AES Façade Pte Ltd v WYSE Pte Ltd: Security of Payment Act & Sub-Contractor Claims

In AES Façade Pte Ltd v WYSE Pte Ltd, the High Court of Singapore heard an application by WYSE Pte Ltd to set aside an order enforcing an adjudication decision in favor of AES Façade Pte Ltd, concerning claims by a sub-contractor under the Building and Construction Industry Security of Payment Act. The court dismissed WYSE's application and refused a stay of execution, ordering the release of funds to AES. The court held that WYSE was not entitled to raise a set-off against the adjudicated amount.

1. Case Overview

1.1 Court

High Court of the Republic of Singapore

1.2 Outcome

Application dismissed

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

The High Court dismissed WYSE's application to set aside an order enforcing an adjudication decision in favor of AES, concerning claims by a sub-contractor.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
AES Façade Pte LtdPlaintiffCorporationApplication grantedWonIan Marc Rosairo de Vaz, Tay Bing Wei, Chek Xinwei Liana
WYSE Pte LtdDefendant, ApplicantCorporationApplication dismissedLostPhilip Antony Jeyaretnam SC, Melissa Thng Huilin, Amogh Nallan Chakravarti

3. Judges

Judge NameTitleDelivered Judgment
Tan Siong ThyeJudgeYes

4. Counsels

Counsel NameOrganization
Ian Marc Rosairo de VazWongPartnership LLP
Tay Bing WeiWongPartnership LLP
Chek Xinwei LianaWongPartnership LLP
Philip Antony Jeyaretnam SCDentons Rodyk & Davidson LLP
Melissa Thng HuilinDentons Rodyk & Davidson LLP
Amogh Nallan ChakravartiDentons Rodyk & Davidson LLP

4. Facts

  1. WYSE was the main contractor for the construction of a 19-storey commercial building.
  2. WYSE engaged AES as its subcontractor for the design, supply, installation, testing and commissioning, and maintenance of the façade works.
  3. The value of the Sub-Contract was $4,965,000.
  4. The completion date for the main contract as well as the Sub-contract was 12 April 2016.
  5. WyWy allegedly claimed liquidated damages of $2.05m against WYSE due to delays.
  6. WYSE attributed about $1.47m of the liquidated damages to AES.
  7. AES served WYSE with Payment Claim No 20 for the amount of $1,280,179.92.
  8. WYSE refused to make payment, stating its right to set-off as a reason for withholding the amount claimed.
  9. The payment response in which WYSE stated its right to set-off as a reason for withholding the amount claimed was filed out of time, on 28 December 2016.
  10. AES lodged an adjudication application with the Singapore Mediation Centre on 29 December 2016 under the Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed).
  11. On 17 February 2017, the Adjudicator gave an Adjudication Determination in AES’s favour for the amount of $1,077,151.37 inclusive of GST and costs.
  12. WYSE refused to pay AES the Adjudicated Amount.
  13. On 28 February 2017, AES took out OS 205 to seek leave of court to enforce the AD as a judgment debt or order of court under s 27(1) of the SOP Act.
  14. WYSE then applied to this court, in SUM 1227, to set aside ORC 1337.

5. Formal Citations

  1. AES Façade Pte Ltd v WYSE Pte Ltd, Originating Summons No 205 of 2017(Summons No 1227 of 2017), [2017] SGHC 171

6. Timeline

DateEvent
Letter of Acceptance dated
Completion date for the main contract and the Sub-contract
Payment response filed out of time
AES lodged an adjudication application with the Singapore Mediation Centre
Adjudication Determination given in AES’s favour
AES took out OS 205 to seek leave of court to enforce the AD
SUM 1227 dismissed
Judgment Date

7. Legal Issues

  1. Set-off
    • Outcome: The court held that WYSE was not entitled to raise a set-off against the adjudicated amount.
    • Category: Substantive
    • Sub-Issues:
      • Failure to serve payment response within the required timeframe
  2. Stay of Execution
    • Outcome: The court refused to grant a stay of execution of ORC 1337 pending the determination of arbitral proceedings.
    • Category: Procedural

8. Remedies Sought

  1. Enforcement of adjudication determination
  2. Setting aside of ORC 1337
  3. Stay of execution of ORC 1337
  4. Monetary damages (liquidated damages)

9. Cause of Actions

  • Claim for enforcement of adjudication determination
  • Claim for liquidated damages (in arbitration)

