GPE Pte Ltd v Siemens Pte Ltd: Construction Law, Damages for Defects & Delay
In GPE Pte Ltd v Siemens Pte Ltd, heard in the High Court of Singapore on 6 September 2018, GPE sued Siemens for losses arising from delays and variation works related to the construction of E-Houses across three projects (Jangkrik, 030, and 103). Siemens counterclaimed for liquidated damages, overpayment, and back charges for rectification of defects. The court allowed some of GPE's claims for losses and variation works to be assessed, entered judgment for certain completed works, and also allowed some of Siemens' counterclaims for liquidated damages and back charges, ordering assessment for others. The court dismissed some of GPE's claims and Siemens' counterclaims. The claims included breach of contract and delays. The court ordered that all judgments on the claims and counterclaims for each project are to be consolidated and set off accordingly.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Partial Judgment for Plaintiff; Partial Judgment for Defendant; Assessment Ordered
1.3 Case Type
Civil
1.4 Judgment Type
Judgment
1.5 Jurisdiction
Singapore
1.6 Description
GPE sued Siemens for losses and variations in constructing E-Houses. Siemens counterclaimed for delays and defects. The court allowed some claims and counterclaims, ordering assessment.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
GPE Pte Ltd | Plaintiff | Corporation | Partial Judgment for Plaintiff; Assessment Ordered | Partial | |
Siemens Pte Ltd | Defendant | Corporation | Partial Judgment for Defendant; Assessment Ordered | Partial |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Chan Seng Onn | Judge | Yes |
4. Counsels
4. Facts
- Siemens engaged GPE to fabricate, assemble, and erect the structure and casing of three E-Houses.
- The three projects were the Jangkrik Project, the 030 Project, and the 103 Project.
- GPE claimed for losses arising out of delays allegedly caused by Siemens.
- GPE claimed for variation works allegedly undertaken.
- Siemens counterclaimed for liquidated damages arising from delays allegedly caused by GPE.
- Siemens counterclaimed for back charges for costs incurred to rectify defects allegedly caused by GPE.
- The court found that the defendant was late in the issuance of drawings and materials.
5. Formal Citations
- GPE Pte Ltd v Siemens Pte Ltd, Suits No 532 and 736 of 2016, [2018] SGHC 194
6. Timeline
Date | Event |
---|---|
Trial began | |
Trial continues | |
Trial continues | |
Trial continues | |
Trial continues | |
Trial continues | |
Trial continues | |
Trial continues | |
Trial continues | |
Judgment reserved | |
Further hearing | |
Further hearing | |
Judgment issued |
7. Legal Issues
- Breach of Contract
- Outcome: Some claims allowed, some dismissed, assessment ordered for others.
- Category: Substantive
- Sub-Issues:
- Failure to complete works
- Defective works
- Delays in completion
- Damages for Delay
- Outcome: Assessment ordered to determine losses resulting from delays.
- Category: Substantive
- Sub-Issues:
- Prolongation costs
- Idle machinery and manpower costs
- Variation Works
- Outcome: Assessment ordered to determine reasonable costs for variation works.
- Category: Substantive
- Sub-Issues:
- Quantum meruit basis for pricing
- Compliance with variation clauses
- Liquidated Damages
- Outcome: Judgment entered for liquidated damages based on expert assessment.
- Category: Substantive
- Sub-Issues:
- Attribution of delay
- Critical path analysis
- Pleadings
- Outcome: Court held that pleadings could be read broadly to encompass claim for losses arising out of idle time.
- Category: Procedural
- Sub-Issues:
- Sufficiency of generality
- Explicit mention of claim
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Commercial Litigation
- Construction Law
- Arbitration
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
No cited cases |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- E-Houses
- Variation works
- Liquidated damages
- Back charges
- Idle time
- Prolongation costs
- Quantum meruit
- Weld Procedure Specifications
- Cutting plan
- Critical path analysis
15.2 Keywords
- construction
- contract
- damages
- delay
- E-Houses
- variation
- liquidated damages
- Singapore
17. Areas of Law
Area Name | Relevance Score |
---|---|
Construction Law | 90 |
Damages | 85 |
Breach of Contract | 50 |
Contract Law | 40 |
16. Subjects
- Construction Dispute
- Contract Law
- Damages