Metropole Pte Ltd v Designshop Pte Ltd: Building & Construction Industry Security of Payment Act Dispute
In Metropole Pte Ltd v Designshop Pte Ltd, the High Court of Singapore dismissed Metropole's application to set aside an adjudication determination in favor of Designshop Pte Ltd. The dispute arose from a payment claim under the Building and Construction Industry Security of Payment Act. Metropole argued that the adjudicator breached the rules of natural justice and acted in excess of his jurisdiction. Justice Vinodh Coomaraswamy rejected Metropole's arguments, finding no material breach of natural justice or jurisdictional error, and ordered Metropole to pay costs.
1. Case Overview
1.1 Court
High Court of the Republic of Singapore1.2 Outcome
Application dismissed
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Metropole's application to set aside an adjudication determination in favor of Designshop was dismissed. The court found no breach of natural justice or jurisdictional error.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Metropole Pte Ltd | Applicant | Corporation | Application dismissed | Lost | |
Designshop Pte Ltd | Respondent | Corporation | Application dismissed | Won |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Vinodh Coomaraswamy | Judge | Yes |
4. Counsels
4. Facts
- Metropole engaged Designshop Architects LLP in June 2009 for architectural services.
- The contract was based on the Singapore Institute of Architects' standard form.
- In January 2012, the partners of the LLP incorporated their practice as Designshop Pte Ltd.
- Designshop Pte Ltd took over the ongoing projects, including Metropole's project.
- Lim Hong Kian, a partner, left Designshop Pte Ltd in January 2016.
- Metropole terminated the contract with Designshop Pte Ltd in February 2016.
- Designshop Pte Ltd issued a payment claim for $453,948.43, which Metropole disputed.
- An adjudication determination was issued on 1 April 2016, allowing some of Designshop's claims.
5. Formal Citations
- Metropole Pte Ltd v Designshop Pte Ltd, Originating Summons No 384 of 2016, [2017] SGHC 45
6. Timeline
Date | Event |
---|---|
Metropole engaged Designshop Architects LLP to provide architectural services. | |
Designshop Architects LLP incorporated as Designshop Pte Ltd. | |
Lim Hong Kian left Designshop Pte Ltd. | |
Designshop Pte Ltd issued a payment claim to Metropole. | |
Metropole served its payment response to Designshop Pte Ltd. | |
Designshop Pte Ltd responded to Metropole’s payment response. | |
Designshop Pte Ltd gave notice to Metropole under s 12(2) of the Building and Construction Industry Security of Payment Act. | |
Designshop Pte Ltd made its adjudication application. | |
Metropole lodged its adjudication response. | |
Adjudication conference took place. | |
Adjudication determination issued. | |
Metropole applied to set aside the adjudication determination. | |
Hearing date. | |
Judgment date. |
7. Legal Issues
- Breach of Natural Justice
- Outcome: The court found a breach of the audi alteram partem rule but held that it was not sufficiently material to cause prejudice to Metropole.
- Category: Procedural
- Sub-Issues:
- Unilateral communication with one party
- Failure to consider all defences
- Jurisdictional Error
- Outcome: The court found that the adjudicator did not exceed his jurisdiction.
- Category: Jurisdictional
- Sub-Issues:
- Determining claims outside the scope of the Act
- Failure to independently assess work done
- Failure to determine existence of contract
- Interpretation of Contract Clause
- Outcome: The court upheld the adjudicator's interpretation of clause 2.3(3) as a clause stipulating conditions for payment, not damages.
