Shanghai Tunnel v Econ-NCC: Arbitration Appeal on Sub-Contract Delay and Waiver

Shanghai Tunnel Engineering Co Ltd (STEC) appealed against a decision in arbitration with Econ-NCC Joint Venture (ENJV) regarding a sub-contract for bored tunnelling works in Phase 3 of the Circle Line MRT project. The High Court of Singapore, presided over by Judith Prakash J, heard STEC's appeal on questions of law relating to the arbitrator's findings on substantial completion, extension of time, and ENJV's claim for reimbursement of liability to LTA for delay. The court allowed the appeal, remitting the partial award for reconsideration of ENJV's counterclaim.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Appeal Allowed

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Appeal regarding arbitration over sub-contract delay in MRT construction. Court remits award for reconsideration of ENJV's counterclaim.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Shanghai Tunnel Engineering Co LtdAppellantCorporationAppeal AllowedWon
Econ-NCC Joint VentureRespondentPartnershipCounterclaim to be reconsideredRemanded

3. Judges

Judge NameTitleDelivered Judgment
Judith PrakashJudgeYes

4. Counsels

4. Facts

  1. STEC was subcontracted by ENJV for bored tunnelling works in Phase 3 of the Circle Line MRT project.
  2. The sub-contract completion date was 31 December 2004.
  3. ENJV handed over the SB and NB launch shafts late.
  4. STEC and ENJV entered into a 2nd SA where ENJV made an advance payment to STEC.
  5. STEC waived its claims for extension of time in the 2nd SA.
  6. ENJV claimed damages from STEC for delay in completion of the sub-contract works.
  7. The arbitrator found STEC liable for 68 days of delay but did not award damages to ENJV.

5. Formal Citations

  1. Shanghai Tunnel Engineering Co Ltd v Econ-NCC Joint Venture, Originating Summons No 226 of 2009, [2010] SGHC 252

6. Timeline

DateEvent
Main contract between LTA and ENJV was dated
Letter of Award for sub-contract awarded to STEC by ENJV
Commencement date for the sub-contract works
Based on the 22B3 programme, the date for handing over of the SB launch shafts to STEC for commencement of work
Based on the 22B3 programme, the date for handing over of the NB launch shafts to STEC for commencement of work
SB launch shaft handed over to STEC
STEC and ENJV entered into the second supplemental agreement
NB shaft handed over to STEC
Scheme of arrangement concerning ECON approved by the court
STEC was to complete the installation of tunnelling works including First Stage Concrete
Completion date for the sub-contract works
STEC gave notice to ENJV of its intention to commence arbitration proceedings
STEC's application for an interim award to be made summarily in its favour was dismissed by the Arbitrator’s interim award
Hearing of the arbitration commenced
Further hearings took place in arbitration
Further hearings took place in arbitration
Oral evidence was completed in arbitration
Fifth and final set of submissions from ENJV was received
The Arbitrator denied ENJV’s request to put in a sixth set of submissions and declared the close of the hearing of the arbitration
Arbitrator issued the Partial Award
Solicitors for both STEC and ENJV wrote to the Arbitrator to seek clarification and correction on various points of the Partial Award
The Arbitrator issued the Correction Award
STEC made a clarification request for reduction of number of days in delay
Gay Choon Ing was decided
Yamashita was decided on 30 December 2008
The last of the parties’ closing submissions before the Arbitrator was submitted in October 2008
Domestic Arbitration Rules of the Singapore International Arbitration Centre (2nd Ed, 1 September 2002) (“SIAC Rules”) (which, as agreed by the parties, applied to the arbitration)
Judgment reserved

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found that ENJV had not established actual liability for damages, and the arbitrator should have dismissed the counterclaim.
    • Category: Substantive
    • Sub-Issues:
      • Delay in completion of sub-contract works
      • Failure to establish actual liability for damages
  2. Interpretation of Contract
    • Outcome: The court found that the 2nd SA was not a compromise agreement and STEC had waived its claims for extension of time.
    • Category: Substantive
    • Sub-Issues:
      • Waiver of claims
      • Commercial purpose of agreement
  3. Completeness of Arbitral Award
    • Outcome: The court found that the arbitrator did not render a complete decision by not dismissing ENJV's claim and allowing it to pursue further action in another forum.
    • Category: Procedural
    • Sub-Issues:
      • Failure to determine all issues
      • Delegation of decision-making power

8. Remedies Sought

  1. Monetary Damages
  2. Declaration

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Arbitration
  • Construction Law
  • Commercial Litigation

11. Industries

  • Construction
  • Engineering

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Yamashita Tetsuo v See Hup Seng LtdCourt of AppealYes[2009] 2 SLR(R) 265SingaporeCited for principles on the interpretation of contracts, specifically the contextual approach and consideration of commercial purpose.
Gay Choong Ing v Loh Sze Ti Terence Peter and Another AppealCourt of AppealYes[2009] 2 SLR(R) 332SingaporeCited for principles on the law of compromise, including the requirements for a valid compromise agreement.
Zurich Insurance (Singapore) Pte Ltd v B-Gold Interior Design & Construction Pte LtdCourt of AppealYes[2008] 3 SLR(R) 1029SingaporeCited for the principle that surrounding circumstances may create ambiguity about the language used in a contract.
Citicorp Investment Bank (Singapore) Ltd v Wee Ah KeeCourt of AppealYes[1997] 2 SLR(R) 1SingaporeCited regarding the meaning imputed by the court be one which 'the words are reasonably adequate to convey'
Ronly Holdings Ltd v JSC Zestafoni G Nikoladze Ferroalloy PlantNot AvailableYes[2004] 1 CLC 1168Not AvailableCited for the principle that an award must be final and a tribunal cannot delegate its decision-making power to another forum.
MAE Engineering Ltd v. Fire-Stop Marketing Services Pte LtdCourt of AppealYes[2005] 1 SLR(R) 379SingaporeCited for the principle that the perceived “commercial sense” of the court cannot be allowed to override the words of a contract where they are clear and unambiguous.
Charter Reinsurance Co Ltd v FaganNot AvailableYes[1997] 3 AC 313Not AvailableCited for the principle that to force upon the words a meaning which they cannot fairly bear is to substitute for the bargain actually made one which the court believes could better have been made.

13. Applicable Rules

Rule Name
Domestic Arbitration Rules of the Singapore International Arbitration Centre

14. Applicable Statutes

Statute NameJurisdiction
Arbitration Act (Cap 10, 2002 Rev Ed)Singapore
Evidence Act (Cap 97, 1997 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Sub-Contract
  • Extension of Time
  • Waiver
  • Liquidated Damages
  • Second Supplemental Agreement
  • Partial Award
  • Completion Date
  • Launch Shaft
  • Main Contract
  • Delay

15.2 Keywords

  • arbitration
  • contract
  • construction
  • delay
  • waiver
  • sub-contract
  • extension of time

17. Areas of Law

16. Subjects

  • Arbitration
  • Contract Law
  • Construction Dispute