Lian Teck Construction v Woh Hup: Stay of Proceedings & Interim Payment in Arbitration Dispute

In Lian Teck Construction Pte Ltd v Woh Hup (Pte) Ltd, the High Court of Singapore addressed an appeal regarding whether an application for a stay of proceedings in favor of arbitration should be heard before an application for interim payment. Lian Teck Construction, the plaintiff/appellant, was appointed as an earthworks subcontractor by Woh Hup, the defendant/respondent. After a dispute arose, Lian Teck sought interim payment, while Woh Hup applied for a stay of proceedings in favor of arbitration. The High Court dismissed the appeal, ruling that the stay application should be resolved before the interim payment application.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Appeal Dismissed

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

The High Court addressed whether a stay of proceedings for arbitration should be heard before an interim payment application. The court dismissed the appeal.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Lian Teck Construction Pte LtdAppellant, PlaintiffCorporationAppeal DismissedLostSean La'Brooy
Woh Hup (Pte) LtdRespondent, DefendantCorporationAppeal DismissedWonWong Por Luk Paul, Loh Jen Wei
Shanghai Tunnel Engineering Co LtdRespondent, DefendantCorporationAppeal DismissedWonWong Por Luk Paul, Loh Jen Wei
NCC International AktiebolagRespondent, DefendantCorporationAppeal DismissedWonWong Por Luk Paul, Loh Jen Wei

3. Judges

Judge NameTitleDelivered Judgment
Andrew AngJudgeYes

4. Counsels

Counsel NameOrganization
Sean La'BrooyWong Partnership
Wong Por Luk PaulRodyk & Davidson
Loh Jen WeiRodyk & Davidson

4. Facts

  1. The defendants were the main contractors for a Land Transport Authority project.
  2. The plaintiff was appointed as earthworks subcontractor for the project.
  3. The defendants gave notice to the plaintiff of partial termination of the subcontract.
  4. The plaintiff claimed an aggregate amount of $2,560,239.52 for works already performed.
  5. The plaintiff issued a writ of summons against the defendants claiming the unpaid amount, loss of profits, and special damages.
  6. The defendants applied for a stay of proceedings in favor of arbitration.
  7. The plaintiff filed a cross application for interim payment.

5. Formal Citations

  1. Lian Teck Construction Pte Ltd v Woh Hup (Pte) Ltd and Others, Suit 98/2006, RA 124/2006, [2006] SGHC 118

6. Timeline

DateEvent
Letter of award issued to plaintiff as earthworks subcontractor.
Defendants gave notice to the plaintiff of partial termination of the subcontract.
Plaintiff accepted repudiation of the subcontract.
Plaintiff issued a writ of summons against the defendants.
Defendants entered an appearance in the action.
Defendants filed a summons application seeking a stay of proceedings in favour of arbitration.
Plaintiff filed a cross application for interim payment.
Defendants filed a summons seeking an extension of time to file an affidavit in reply to the plaintiff’s application for interim payment.
Hearing fixed for stay application and interim payment application.
Appeal dismissed.

7. Legal Issues

  1. Stay of Proceedings in Favor of Arbitration
    • Outcome: The court held that the stay application should be resolved before the interim payment application.
    • Category: Procedural
    • Sub-Issues:
      • Taking a step in proceedings
      • Jurisdiction of the court
  2. Interim Payment
    • Outcome: The court held that it was not sensible to distinguish between an Order 14 Rule 1 application and one under Order 29 Rule 10 in the context of a stay application.
    • Category: Procedural
    • Sub-Issues:
      • Application on the merits
      • Satisfaction of court

8. Remedies Sought

  1. Monetary Damages
  2. Loss of Profits
  3. Special Damages
  4. Interim Payment

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Arbitration
  • Construction Law
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Tropicon Contractors Pte Ltd v Lojan Properties Pte LtdHigh CourtYes[1989] SLR 610SingaporeCited for the practice of hearing an Order 14 application and a stay application together.
Aoki Corp v Lippoland (Singapore) Pte LtdHigh CourtYes[1995] 2 SLR 609SingaporeCited for the practice of hearing an Order 14 application and a stay application together.
Ellis Mechanical Services Ltd v Wates Construction LtdCourt of AppealYes(1976) 2 BLR 60United KingdomCited for the test to be applied in cases with an arbitration clause, where judgment can be given for a sum indisputably due.
Associated Bulk Carriers Ltd v Koch Shipping IncCourt of AppealYes(1978) 7 BLR 22United KingdomCited to clarify that summary judgment may only be given where there is an admitted or decided quantified sum with no dispute.
Imodco Ltd v Wimpey Major Projects Ltd and Taylor Woodrow International LtdCourt of AppealYes(1987) 40 BLR 1United KingdomCited for the proposition that an order for interim payment can be made even if the dispute is to be stayed and referred to arbitration.
Samsung Corp v Chinese Chamber Realty Pte LtdCourt of AppealYes[2004] 1 SLR 382SingaporeCited for the difficulties arising from the amendment of Order 14 Rule 1 and the court's reasoning that a stay application should be resolved before an Order 14 application.
Chinese Chamber Realty Pte Ltd v Samsung CorpHigh CourtYes[2003] 3 SLR 656SingaporeCited for the difficulties in relation to obtaining summary judgments under Order 14 for contracts which provided for disputes to be referred to arbitration.
Yeoh Poh San v Won Siok WanHigh CourtYes[2002] 4 SLR 91SingaporeCited for the reasoning that a compromise order requiring a defendant to file a defence while also applying for a stay is inconsistent with logic.
British and Commonwealth Holdings Plc v Quadrex Holdings IncHigh CourtYes[1989] QB 842United KingdomCited for the principle that the court must be satisfied that the claim would succeed at trial before granting an order for interim payment.
Eagle Star Insurance Co Ltd v Yuval Insurance Co LtdCourt of AppealYes[1978] 1 Lloyd’s Rep 357United KingdomCited for the definition of 'step in the proceedings' as one which impliedly affirms the correctness of the proceedings and the willingness of the defendant to go along with a determination by the Courts of law instead of arbitration.
Kuwait Airways Corporation v Iraq Airways CoCourt of AppealYes[1994] 1 Lloyd’s Rep 276United KingdomCited following Eagle Star Insurance Co Ltd v Yuval Insurance Co Ltd on the definition of 'step in the proceedings'.
Australian Timber Products Pte Ltd v Koh Brothers Building & Civil Engineering Contractor (Pte) LtdHigh CourtYes[2005] 1 SLR 168SingaporeCited following Eagle Star Insurance Co Ltd v Yuval Insurance Co Ltd on the definition of 'step in the proceedings'.

13. Applicable Rules

Rule Name
Rules of Court (Cap 322, R 5, 2006 Rev Ed)
O 29 r 10 Rules of Court (Cap 322, R 5, 2006 Rev Ed)

14. Applicable Statutes

Statute NameJurisdiction
Arbitration Act (Cap 10, 2002 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Stay of proceedings
  • Arbitration
  • Interim payment
  • Subcontract
  • Repudiation
  • Earthworks
  • Rules of Court
  • Arbitration Act

15.2 Keywords

  • Arbitration
  • Stay of proceedings
  • Interim payment
  • Construction dispute

16. Subjects

  • Civil Procedure
  • Arbitration

17. Areas of Law

  • Civil Procedure
  • Arbitration Law
  • Construction Law