Yau Lee Construction v Far East Square: SOPA Dispute over Payment Claim Validity and Adjudicator's Jurisdiction

In Yau Lee Construction (Singapore) Pte Ltd v Far East Square Pte Ltd, the Singapore High Court addressed a dispute arising from the Building and Construction Industry Security of Payment Act (SOPA). Yau Lee Construction, the contractor, sought payment from Far East Square, the developer, for a construction project. The developer applied to set aside an adjudication determination in favor of the contractor, arguing the payment claim was invalid, the adjudication application was untimely, and the adjudicator exceeded jurisdiction. Justice Lee Seiu Kin dismissed the developer's application, finding they were estopped from raising objections due to failing to file a payment response.

1. Case Overview

1.1 Court

High Court of Singapore

1.2 Outcome

Application to set aside the adjudication determination and the order of court enforcing the adjudication determination was dismissed.

1.3 Case Type

Building and Construction Law

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Singapore High Court case involving Yau Lee Construction and Far East Square. The dispute centered on the validity of a payment claim and the adjudicator's jurisdiction.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Yau Lee Construction (Singapore) Pte LtdApplicantCorporationApplication AllowedWonRaymond Chan, Oung Hui Wen Karen
Far East Square Pte LtdRespondentCorporationApplication DismissedLostChuah Chee Kian Christopher, Lee Hwai Bin, Muhammad Asfian Bin Mohaimi, Valerie Koh, Deborah Hoe

3. Judges

Judge NameTitleDelivered Judgment
Lee Seiu KinJudgeYes

4. Counsels

Counsel NameOrganization
Raymond ChanChan Neo LLP
Oung Hui Wen KarenChan Neo LLP
Chuah Chee Kian ChristopherWongPartnership LLP
Lee Hwai BinWongPartnership LLP
Muhammad Asfian Bin MohaimiWongPartnership LLP
Valerie KohWongPartnership LLP
Deborah HoeWongPartnership LLP

4. Facts

  1. Far East Square Pte Ltd was the developer for a building and construction project.
  2. Yau Lee Construction (Singapore) Pte Ltd was the main contractor for the project.
  3. The developer engaged the contractor via a Letter of Award dated 29 November 2010 for $82.8m.
  4. The contractor submitted 18 payment claims after the expiry of the maintenance period.
  5. The architect issued a final certificate certifying the final balance payable.
  6. The contractor submitted payment claim number 75 (PC 75), which was a repeat of PC 73.
  7. The developer did not issue a payment response to PC 75.

5. Formal Citations

  1. Yau Lee Construction (Singapore) Pte Ltd v Far East Square Pte Ltd, Originating Summons No 258 of 2018, [2018] SGHC 261

6. Timeline

DateEvent
Letter of Award (LOA) signed
Phase one of the works completed
Formal contractual documents signed
Phase two of the works completed
Maintenance period of the works commenced
Maintenance period of the works ended
Contractor submitted payment claim number 55
Contractor submitted payment claim number 72
Contractor submitted payment claim number 73 (PC 73)
Architect issued a final certificate
Developer issued a payment response entitled 'Payment Response Reference Number 73 (Final)'
Contractor submitted payment claim number 74 (PC 74)
Architect informed the contractor that he had proceeded to issue the final certificate
Contractor submitted payment claim number 75 (PC 75)
Architect issued another letter repeating that no further progress payments shall be issued
Contractor lodged an adjudication application in relation to PC 75
Adjudicator issued the adjudication determination
Order of court for the enforcement of the adjudication determination
Hearing before Lee Seiu Kin J
Judgment by Lee Seiu Kin J

7. Legal Issues

  1. Validity of Payment Claim
    • Outcome: The court found that the developer was estopped from arguing the invalidity of the payment claim and that the payment claim was valid.
    • Category: Substantive
    • Sub-Issues:
      • Submission of payment claim after final certificate
      • Waiver of contractual requirements
    • Related Cases:
      • [2015] 4 SLR 615
      • [2016] 5 SLR 1011
  2. Adjudicator's Jurisdiction
    • Outcome: The court found that the adjudicator had jurisdiction to grant the additional preliminaries and that his decision was not reviewable.
    • Category: Jurisdictional
    • Sub-Issues:
      • Exceeding jurisdiction by assessing additional preliminaries
      • Applicability of statutory timelines
    • Related Cases:
      • [2018] 1 SLR 317
      • [2017] 4 SLR 277
  3. Estoppel
    • Outcome: The court found that the developer was estopped from raising objections due to its failure to file a payment response.
    • Category: Procedural
    • Sub-Issues:
      • Failure to file payment response
      • Duty to speak
    • Related Cases:
      • [2018] 1 SLR 317

8. Remedies Sought

  1. Setting aside of adjudication determination
  2. Stay of enforcement of adjudication determination

9. Cause of Actions

  • Claim for payment under the Building and Construction Industry Security of Payment Act

10. Practice Areas

  • Construction Law
  • Commercial Litigation
  • Arbitration

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Lau Fook Hoong Adam v GTH Engineering & Construction Pte LtdHigh CourtYes[2015] 4 SLR 615SingaporeCited regarding the validity of payment claims submitted after the final payment claim and/or final certificate had been issued.
Audi Construction Pte Ltd v Kian Hiap Construction Pte LtdCourt of AppealYes[2018] 1 SLR 317SingaporeCited for the principle that a respondent has a duty to raise objections to a payment claim in its payment response, and failure to do so constitutes a waiver of the right to object.
Grouteam Pte Ltd v UES Holdings Pte LtdCourt of AppealYes[2016] 5 SLR 1011SingaporeCited regarding the permissibility of a payment claim that merely repeated an earlier claim under section 10(4) of the SOPA.
Metropole Pte Ltd v Designshop Pte LtdHigh CourtYes[2017] 4 SLR 277SingaporeCited regarding the adjudicator’s jurisdiction to interpret a term of the parties’ contract.
W Y Steel Construction Pte Ltd v Osko Pte LtdCourt of AppealYes[2013] 3 SLR 380SingaporeCited regarding the consequences of a respondent failing to ventilate reasons for withholding payment within the timelines prescribed by the Act.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 10(1)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 10(4)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 15(3)(a)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Adjudication determination
  • Payment claim
  • Payment response
  • Final certificate
  • SOPA
  • Estoppel
  • Jurisdiction
  • Additional preliminaries
  • Maintenance period

15.2 Keywords

  • Construction
  • SOPA
  • Adjudication
  • Payment Claim
  • Singapore

16. Subjects

  • Construction Dispute
  • Arbitration
  • Contract Law

17. Areas of Law

  • Building and Construction Law
  • Dispute Resolution
  • Contract Law
  • Arbitration Law