Chua Tian Chu v Chin Bay Ching: Specific Performance & Liquidated Damages in Property Sale

In Chua Tian Chu and another v Chin Bay Ching and another, the High Court of Singapore addressed a dispute arising from a property sale agreement. The plaintiffs, Chua Tian Chu and Cheang Poh Ling Pauline, sought specific performance, liquidated damages, and rectification costs from the defendants, Chin Bay Ching and Tjia Mui Kui, regarding a property purchase. The court ordered specific performance of the agreement, allowed the plaintiffs' claim for rectification costs in the agreed sum of $410,000, and dismissed the claim for liquidated damages in part, finding that the plaintiffs' conduct had set time at large.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Specific performance of the agreement ordered. Claim for rectification costs allowed. Claim for liquidated damages dismissed in part.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

High Court case involving a property purchase dispute. Court ordered specific performance, allocated rectification costs, and addressed liquidated damages.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Chua Tian ChuPlaintiffIndividualSpecific performance ordered, claim for rectification costs allowed, claim for liquidated damages dismissed in partPartial
Cheang Poh Ling PaulinePlaintiffIndividualSpecific performance ordered, claim for rectification costs allowed, claim for liquidated damages dismissed in partPartial
Chin Bay ChingDefendantIndividualSpecific performance ordered, claim for rectification costs allowed, claim for liquidated damages dismissed in partPartial
Tjia Mui KuiDefendantIndividualSpecific performance ordered, claim for rectification costs allowed, claim for liquidated damages dismissed in partPartial

3. Judges

Judge NameTitleDelivered Judgment
Andrew AngJudgeYes

4. Counsels

4. Facts

  1. Plaintiffs and defendants entered into a sale and purchase agreement for a property on 30 November 2006.
  2. The agreed purchase price of the property was $5,680,000.
  3. The defendants were the vendors and developers of the property.
  4. The original building layout plans were approved by the Building and Construction Authority on 21 August 2006.
  5. The plaintiffs requested amendments to the original building layout plans, which were incorporated into the agreement.
  6. The contract stipulated a deadline of 31 December 2007 for the delivery of the notice to take vacant possession.
  7. The defendants gave notice to the plaintiffs to take vacant possession on 6 January 2009, following the issuance of the temporary occupation permit.
  8. The plaintiffs withheld payment of $418,000 due under cl 4.1.5(a) on the basis that the property was not fit for occupation.
  9. The defendants served 21 days’ notice on the plaintiffs under cl 6.1 of the Agreement demanding payment of the sum of $418,000.
  10. The defendants rescinded the Agreement on 23 July 2009, construing the plaintiffs’ act of non-payment as a repudiatory act.

5. Formal Citations

  1. Chua Tian Chu and another v Chin Bay Ching and another, Suit No 778 of 2009, [2011] SGHC 126

6. Timeline

DateEvent
Sale and purchase agreement entered into
Additional changes made to the Fifth Schedule
Revised building layout plan drawn up
Second application for BCA’s approval submitted
Second application for BCA’s approval approved
Contractually stipulated deadline for delivery of notice to take vacant possession
Defendants gave notice to plaintiffs to take vacant possession
Temporary occupation permit issued
Plaintiffs completed the payment of 20% of the purchase price
Defendants forwarded the architect’s certificate
Plaintiffs made payment of $3,834,077.81
Defendants solicitors gave the plaintiffs the Notice to Complete the sale
Defendants served 21 days’ notice on the plaintiffs
Defendants rescinded the Agreement
Plaintiffs commenced action by way of writ
Decision Date

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found that the defendants wrongfully rescinded the Agreement by mischaracterizing the plaintiffs’ conduct as a repudiation of the Agreement.
    • Category: Substantive
    • Sub-Issues:
      • Repudiation of contract
      • Failure to complete sale
      • Delay in delivery of vacant possession
      • Delay in giving notice to complete
    • Related Cases:
      • [1994] 3 SLR(R) 1004
      • [2001] SGHC 243
      • [1962] 2 QB 26
      • [2009] 4 SLR(R) 602
  2. Liquidated Damages
    • Outcome: The court found that time was set at large by the plaintiffs’ conduct. As such, apart from the sum of $141,922.19 already deducted (as conceded by the defendants), liquidated damages are unavailable for the delay from 16 January 2009 onwards.
    • Category: Substantive
    • Sub-Issues:
      • Calculation of liquidated damages
      • Entitlement to liquidated damages
      • Time being set at large
    • Related Cases:
      • (1903) Construction Law Year Book, Vol 4, 65 CA
      • [1897] 1 QB 562
      • [1973] 1 WLR 601
      • [2009] 1 SLR(R) 385
      • [1983] 1 MLJ 151
  3. Specific Performance
    • Outcome: The court ordered specific performance of the Agreement.
    • Category: Substantive
  4. Rectification Costs
    • Outcome: The court allowed the plaintiffs’ claim for rectification costs in the agreed sum of $410,000.
    • Category: Substantive
  5. Validity of Notice to Take Vacant Possession
    • Outcome: The court found that the Notice given to take vacant possession of the property was valid.
    • Category: Substantive
    • Sub-Issues:
      • Fitness for occupation
      • Outstanding works
    • Related Cases:
      • [1979] 1 WLR 446
      • [1999] 1 SLR(R) 309
  6. Time Being Set at Large
    • Outcome: The court found that time was set at large by the plaintiffs’ conduct.
    • Category: Substantive
    • Sub-Issues:
      • Acts of prevention
      • Variations to contract
      • Appointment of independent contractors
    • Related Cases:
      • [2007] EWHC 447
      • [2007] 3 SLR(R) 566
      • [1994] 3 SLR 823
      • [2007] 4 SLR(R) 413
      • [1979] Ch 250
      • [1931] 1 KB 557

