BQP v BQQ: Appeal Against Jurisdictional Ruling in SIAC Arbitration

In Originating Summons No 534 of 2016, BQP appealed against the jurisdictional ruling of an arbitral tribunal in SIAC Arbitration No 197 of 2014, where BQQ was the claimant. The High Court dismissed BQP's challenge to the award and subsequently dismissed BQP's application for leave to appeal. The central issue was whether a Round Logs Supply Memorandum of Agreement (RLS MOA) had been superseded by a Merchantability Wood Agreement (MWA). The court held that the RLS MOA was not superseded by the MWA, and the tribunal had jurisdiction to hear the disputes.

1. Case Overview

1.1 Court

High Court of the Republic of Singapore

1.2 Outcome

Plaintiff's application for leave to appeal dismissed.

1.3 Case Type

Arbitration

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

BQP appeals against a jurisdictional ruling in a SIAC arbitration. The court dismisses BQP's application for leave to appeal, upholding the tribunal's jurisdiction.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
BQPPlaintiff, RespondentCorporationApplication for leave to appeal dismissedLost
BQQDefendant, ClaimantCorporationTribunal's jurisdictional ruling upheldWon

3. Judges

Judge NameTitleDelivered Judgment
Quentin LohJudgeYes

4. Counsels

4. Facts

  1. The Plaintiff and the Defendant had commercial dealings in the forestry industry since at least 2003.
  2. The parties entered into a Master Agreement on 18 September 2009.
  3. The Master Agreement included the Round Logs Supply Memorandum of Agreement (RLS MOA).
  4. The RLS MOA contained a Singapore International Arbitration Centre (SIAC) arbitration clause.
  5. The parties subsequently entered into a Merchantability Wood Agreement (MWA) on 10 December 2009.
  6. The MWA contained an Indonesian National Board of Arbitration (BANI) arbitration clause.
  7. A dispute arose, and the Defendant commenced SIAC arbitration proceedings against the Plaintiff.
  8. The Plaintiff challenged the tribunal's jurisdiction, arguing that the RLS MOA had been superseded by the MWA.

5. Formal Citations

  1. BQP v BQQ, Originating Summons No 534 of 2016, [2018] SGHC 55

6. Timeline

DateEvent
Commercial dealings between the Plaintiff, the Defendant, and their affiliates began in the forestry industry.
The group of companies to which the Defendant belongs and CAH, an affiliate of the Plaintiff, entered into a Memorandum of Understanding.
The Plaintiff and the Defendant signed a Master Agreement.
The Plaintiff and the Defendant signed the JOA MOA.
The Plaintiff and the Defendant signed the Shares MOA.
The Plaintiff and the Defendant signed the RLS MOA.
The Plaintiff and PER, an affiliate of the Defendant, entered into a Commission Entitlement Agreement.
The Defendant and SUM entered into the Merchantability Wood Agreement.
The Defendant and LES entered into a performance bond.
The Defendant and PER commenced SIAC arbitration proceedings against the Plaintiff and SUM in Singapore.
Procedural Order No 1 issued by the Tribunal.
The Tribunal issued the Award.
Originating Summons No 534 of 2016 was filed.
Oral arguments were heard.
The court dismissed the Plaintiff’s challenge on the Award.
The court gave brief oral grounds dismissing the Plaintiff's challenge on the Award.
Summons No 4722 of 2017 was filed.
Hearing for Summons No 4722 of 2017.
Parties filed further simultaneous written submissions.
Parties filed written reply submissions.
The court dismissed the Plaintiff’s application in SUM 4722/2017 for leave to appeal and gave the full grounds for the decision.

7. Legal Issues

  1. Jurisdiction of Arbitral Tribunal
    • Outcome: The court held that the arbitral tribunal had jurisdiction to hear the disputes.
    • Category: Jurisdictional
    • Sub-Issues:
      • Supersession of arbitration agreements
      • Interpretation of contract clauses
  2. Admissibility of Pre-Contractual Negotiations
    • Outcome: The court declined to grant leave to appeal on the question of admissibility of pre-contractual negotiations, finding no general principle to be decided for the first time or question of public importance.
    • Category: Procedural

8. Remedies Sought

  1. Monetary Damages

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Arbitration
  • Commercial Litigation

11. Industries

  • Forestry

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Xia Zhengyan v Geng ChangqingCourt of AppealYes[2015] 3 SLR 732SingaporeCited as a case that left open the question of whether pre-contractual negotiations were admissible in evidence to construe written agreements.
Sembcorp Marine Ltd v PPL Holdings Pte LtdCourt of AppealYes[2013] 4 SLR 193SingaporeCited as a case that left open the question of whether pre-contractual negotiations were admissible in evidence to construe written agreements.
Zurich Insurance (Singapore) Pte Ltd v B-Gold Interior Design & Construction Pte LtdCourt of AppealYes[2008] 3 SLR(R) 1029SingaporeCited as a case that left open the question of whether pre-contractual negotiations were admissible in evidence to construe written agreements.
Lee Kuan Yew v Tang Liang HongN/AYes[1997] 2 SLR(R) 862SingaporeCited for the three limbs an applicant seeking leave to appeal must demonstrate.
Y.E.S. F&B Group Pte Ltd v Soup Restaurant Singapore Pte LtdCourt of AppealYes[2015] 5 SLR 1187SingaporeCited as a case that left open the question of whether pre-contractual negotiations were admissible in evidence to construe written agreements.
HSBC Trustee (Singapore) Ltd v Lucky Realty Co Pte LtdN/AYes[2015] 3 SLR 885SingaporeCited for the principle that there is only one body of principles applicable to construing contracts in Singapore law.
Browne v DunnN/AYes(1893) 6 R 67N/ACited as an example of a common law concept that may not make sense to a businessman from a civil law country.

13. Applicable Rules

Rule Name
SIAC Rules
SIAC Rules 2013, Rule 16.2

14. Applicable Statutes

Statute NameJurisdiction
International Arbitration Act (Cap 143A, 2002 Rev Ed)Singapore
International Arbitration Act (Cap 143A, 2002 Rev Ed), s 10Singapore
Rules of Court (Cap 322, R 5, 2014 Rev Ed), Order 69ASingapore
Evidence Act (Cap 97, 1997 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Arbitration
  • Jurisdiction
  • Pre-contractual negotiations
  • Round Logs Supply Memorandum of Agreement
  • Merchantability Wood Agreement
  • SIAC
  • BANI
  • Definite legal agreement
  • Onshore agreement
  • Offshore agreement

15.2 Keywords

  • arbitration
  • jurisdiction
  • contract law
  • Singapore
  • SIAC
  • BANI
  • forestry
  • pre-contractual negotiations

17. Areas of Law

16. Subjects

  • Arbitration
  • Contractual Interpretation
  • Jurisdiction