Permasteelisa v Hyundai: Arbitration Award Recourse & Misconduct Claim

In Permasteelisa Pacific Holdings Ltd v Hyundai Engineering and Construction Co Ltd, the Singapore High Court heard an application by Permasteelisa (PISA) against Hyundai, seeking to set aside or appeal an arbitration award related to a sub-contract for curtain-walling and glazing works. PISA alleged arbitrator misconduct and sought leave to appeal on questions of law. The High Court allowed the application in part, remitting certain matters to the arbitrator for reconsideration, including the apportionment of liquidated damages, the claim for additional preliminaries, the balance of work done, and the claim for the cost of replacement of original stayarms.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Application allowed in part. Certain matters remitted to the arbitrator for reconsideration.

1.3 Case Type

Arbitration

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

High Court case regarding recourse against an arbitration award. PISA sought to set aside the award based on arbitrator misconduct.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Permasteelisa Pacific Holdings LtdApplicantCorporationApplication allowed in partPartial
Hyundai Engineering and Construction Co LtdRespondentCorporationApplication dismissed in partPartial

3. Judges

Judge NameTitleDelivered Judgment
Judith PrakashJudgeYes

4. Counsels

4. Facts

  1. Hyundai was the main contractor for a construction project.
  2. PISA was engaged as the nominated sub-contractor for curtain-walling and glazing.
  3. Disputes arose between PISA and Hyundai regarding the sub-contract works.
  4. PISA claimed the works were completed by November 15, 2000.
  5. Hyundai alleged the works were incomplete due to scratched glass panels.
  6. An arbitrator was appointed to resolve the disputes.
  7. The arbitrator awarded Hyundai $1,463,481.55 on its counterclaim.

5. Formal Citations

  1. Permasteelisa Pacific Holdings Ltd v Hyundai Engineering and Construction Co Ltd, OM 5/2004, [2005] SGHC 33

6. Timeline

DateEvent
Sub-contract works commencement date
Sub-contract dated
Original completion date for main contract works
PISA claimed sub-contract works completed
PISA gave notice to Hyundai of intention to refer disputes to arbitration
President of the SIA appointed Mr Johnny Tan Cheng Hye as the sole arbitrator
Architect granted extension of time for the Sub-Contract Completion Date to 31 July 2001
Arbitration hearing began
Arbitration hearing concluded
Arbitrator delivered the Award
PISA filed proceedings seeking to set aside the Award
Arbitrator corrected the Award
Judgment reserved

7. Legal Issues

  1. Misconduct of Arbitration Proceedings
    • Outcome: The court found that the arbitrator had misconducted the proceedings in certain instances, including the apportionment of liquidated damages and the failure to make an award for the balance of work done.
    • Category: Procedural
    • Sub-Issues:
      • Failure to consider relevant evidence
      • Reliance on inadmissible evidence
      • Failure to provide opportunity to rebut evidence
  2. Interpretation of Contract Clauses
    • Outcome: The court granted leave to appeal on the question of whether it was necessary for a sub-contractor to object to the classification of the architect’s instructions or directions before the arbitrator was entitled to review a claim made by the sub-contractor for variations.
    • Category: Substantive
    • Sub-Issues:
      • Interpretation of completion certificate clause
      • Interpretation of temporary protection clause
      • Interaction of sub-contract and main contract conditions
  3. Leave to Appeal on Questions of Law
    • Outcome: The court granted leave to appeal on one question of law and denied leave to appeal on other questions of law.
    • Category: Procedural
    • Sub-Issues:
      • Determination of a question of law
      • Substantial effect on the rights of the parties
      • Clarity and certainty of Singapore law
  4. Causation of Delay
    • Outcome: The court remitted the matter to the arbitrator to determine the extent to which PISA's delay caused or contributed to the overall project delay.
    • Category: Substantive
    • Sub-Issues:
      • Contribution to overall project delay
      • Apportionment of liquidated damages

8. Remedies Sought

  1. Setting aside of arbitration award
  2. Leave to appeal on questions of law
  3. Remission of matter to arbitrator

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Arbitration
  • Construction Disputes
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Pioneer Shipping Ltd v BTP Tioxide LtdN/AYes[1982] AC 724N/ACited for principles to be applied regarding leave to appeal to the court under s 28 of the Act.
Hong Huat Development Co (Pte) Ltd v Hiap Hong & Co Pte LtdCourt of AppealYes[2000] 2 SLR 609SingaporeCited for principles to be applied regarding leave to appeal to the court under s 28 of the Act.
Northern Elevator Manufacturing Sdn Bhd v United Engineers (Singapore) Pte Ltd (No 2)Court of AppealYes[2004] 2 SLR 494SingaporeCited for principles to be applied regarding leave to appeal to the court under s 28 of the Act and clarification of what constitutes a 'question of law'.
Ahong Construction (S) Pte Ltd v United Boulevard Pte LtdN/AYes[2000] 1 SLR 749SingaporeCited for the definition of a 'question of law' in the context of arbitration appeals.
Italmare Shipping Co v Ocean Tanker Co Inc (The Rio Sun)N/AYes[1981] 2 Lloyd’s Rep 489N/ACited to show a rejected view that the application of law to facts can raise a question of law even if there is no dispute as to the general law.
L & M Airconditioning & Refrigeration (Pte) Ltd v SA Shee & Co (Pte) LtdN/AYes[1993] 3 SLR 482SingaporeCited for the proposition that a sub-contractor can be liable for liquidated damages the main contractor has been made to pay if the sub-contractor caused or contributed to the delay.
Goh Kian Swee v Keng Seng Builders (Pte) LtdHigh CourtYes[1992] SGHC 26SingaporeCited for the principle that a claim for damages may be disallowed if the main contractor cannot identify what part of the delay was caused by the sub-contractor.
Modern Engineering (Bristol) Ltd v C Miskin & Sons LtdN/AYes[1981] 1 Lloyd’s Rep 135N/ACited for the principle that making an award before one party’s submissions on a point had been heard was equivalent to hearing evidence in the absence of a party.
Mooney v Henry Boot Construction LtdN/AYesMooney v Henry Boot Construction Ltd (1995) 53 Con LR 120N/ACited for the principle that an arbitrator had failed to give a party any proper opportunity of dealing with the method he adopted to assess the disputed items in the Scott Schedule.
Montrose Canned Foods, Ltd v Eric Wells (Merchants), LtdN/AYes[1965] 1 Lloyd’s Rep 597N/ACited for the principle that an arbitrator should not make findings based on the evidence of one party that had not been seen by the other.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Arbitration Act (Cap 10, 1985 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Arbitration
  • Sub-contract
  • Liquidated damages
  • Completion certificate
  • Misconduct
  • Extension of time
  • Variation works
  • Defective works
  • Apportionment
  • Delay

15.2 Keywords

  • arbitration award
  • misconduct
  • construction
  • sub-contract
  • liquidated damages
  • completion certificate
  • Singapore

17. Areas of Law

16. Subjects

  • Arbitration
  • Construction Dispute
  • Contract Law