Shanghai Tunnel v Econ-NCC: Arbitration Appeal on Sub-Contract Delay and Waiver
Shanghai Tunnel Engineering Co Ltd (STEC) appealed against a decision in arbitration with Econ-NCC Joint Venture (ENJV) regarding a sub-contract for bored tunnelling works in Phase 3 of the Circle Line MRT project. The High Court of Singapore, presided over by Judith Prakash J, heard STEC's appeal on questions of law relating to the arbitrator's findings on substantial completion, extension of time, and ENJV's claim for reimbursement of liability to LTA for delay. The court allowed the appeal, remitting the partial award for reconsideration of ENJV's counterclaim.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Appeal Allowed
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Appeal regarding arbitration over sub-contract delay in MRT construction. Court remits award for reconsideration of ENJV's counterclaim.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Shanghai Tunnel Engineering Co Ltd | Appellant | Corporation | Appeal Allowed | Won | |
Econ-NCC Joint Venture | Respondent | Partnership | Counterclaim to be reconsidered | Remanded |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Judith Prakash | Judge | Yes |
4. Counsels
4. Facts
- STEC was subcontracted by ENJV for bored tunnelling works in Phase 3 of the Circle Line MRT project.
- The sub-contract completion date was 31 December 2004.
- ENJV handed over the SB and NB launch shafts late.
- STEC and ENJV entered into a 2nd SA where ENJV made an advance payment to STEC.
- STEC waived its claims for extension of time in the 2nd SA.
- ENJV claimed damages from STEC for delay in completion of the sub-contract works.
- The arbitrator found STEC liable for 68 days of delay but did not award damages to ENJV.
5. Formal Citations
- Shanghai Tunnel Engineering Co Ltd v Econ-NCC Joint Venture, Originating Summons No 226 of 2009, [2010] SGHC 252
6. Timeline
Date | Event |
---|---|
Main contract between LTA and ENJV was dated | |
Letter of Award for sub-contract awarded to STEC by ENJV | |
Commencement date for the sub-contract works | |
Based on the 22B3 programme, the date for handing over of the SB launch shafts to STEC for commencement of work | |
Based on the 22B3 programme, the date for handing over of the NB launch shafts to STEC for commencement of work | |
SB launch shaft handed over to STEC | |
STEC and ENJV entered into the second supplemental agreement | |
NB shaft handed over to STEC | |
Scheme of arrangement concerning ECON approved by the court | |
STEC was to complete the installation of tunnelling works including First Stage Concrete | |
Completion date for the sub-contract works | |
STEC gave notice to ENJV of its intention to commence arbitration proceedings | |
STEC's application for an interim award to be made summarily in its favour was dismissed by the Arbitrator’s interim award | |
Hearing of the arbitration commenced | |
Further hearings took place in arbitration | |
Further hearings took place in arbitration | |
Oral evidence was completed in arbitration | |
Fifth and final set of submissions from ENJV was received | |
The Arbitrator denied ENJV’s request to put in a sixth set of submissions and declared the close of the hearing of the arbitration | |
Arbitrator issued the Partial Award | |
Solicitors for both STEC and ENJV wrote to the Arbitrator to seek clarification and correction on various points of the Partial Award | |
The Arbitrator issued the Correction Award | |
STEC made a clarification request for reduction of number of days in delay | |
Gay Choon Ing was decided | |
Yamashita was decided on 30 December 2008 | |
The last of the parties’ closing submissions before the Arbitrator was submitted in October 2008 | |
Domestic Arbitration Rules of the Singapore International Arbitration Centre (2nd Ed, 1 September 2002) (“SIAC Rules”) (which, as agreed by the parties, applied to the arbitration) | |
Judgment reserved |
7. Legal Issues
- Breach of Contract
- Outcome: The court found that ENJV had not established actual liability for damages, and the arbitrator should have dismissed the counterclaim.
- Category: Substantive
- Sub-Issues:
- Delay in completion of sub-contract works
- Failure to establish actual liability for damages
- Interpretation of Contract
- Outcome: The court found that the 2nd SA was not a compromise agreement and STEC had waived its claims for extension of time.
- Category: Substantive
- Sub-Issues:
- Waiver of claims
- Commercial purpose of agreement
- Completeness of Arbitral Award
- Outcome: The court found that the arbitrator did not render a complete decision by not dismissing ENJV's claim and allowing it to pursue further action in another forum.
- Category: Procedural
- Sub-Issues:
- Failure to determine all issues
- Delegation of decision-making power
8. Remedies Sought
- Monetary Damages
- Declaration
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Arbitration
- Construction Law
- Commercial Litigation
11. Industries
- Construction
- Engineering
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Yamashita Tetsuo v See Hup Seng Ltd | Court of Appeal | Yes | [2009] 2 SLR(R) 265 | Singapore | Cited for principles on the interpretation of contracts, specifically the contextual approach and consideration of commercial purpose. |
Gay Choong Ing v Loh Sze Ti Terence Peter and Another Appeal | Court of Appeal | Yes | [2009] 2 SLR(R) 332 | Singapore | Cited for principles on the law of compromise, including the requirements for a valid compromise agreement. |
Zurich Insurance (Singapore) Pte Ltd v B-Gold Interior Design & Construction Pte Ltd | Court of Appeal | Yes | [2008] 3 SLR(R) 1029 | Singapore | Cited for the principle that surrounding circumstances may create ambiguity about the language used in a contract. |
Citicorp Investment Bank (Singapore) Ltd v Wee Ah Kee | Court of Appeal | Yes | [1997] 2 SLR(R) 1 | Singapore | Cited regarding the meaning imputed by the court be one which 'the words are reasonably adequate to convey' |
Ronly Holdings Ltd v JSC Zestafoni G Nikoladze Ferroalloy Plant | Not Available | Yes | [2004] 1 CLC 1168 | Not Available | Cited for the principle that an award must be final and a tribunal cannot delegate its decision-making power to another forum. |
MAE Engineering Ltd v. Fire-Stop Marketing Services Pte Ltd | Court of Appeal | Yes | [2005] 1 SLR(R) 379 | Singapore | Cited for the principle that the perceived “commercial sense” of the court cannot be allowed to override the words of a contract where they are clear and unambiguous. |
Charter Reinsurance Co Ltd v Fagan | Not Available | Yes | [1997] 3 AC 313 | Not Available | Cited for the principle that to force upon the words a meaning which they cannot fairly bear is to substitute for the bargain actually made one which the court believes could better have been made. |
13. Applicable Rules
Rule Name |
---|
Domestic Arbitration Rules of the Singapore International Arbitration Centre |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Arbitration Act (Cap 10, 2002 Rev Ed) | Singapore |
Evidence Act (Cap 97, 1997 Rev Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Sub-Contract
- Extension of Time
- Waiver
- Liquidated Damages
- Second Supplemental Agreement
- Partial Award
- Completion Date
- Launch Shaft
- Main Contract
- Delay
15.2 Keywords
- arbitration
- contract
- construction
- delay
- waiver
- sub-contract
- extension of time
17. Areas of Law
Area Name | Relevance Score |
---|---|
Arbitration | 90 |
Breach of Contract | 90 |
Contract Law | 90 |
Construction Law | 70 |
Commercial Disputes | 60 |
Sub-Contract | 50 |
16. Subjects
- Arbitration
- Contract Law
- Construction Dispute