Didwania v Hauslab: Enforcing Adjudication & Standard of Proof for Novation in Construction
Vinod Kumar Ramgopal Didwania appealed to the Court of Appeal of Singapore against the High Court's decision to dismiss his application to set aside an order enforcing an adjudication determination in favor of Hauslab Design & Build Pte Ltd. The primary legal issue was the standard of proof required to challenge the adjudication determination, specifically regarding the existence of a contract between the parties under the Building and Construction Industry Security of Payment Act. The court dismissed the appeal, holding that the appellant had to prove on the balance of probabilities that there was no contract between himself and the respondent.
1. Case Overview
1.1 Court
Court of Appeal of the Republic of Singapore1.2 Outcome
Appeal Dismissed
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Appeal on setting aside adjudication. Court held balance of probabilities is standard to prove contract novation under Security of Payment Act.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Vinod Kumar Ramgopal Didwania | Appellant | Individual | Appeal Dismissed | Lost | Steven Lam, Madeline Choong |
Hauslab Design & Build Pte Ltd | Respondent | Corporation | Appeal Dismissed | Won | Rey Foo Jong Han, Munirah Mydin |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Sundaresh Menon | Chief Justice | Yes |
Andrew Phang Boon Leong | Judge of Appeal | No |
Tay Yong Kwang | Judge of Appeal | No |
4. Counsels
Counsel Name | Organization |
---|---|
Steven Lam | Templars Law LLC |
Madeline Choong | Templars Law LLC |
Rey Foo Jong Han | KSCGP Juris LLP |
Munirah Mydin | KSCGP Juris LLP |
4. Facts
- Appellant entered into a construction contract with Hauslab D&B Pte Ltd on 15 April 2013.
- The contract required Hauslab D&B Pte Ltd to design and build a two-storey detached house on the Appellant's property.
- Hauslab D&B Pte Ltd and the Respondent, Hauslab Design & Build Pte Ltd, are separate entities but wholly-owned subsidiaries of Hauslab Holdings Pte Ltd.
- In December 2013, a draft novation agreement was presented to the Appellant to novate the contract from Hauslab D&B Pte Ltd to the Respondent.
- The Appellant signed a Re-application Form to the BCA naming the Respondent as the new Builder.
- The BCA issued a permit naming only the Respondent as the Builder.
- Progress claims were paid to the Respondent after the alleged date of novation.
5. Formal Citations
- Vinod Kumar Ramgopal Didwania v Hauslab Design & Build Pte Ltd, Civil Appeal No 15 of 2016, [2017] SGCA 19
6. Timeline
Date | Event |
---|---|
Construction Contract signed between Appellant and Hauslab D&B Pte Ltd | |
Draft novation agreement produced by Mr. Tan | |
Joint Application for Permit to Carry out Demolition Works (Change of Builder) sent to BCA | |
BCA issued a permit to carry out structural works | |
Respondent served Progress Claim No. 18 on the Appellant | |
Mrs Didwania informed the Respondent that the Appellant’s contract was with Mr Tan of D&B and not with the Respondent | |
Respondent served on the Appellant its Notice of Intention to Apply for Adjudication | |
Respondent lodged its Adjudication Application with the Singapore Mediation Centre | |
Adjudication Application was served on the Appellant | |
Adjudicator was appointed | |
Appellant lodged his Adjudication Response | |
Adjudication determination was issued | |
Order granting leave to enforce the adjudication determination issued | |
Appellant applied to the High Court to set aside the adjudication determination | |
Court hearing | |
Grounds of decision delivered |
7. Legal Issues
- Standard of Proof for Setting Aside Adjudication Determination
- Outcome: The court held that the standard of proof is on the balance of probabilities.
- Category: Procedural
- Related Cases:
- [2017] 3 SLR 103
- [2010] NSWCA 190
- [1999] All ER (D) 143
- [2013] 3 SLR 380
- [2016] 5 SLR 1011
- [2004] 1 WLR 2082
- (1999) 65 ConLR 146
- [2015] 1 SLR 797
- Existence of a Contract under the Building and Construction Industry Security of Payment Act
- Outcome: The court found that a contract existed between the Appellant and the Respondent due to the novation of the original contract.
- Category: Substantive
- Sub-Issues:
- Validity of Novation Agreement
8. Remedies Sought
- Setting aside of Adjudication Determination
- Setting aside of Order granting leave to enforce the adjudication determination
9. Cause of Actions
- Enforcement of Adjudication Determination
10. Practice Areas
- Construction Law
- Commercial Litigation
- Arbitration
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Hauslab Design & Build Pte Ltd v Vinod Kumar Ramgopal Didwania | High Court | Yes | [2017] 3 SLR 103 | Singapore | The High Court decision that was appealed against in this case. |
Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd | New South Wales Court of Appeal | Yes | [2010] NSWCA 190 | New South Wales | Cited in relation to judicial review proceedings for setting aside adjudication determinations. |
Macob Civil Engineering Ltd v Morrison Construction Ltd | English Courts | Yes | [1999] All ER (D) 143 | England | Cited for the usual remedy for failure to pay in accordance with an adjudicator’s decision. |
W Y Steel Construction Pte Ltd v Osko Pte Ltd | Court of Appeal | Yes | [2013] 3 SLR 380 | Singapore | Cited for the concept of temporary finality in adjudication. |
Grouteam Pte Ltd v UES Holdings Pte Ltd | Court of Appeal | Yes | [2016] 5 SLR 1011 | Singapore | Cited for the concept of temporary finality in adjudication. |
Pegram Shopfitters Ltd v Tally Weijl (UK) Ltd | English Courts | Yes | [2004] 1 WLR 2082 | England | Cited for enforcement of adjudication determinations by way of summary judgment. |
Project Consultancy Group v Trustees of the Gray Trust | Technology and Construction Court | Yes | (1999) 65 ConLR 146 | England | Cited for raising a triable issue as to the adjudicator’s jurisdiction. |
Citiwall Safety Glass Pte Ltd v Mansource Interior Pte Ltd | Court of Appeal | Yes | [2015] 1 SLR 797 | Singapore | Cited for the court not reviewing the merits of the adjudicator’s decision. |
13. Applicable Rules
Rule Name |
---|
Rules of Court (Cap 322, R 5, 2014 Rev Ed) |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) | Singapore |
Building Control Act (Cap 29, 1999 Rev Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Adjudication Determination
- Novation Agreement
- Building and Construction Industry Security of Payment Act
- Balance of Probabilities
- Temporary Finality
- Progress Claim
- Re-application Form
- Builder
- Construction Contract
15.2 Keywords
- Adjudication
- Construction
- Novation
- Security of Payment Act
- Singapore
- Contract
- Building
16. Subjects
- Construction Law
- Contract Law
- Adjudication
- Civil Procedure
17. Areas of Law
- Building and Construction Law
- Contract Law
- Civil Procedure
- Dispute Resolution
- Alternative Dispute Resolution Procedures