misconduct
- construction
- sub-contract
- liquidated damages
- completion certificate
- Singapore
17. Areas of Law
Area Name | Relevance Score |
---|---|
Arbitration | 95 |
Contract Law | 80 |
Construction Law | 75 |
Damages | 60 |
Construction Contracts | 50 |
16. Subjects
- Arbitration
- Construction Dispute
- Contract Law