10. Practice Areas

  • Construction Law
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
W Y Steel Construction Pte Ltd v Osko Pte LtdCourt of AppealYes[2013] 3 SLR 380SingaporeCited for the object and purpose of the Security of Payment Act, which is to provide the construction industry with a low-cost, efficient and quick process for the adjudication of payment disputes.
Vinod Kumar Ramgopal Didwania v Hauslab Design & Build Pte LtdCourt of AppealYes[2017] 1 SLR 890SingaporeCited to reiterate the concept of temporary finality, which undergirds the adjudication regime in Singapore.
RJT Consulting Engineers Ltd v DM Engineering (Northern Ireland) LtdN/AYes[2002] 1WLR 2344United KingdomCited for the principle that parties to a construction contract should “pay now, argue later”.
In re Harmony and Montague Tin and Copper Mining CompanyEnglish Court of AppealYes[1873] 8 Ch App 407United KingdomDiscussed in relation to whether a set-off constitutes payment.
Burton (Collector of Taxes) v Mellham LtdHouse of LordsYes[2006] 1 WLR 2820United KingdomDiscussed in relation to whether a taxpayer could set off a sum of advance corporation tax against a sum of mainstream corporation tax due.
VHE Construction plc v RBSTB Trust Co LtdN/AYes[2000]United KingdomCited to support the position that to permit a set-off against a sum awarded by an adjudicator would be tantamount to defeating the purpose of the Housing Grants, Construction and Regeneration Act 1996.
William Verry Limited v The Mayor and Burgesses of the London Borough of CamdenN/AYes[2006] EWHC 761 (TCC)United KingdomCited to support the position that any contractual right that might allow a party to avoid the obligation to comply with the adjudicator’s decision must be disallowed.
Ferson Contractors Ltd v Levolux AT LtdEnglish Court of AppealYes[2003] EWCA Civ 11United KingdomCited to support the position that the contract must be construed so as to give effect to the intention of Parliament rather than to defeat it.
Parsons Plastics v Purac LtdEnglish Court of AppealYes[2002] EWCA Civ 559United KingdomDiscussed in relation to whether the respondent was entitled to exercise its contractual right of set-off against the ad hoc adjudicator’s decision.
Balfour Beatty v Serco LimitedN/AYes[2004] EWHC 3336United KingdomDiscussed in relation to whether the employer is entitled to set off liquidated and ascertained damages against sums awarded by the adjudicator will depend upon the terms of the contract and the circumstances of the case.
JPA Design and Build Limited v Sentosa (UK) LimitedN/AYes[2009] EWHC 2312 (TCC)United KingdomCited to illustrate that English law allowed two adjudication decisions to be set-off against each other.
Thameside Construction Co Ltd v Stevens and anotherN/AYes[2013] EWHC 2071 (TCC)United KingdomCited to illustrate the circumstances in which set-off could operate.
Admin Construction Pte Ltd v Vivaldi (S) Pte LtdN/AYes[2013] 3 SLR 609SingaporeCited to support the position that a claim dismissed as being either premature or untimely could validly form the subject of a subsequent payment claim and adjudication.
Choi Peng Kum and another v Tan Poh Eng Construction Pte LtdN/AYes[2014] 1 SLR 1210SingaporeCited to illustrate a clause which, if given the reading the plaintiffs contended for, would be caught by s 36(2)(b), which rendered void “a provision that may reasonably be construed as an attempt to deter a person from taking action under this Act”.
Lim Poh Yeoh (alias Aster Lim) v TS Ong Construction Pte LtdHigh CourtYes[2017] SGHC 11SingaporeCited to support the position that parties should not be allowed to withhold payment of the adjudicated sum whilst seeking to effectively overturn the adjudication determination at the same time.
Hyundai Engineering & Construction Co Ltd v International Elements Pte LtdN/AYes[2016] 4 SLR 626SingaporeCited to support the position that the term ‘final determination of those proceedings’ had to be construed in the context of the Act.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)Singapore
Interpretation Act (Cap 1, 2002 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Adjudication Determination
  • Payment Claim
  • Payment Response
  • Set-off
  • Liquidated Damages
  • Security of Payment Act
  • Sub-Contract
  • SIA Conditions of Sub-Contract

15.2 Keywords

  • construction
  • security of payment
  • adjudication
  • set-off
  • subcontractor
  • liquidated damages

16. Subjects

  • Construction Dispute
  • Adjudication
  • Contract Law
  • Civil Procedure

17. Areas of Law

  • Building and Construction Law
  • Sub-contracts
  • Security of Payment