GPE Pte Ltd v Siemens Pte Ltd: Construction Law, Damages for Defects & Delay

In GPE Pte Ltd v Siemens Pte Ltd, heard in the High Court of Singapore on 6 September 2018, GPE sued Siemens for losses arising from delays and variation works related to the construction of E-Houses across three projects (Jangkrik, 030, and 103). Siemens counterclaimed for liquidated damages, overpayment, and back charges for rectification of defects. The court allowed some of GPE's claims for losses and variation works to be assessed, entered judgment for certain completed works, and also allowed some of Siemens' counterclaims for liquidated damages and back charges, ordering assessment for others. The court dismissed some of GPE's claims and Siemens' counterclaims. The claims included breach of contract and delays. The court ordered that all judgments on the claims and counterclaims for each project are to be consolidated and set off accordingly.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Partial Judgment for Plaintiff; Partial Judgment for Defendant; Assessment Ordered

1.3 Case Type

Civil

1.4 Judgment Type

Judgment

1.5 Jurisdiction

Singapore

1.6 Description

GPE sued Siemens for losses and variations in constructing E-Houses. Siemens counterclaimed for delays and defects. The court allowed some claims and counterclaims, ordering assessment.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
GPE Pte LtdPlaintiffCorporationPartial Judgment for Plaintiff; Assessment OrderedPartial
Siemens Pte LtdDefendantCorporationPartial Judgment for Defendant; Assessment OrderedPartial

3. Judges

Judge NameTitleDelivered Judgment
Chan Seng OnnJudgeYes

4. Counsels

4. Facts

  1. Siemens engaged GPE to fabricate, assemble, and erect the structure and casing of three E-Houses.
  2. The three projects were the Jangkrik Project, the 030 Project, and the 103 Project.
  3. GPE claimed for losses arising out of delays allegedly caused by Siemens.
  4. GPE claimed for variation works allegedly undertaken.
  5. Siemens counterclaimed for liquidated damages arising from delays allegedly caused by GPE.
  6. Siemens counterclaimed for back charges for costs incurred to rectify defects allegedly caused by GPE.
  7. The court found that the defendant was late in the issuance of drawings and materials.

5. Formal Citations

  1. GPE Pte Ltd v Siemens Pte Ltd, Suits No 532 and 736 of 2016, [2018] SGHC 194

6. Timeline

DateEvent
Trial began
Trial continues
Trial continues
Trial continues
Trial continues
Trial continues
Trial continues
Trial continues
Trial continues
Judgment reserved
Further hearing
Further hearing
Judgment issued

7. Legal Issues

  1. Breach of Contract
    • Outcome: Some claims allowed, some dismissed, assessment ordered for others.
    • Category: Substantive
    • Sub-Issues:
      • Failure to complete works
      • Defective works
      • Delays in completion
  2. Damages for Delay
    • Outcome: Assessment ordered to determine losses resulting from delays.
    • Category: Substantive
    • Sub-Issues:
      • Prolongation costs
      • Idle machinery and manpower costs
  3. Variation Works
    • Outcome: Assessment ordered to determine reasonable costs for variation works.
    • Category: Substantive
    • Sub-Issues:
      • Quantum meruit basis for pricing
      • Compliance with variation clauses
  4. Liquidated Damages
    • Outcome: Judgment entered for liquidated damages based on expert assessment.
    • Category: Substantive
    • Sub-Issues:
      • Attribution of delay
      • Critical path analysis
  5. Pleadings
    • Outcome: Court held that pleadings could be read broadly to encompass claim for losses arising out of idle time.
    • Category: Procedural
    • Sub-Issues:
      • Sufficiency of generality
      • Explicit mention of claim

8. Remedies Sought

  1. Monetary Damages

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Commercial Litigation
  • Construction Law
  • Arbitration

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
No cited cases

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
No applicable statutes

15. Key Terms and Keywords

15.1 Key Terms

  • E-Houses
  • Variation works
  • Liquidated damages
  • Back charges
  • Idle time
  • Prolongation costs
  • Quantum meruit
  • Weld Procedure Specifications
  • Cutting plan
  • Critical path analysis

15.2 Keywords

  • construction
  • contract
  • damages
  • delay
  • E-Houses
  • variation
  • liquidated damages
  • Singapore

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Contract Law
  • Damages