- Category: Substantive
8. Remedies Sought
- Setting aside of adjudication determination
9. Cause of Actions
- Claim for progress payment under the Building and Construction Industry Security of Payment Act
10. Practice Areas
- Construction Litigation
- Adjudication
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
SEF Construction Pte Ltd v Skoy Connected Pte Ltd | High Court | Yes | [2010] 1 SLR 733 | Singapore | Cited for the principle that an adjudicator has an express statutory obligation to comply with the rules of natural justice under s 16(3)(c) of the Act. |
Re Shankar Alan s/o Anant Kulkarni | High Court | Yes | [2007] 1 SLR(R) 85 | Singapore | Cited for the test of apparent bias in Singapore law. |
Re Singh Kalpanath | High Court | Yes | [1992] 1 SLR(R) 595 | Singapore | Cited for the principle that private communications between an adjudicator and a party to an adjudication can warrant setting aside the determination on the basis of apparent bias. |
Paice and another v MJ Harding (trading as MJ Harding Contractors) | English High Court | Yes | [2015] EWHC 661 (TCC) | England and Wales | Cited regarding waiver of a breach of the rules of natural justice. |
Farrelly (M&E) Building Services Ltd v Byrne Brothers (Formwork) Ltd | English High Court | Yes | [2013] EWHC 1186 (TCC) | England and Wales | Cited regarding waiver of a breach of the rules of natural justice. |
Dean and Dyball Construction Limited v Kenneth Grubb Associates Ltd | English High Court | Yes | [2003] EWHC 2465 (TCC) | England and Wales | Cited for the principle that where an adjudicator communicates with just one party, the absent party must be told the substance of what has been said and afforded an opportunity to comment upon it. |
AMZ v AXX | High Court | Yes | [2016] 1 SLR 549 | Singapore | Cited for the test for prejudice as applied in the context of arbitration. |
L W Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd and another appeal | Court of Appeal | Yes | [2013] 1 SLR 125 | Singapore | Cited for the test for prejudice as applied in the context of arbitration. |
AM Associates (Singapore) Pte Ltd v Laguna National Golf and Country Club Ltd | High Court | Yes | [2009] SGHC 260 | Singapore | Cited for the principle that the audi alteram partem rule requires the adjudicator to receive both parties’ submissions and consider them. |
W Y Steel Construction Pte Ltd v Osko Pte Ltd | High Court | Yes | [2013] 3 SLR 380 | Singapore | Cited for the principle that a respondent is entitled to raise patent errors on the face of the material before the adjudicator even if those errors were not raised in the payment response. |
Aik Heng Contracts and Services Pte Ltd v Deshin Engineering & Construction Pte Ltd | High Court | Yes | [2015] SGHC 293 | Singapore | Cited for the principle that not all breaches of natural justice warrant the setting aside of an adjudication determination; there must be a material breach. |
JRP & Associates Pte Ltd v Kindly Construction & Services Pte Ltd | High Court | Yes | [2015] 3 SLR 575 | Singapore | Cited for the principle that despite a prior adjudication, the parties remain entirely free to go on to resolve their disputes with full finality. |
Balfour Beatty Construction Ltd v Lambeth Borough Council | High Court of Justice | Yes | [2002] EWHC 597 | England and Wales | Cited in support of the approach that a court hearing an application to set aside an adjudication determination for a breach of the rules of natural justice has less reason to intervene in adjudication than in arbitration. |
Brodyn Pty Ltd t/as Time Cost and Quality v Davenport & Anor | New South Wales Court of Appeal | Yes | [2004] NSWCA 394 | Australia | Cited in support of the approach that a court hearing an application to set aside an adjudication determination for a breach of the rules of natural justice has less reason to intervene in adjudication than in arbitration. |
Front Row Investment Holdings (Singapore) Pte Ltd v Daimler South East Asia Pte Ltd | High Court | Yes | [2010] SGHC 80 | Singapore | Cited for the principle that an adjudicator breaches the rules of natural justice if he disregards some of the defences raised without considering the merits thereof or making an effort to understand them. |
Lanskey v Noxequin | New South Wales Supreme Court | Yes | [2005] NSWSC 963 | Australia | Cited for the principle that the court should look at the face of the documents and the adjudicator’s decision to determine whether the adjudicator has addressed his mind to the merits of the case before him. |
Chip Hup Hup Kee Construction Pte Ltd v Ssangyong Engineering & Construction Co Ltd | High Court | Yes | [2008] SGHC 159 | Singapore | Cited for the principle that an adjudicator is entitled to disregard an additional reason for withholding payment which was not found in the payment response by virtue of the bar in s 15(3) of the Act. |
Chip Hup Hup Kee Construction Pte Ltd v Ssangyong Engineering & Construction Co Ltd | Court of Appeal | Yes | [2010] 1 SLR 658 | Singapore | Cited for the principle that an adjudicator is entitled to disregard an additional reason for withholding payment which was not found in the payment response by virtue of the bar in s 15(3) of the Act. |
