BRS v BRQ: Setting Aside Arbitration Award for Breach of Natural Justice & Time Limit Extension

In BRS v BRQ, the Singapore Court of Appeal addressed two appeals concerning an arbitration award related to a hydroelectric power plant project. BRS, the Seller, appealed against the dismissal of its application to set aside the award, while BRQ, the Buyer, appealed against the dismissal of its application to set aside the portion of the award related to the cut-off date. The court dismissed the Seller's appeal, finding it time-barred, and allowed the Buyer's appeal in part, remitting the issue of transmission line delays to the Tribunal for reconsideration. The court found that the Tribunal had breached natural justice by failing to consider evidence related to the transmission line delays.

1. Case Overview

1.1 Court

Court of Appeal of the Republic of Singapore

1.2 Outcome

Civil Appeal No 34 of 2019 dismissed. Civil Appeal No 35 of 2019 allowed in part.

1.3 Case Type

Civil

1.4 Judgment Type

Judgment

1.5 Jurisdiction

Singapore

1.6 Description

Singapore Court of Appeal addresses setting aside an arbitration award, focusing on breaches of natural justice and time limit extensions. Appeal allowed in part.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
BRSAppellant, DefendantCorporationAppeal DismissedLost
BRQRespondent, Appellant, PlaintiffCorporationAppeal Allowed in PartPartial
BRRRespondent, Appellant, PlaintiffCorporationAppeal Allowed in PartPartial

3. Judges

Judge NameTitleDelivered Judgment
Judith PrakashJudge of AppealNo
Steven ChongJudge of AppealNo
Woo Bih LiJudgeYes

4. Counsels

4. Facts

  1. BRS was undertaking a project to build a hydroelectric power plant through a special purpose vehicle company, BRR.
  2. BRR ran out of funds, and BRQ entered as an investor to inject fresh funds for the Project to continue.
  3. Under a Securities Purchase Agreement, BRQ contracted to buy all the shares in BRR.
  4. The SPA envisaged that the Project would be completed by 31 March 2013, and the Project cost would be about S$170m.
  5. The Project was not wet commissioned on 31 March 2013, but more than two years later on 31 October 2015.
  6. The arbitral tribunal issued a final award that was in substance in favour of the Claimants but limited the Seller’s liability to 30 June 2014.
  7. Both the Seller and Claimants filed separate Originating Summonses to set aside portions of the Award.

5. Formal Citations

  1. BRS v BRQ and another and another appeal, , [2020] SGCA 108
  2. BRS v BRQ, , Civil Appeal No 34 of 2019
  3. BRQ v BRS, , Civil Appeal No 35 of 2019
  4. BRS v BRQ, , Originating Summons No 770 of 2018
  5. BRQ v BRS, , Originating Summons No 512 of 2018

6. Timeline

DateEvent
SPV carried on with the Project
SPV entered into the Bulk Power Transmission Agreement with a grid company
SPV ran out of funds
Parties entered into the Securities Purchase Agreement
Project failed to achieve wet commissioning
Buyer issued a Cost Overrun Notice to the Seller
Seller acknowledged the Cost Overrun Notice
Buyer began to oversee the Project more closely
Buyer issued a takeover notice and took over full control of the Project
Legal notice for the arbitration proceedings issued by the Buyer
Buyer initiated arbitration proceedings against the Seller and its parent company
Transmission line works completed
Project was wet commissioned
Award was issued
Award received by the parties
Seller requested the Tribunal to correct the Award
Tribunal dismissed the Correction Request
Claimants applied to set aside part of the Award
Seller sought to set aside other parts of the Award
Civil Appeal No 34 of 2019 and Civil Appeal No 35 of 2019
Judgment reserved
Judgment

7. Legal Issues

  1. Breach of Natural Justice
    • Outcome: The court found that the Tribunal breached natural justice by failing to consider evidence related to transmission line delays, which caused real and actual prejudice to the Claimants.
    • Category: Substantive
    • Sub-Issues:
      • Failure to consider evidence
      • Failure to consider arguments
  2. Time Limit for Setting Aside Award
    • Outcome: The court held that the Seller's setting-aside application was time-barred because the Correction Request was not in substance an Art 33 correction request.
    • Category: Procedural
    • Sub-Issues:
      • Extension of time limit
      • Interpretation of Article 33
      • Correction of award