8. Remedies Sought

  1. Specific Performance
  2. Liquidated Damages
  3. Cost of Rectification Works
  4. Damages

9. Cause of Actions

  • Breach of Contract
  • Specific Performance

10. Practice Areas

  • Commercial Litigation
  • Construction Law
  • Real Estate Transactions

11. Industries

  • Construction
  • Real Estate

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Brani Readymixed Pte Ltd v Yee Hong Pte LtdCourt of AppealYes[1994] 3 SLR(R) 1004SingaporeAffirmed the common law position that the mere failure or delay in making payment per se would not amount to a repudiation of the contract.
AL Stainless Industries Pte Ltd v Wei Sin Construction Pte LtdHigh CourtYes[2001] SGHC 243SingaporeCited Chow Kok Fong’s Law and Practice of Construction Claims as a guide to determining when non-payment constituted a repudiatory breach.
Hongkong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha LtdQueen's BenchYes[1962] 2 QB 26England and WalesEndorsed the "Hong Kong Fir approach" to determine when a party may validly elect to rescind a contract.
Alliance Concrete Singapore Pte Ltd v Comfort Resources Pte LtdCourt of AppealYes[2009] 4 SLR(R) 602SingaporeThe court found that a party may validly elect to rescind the contract when the other contracting party’s non-payment deprived it of substantially the whole benefit which it intended to obtain from the Agreement.
Wells v Army & Navy Co-operative SocietyCourt of AppealYes(1903) Construction Law Year Book, Vol 4, 65 CAEngland and WalesAn early expression of the principle pertaining to time being set at large or the “prevention principle” in construction contracts
Dodd v ChurtonQueen's BenchYes[1897] 1 QB 562England and WalesDescribed the rationale behind the principle of time being set at large.
Trollope & Colls Ltd v North West Metropolitan Regional Hospital BoardCourt of AppealYes[1973] 1 WLR 601England and WalesHeld that if one party renders it impossible or impracticable for the other party to do his work within the stipulated time, the one whose conduct caused the trouble can no longer insist upon strict adherence to the time stated.
Yap Boon Keng Sonny v Pacific Prince International Pte LtdHigh CourtYes[2009] 1 SLR(R) 385SingaporeDefined an act of prevention as one that prevents, impedes, or makes it more difficult for a contractor to complete the works by the stipulated date.
Sim Chio Huat v Wong Ted FuiFederal CourtYes[1983] 1 MLJ 151MalaysiaClarified that it was immaterial whether the hindrance or delay caused by the plaintiffs was a cause of part or the whole delay.
Topfell Ltd v Galley Properties LtdCourt of AppealYes[1979] 1 WLR 446England and WalesVacant possession in relation to a property was defined as “a state in which it can be occupied and enjoyed”
Yin-Marguerite v Pt Jaya Putra KundurHigh CourtYes[1999] 1 SLR(R) 309SingaporeEstablished that the question whether notice was correctly issued was one of fact.
Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No 2)High Court of JusticeYes[2007] EWHC 447England and WalesActions by the employer which are perfectly legitimate under a construction contract may still be characterised as prevention, if those actions cause delay beyond the contractual completion date.
Orient Centre Investments Ltd v Societe GeneraleCourt of AppealYes[2007] 3 SLR(R) 566SingaporeHeld that a party who wished to rely on a clause in a contract which was capable of giving rise to an estoppel only needed to plead it for its legal effect without expressly pleading estoppel.
M K (Project Management) Ltd v Baker Marine Energy Pte LtdHigh CourtYes[1994] 3 SLR 823SingaporeThe court adopted Lord Denning MR’s proposition In Re Vandervell’s Trusts (No 2) [1974] Ch 269 at 321: “It is sufficient for the pleader to state the material facts. He need not state the legal result”.
RDC Concrete Pte Ltd v Sato Kogyo (S) Pte LtdCourt of AppealYes[2007] 4 SLR(R) 413SingaporeStated that if the plea was alluded to in the evidence and the facts were already before the court, no injustice would result from its consideration by the court.
Belmont Finance Corporation Ltd v Williams Furniture LtdChancery DivisionYes[1979] Ch 250England and Walesthe “... court must have jurisdiction to grant any relief that it thinks appropriate to the facts as proved.”
Lever Brothers Ltd v BellCourt of AppealYes[1931] 1 KB 557England and WalesThe practice of the Courts has been to consider and deal with the legal result of pleaded facts, though the particular legal result alleged is not stated in the pleadings, except in cases where to ascertain the validity of the legal result claimed would require the investigation of new and disputed facts which have not been investigated at trial.
Lee Chee Wei v Tan Hor Peow VictorCourt of AppealYes[2007] 3 SLR(R) 537SingaporeThe loss must be shown to have actually occurred and to be legitimately recoverable in law before any award can be made.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Building Control Act (Cap 29, 1999 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Sale and Purchase Agreement
  • Vacant Possession
  • Temporary Occupation Permit
  • Notice to Complete
  • Liquidated Damages
  • Rectification Costs
  • Time at Large
  • Act of Prevention
  • Repudiation
  • Defects Liability Period

15.2 Keywords

  • property
  • sale
  • purchase
  • agreement
  • contract
  • liquidated damages
  • specific performance
  • construction
  • defects
  • vacant possession
  • notice
  • rescission
  • time at large

17. Areas of Law

16. Subjects

  • Contract Law
  • Construction Law
  • Real Estate
  • Specific Performance
  • Liquidated Damages