TMM Division Maritima SA de CV v Pacific Richfield Marine Pte Ltd | High Court | Yes | [2013] 4 SLR 972 | Singapore | Cited for the principle that the fact that some matters are not found in the adjudication determination does not mean that the adjudicator ignored or wrongly excluded such matters from his consideration. |
BLB and another v BLC and others | High Court | Yes | [2013] 4 SLR 1169 | Singapore | Cited for the principle that the fact that some matters are not found in the adjudication determination does not mean that the adjudicator ignored or wrongly excluded such matters from his consideration. |
Soh Beng Tee & Co Pte Ltd v Fairmount Development Pte Ltd | High Court | Yes | [2007] 3 SLR(R) 86 | Singapore | Cited for the principle that only material breaches justify setting aside an adjudication determination. |
APV Sdn Bhd v APW Pte Ltd | Singapore Subordinate Courts | Yes | [2013] SGSOP 24 | Singapore | Cited for the approach under W Y Steel requires him to examine the documents exhibited in the adjudication application to see if there is any obvious contradiction between the said documents and the payment claim. |
SSC Plenty Road v Construction Engineering (Aust) Pty Ltd & Anor | Supreme Court of Victoria | Yes | [2015] VSC 631 | Australia | Cited for the principle that an adjudicator has a duty to assess the amount of work done and the value thereof. |
Krongold Constructions (Aust) Pty Ltd v SR & RS Wales Pty Ltd | Supreme Court of Victoria | Yes | [2016] VSC 94 | Australia | Cited for the principle that an adjudicator has a duty to assess the amount of work done and the value thereof. |
Pacific General Securities Ltd v Soliman & Sons Pty Ltd | New South Wales Supreme Court | Yes | [2006] NSWSC 13 | Australia | Cited for the principle that an adjudicator is entitled to readily find in favor of the claimant on the merits of the claim. |
RN & Associates Pte Ltd v TPX Builders Pte Ltd | High Court | Yes | [2013] 1 SLR 848 | Singapore | Cited for the principle that s 4(1) of the Act requires an adjudicator to determine the existence of a written contract between the parties. |
RJT Consulting Engineers Ltd v DM Engineering (Northern Ireland) Ltd | England and Wales Court of Appeal (Civil Division) | Yes | [2002] EWCA Civ 270 | England and Wales | Cited for the principle that to satisfy the requirement of a written contract, all the relevant terms agreed must be recorded in writing. |
Northbuild Construction Sunshine Coast Pty Ltd v Beyfield Pty Ltd | Supreme Court of Queensland | Yes | [2014] QSC 80 | Australia | Cited for the principle that an adjudicator must identify the relevant terms of the contract upon which the claim is made. |
Laing O’Rourke Australia Construction Pty Ltd v Samsung C & T Corporation | Supreme Court of Western Australia | Yes | [2015] WASC 237 | Australia | Cited for the principle that an adjudicator would fail to perform that task, and would misapprehend his statutory function, if he determines the merits of the payment dispute otherwise than by reference to the terms of the construction contract which are before him. |
Chatsworth Investments Ltd v Cussins (Contractors) Ltd | Court of Appeal | Yes | [1969] 1 WLR 1 | England and Wales | Cited for the principle that novation can be implied from conduct. |
Enterprise Managed Services Ltd v Tony McFadden Utilities Ltd | High Court of Justice | Yes | [2009] EWHC 3222 (TCC) | England and Wales | Cited for the principle that novation can be implied from conduct. |
H & R Johnson Tiles Ltd & Anor v H & R Johnson (M) Bhd | Federal Court | Yes | [1998] 4 MLJ 13 | Malaysia | Cited for the principle that novation can be implied from conduct. |
Tienrui Design & Construction Pte Ltd v G & Y Trading and Manufacturing Pte Ltd | High Court | Yes | [2015] 5 SLR 852 | Singapore | Cited for the principle that a party who carries out any construction work or supplies any goods or services under a construction contract is entitled to progress payments. |
Qingjian International (South Pacific) Group Development Co Pte Ltd v Capstone Engineering Pte Ltd | High Court | Yes | [2014] SGHCR 5 | Singapore | Cited for the principle that for the purposes of the Act, the definition of what constitutes a contract in writing is very wide. |
13. Applicable Rules
Rule Name |
---|
Order 95, Rule 3 of the Rules of Court (Cap 322, R 5, 2014 Rev Ed) |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) | Singapore |
Building Control Act (Cap 29, 1999 Rev Ed) | Singapore |
International Arbitration Act (Cap 143A, 2002 Rev Ed) | Singapore |
Arbitration Act (Cap 10 2002 Rev Ed) | Singapore |
Contract (Rights of Third Parties) Act (Cap 53B, 2002 Rev Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Adjudication determination
- Payment claim
- Payment response
- Construction cost
- Progress payment
- Rules of natural justice
- Jurisdictional error
- SIA terms
- Qualified person
- Contingency sum
15.2 Keywords
- Adjudication
- Construction
- Payment
- Security of Payment Act
- Natural Justice
- Jurisdiction
17. Areas of Law
Area Name | Relevance Score |
---|---|
Construction Law | 90 |
Building and Construction Contracts | 85 |
Adjudication | 75 |
Security of Payment | 70 |
Administrative Law | 30 |
Civil Procedure | 20 |
16. Subjects
- Construction Law
- Adjudication
- Contract Law
- Civil Procedure