8. Remedies Sought

  1. Setting Aside of Arbitration Award
  2. Remission of Award to Tribunal

9. Cause of Actions

  • Breach of Contract
  • Setting Aside Arbitration Award

10. Practice Areas

  • Arbitration
  • Commercial Litigation

11. Industries

  • Construction
  • Energy

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
BRQ and another v BRS and another and another matterHigh CourtYes[2019] SGHC 260SingaporeCited for background facts of the dispute.
State of Arunachal Pradesh v Damani Construction CoSupreme CourtYes(2007) 10 SCC 742IndiaCited regarding the interpretation of Section 33 of the Arbitration and Conciliation Act 1996.
Shayam Sunder v Kotak Securities LtdHigh Court of DelhiYes(2017) Del 4157IndiaCited for following the decision in State of Arunachal Pradesh v Damani Construction Co.
M/s Ved Prakash Mithal and Sons v Union of IndiaSupreme CourtYesM/s Ved Prakash Mithal and Sons v Union of IndiaIndiaCited regarding the interpretation of Section 34(3) of the Arbitration and Conciliation Act 1996.
Municipal Corporation v Walter Bau AGBombay High CourtYes(2019) SCC OnLine Bom 2920IndiaCited regarding the interpretation of Section 34 of the Indian 1996 Act.
Opotiki Packing & Coolstorage Ltd v Opotiki Fruitgrowers Co-operative Ltd (In Receivership)New Zealand Court of AppealYes[2003] 1 NZLR 205New ZealandCited regarding the interpretation of Article 33 of the First Schedule of the New Zealand Arbitration Act.
Todd Petroleum Mining Co Ltd v Shell (Petroleum Mining) Co LtdNew Zealand Court of AppealYes[2015] 2 NZLR 180New ZealandCited regarding the interpretation of Article 33(3) and 34(3) of the Model Law.
ABC Co v XYZ Co LtdHigh CourtYes[2003] 3 SLR(R) 546SingaporeCited for the principle that the court does not have the power to extend the three-month time limit in Article 34(3).
BXS v BXTHigh CourtYes[2019] 4 SLR 390SingaporeCited for the principle that the court does not have the power to extend the three-month time limit in Article 34(3).
Gannet Shipping Ltd v Eastrade Commodities Inc and another applicationCommercial CourtYes[2002] 1 QB (Com Ct) 713EnglandCited for the distinction between errors affecting the tribunal’s thought and errors in the tribunal’s thought process.
Soh Beng Tee & Co Pte Ltd v Fairmount Development Pte LtdHigh CourtYes[2007] 3 SLR(R) 86SingaporeCited for the requirements for setting aside an arbitral award on the breach of natural justice ground.
AKN and another v ALC and others and other appealsCourt of AppealYes[2015] 3 SLR 488SingaporeCited for the principle that to fail to consider an important issue that has been pleaded in an arbitration is a breach of natural justice.
TMM Division Maritime SA de CV v Pacific Richfield Marine Pte LtdHigh CourtYes[2013] 4 SLR 972SingaporeCited for the principle that as long as one argument resolves the issue, there is no justification for insisting that the arbitral tribunal go on to consider the other arguments which have been rendered academic.
Front Row Investment Holdings (Singapore) Pte Ltd v Daimler South East Asia Pte LtdHigh CourtYes[2010] SGHC 80SingaporeCited as an instance where such a clear and inescapable inference that the tribunal had failed to consider an important issue.
European Grain and Shipping Ltd v JohnstonEnglish Court of AppealYes[1983] 2 WLR 241EnglandCited for the doctrine of approbation and reprobation.
BWG v BWFHigh CourtYes[2020] 1 SLR 1296SingaporeCited for the principle that the doctrine of approbation and reprobation applies when the parties who sought to advance inconsistent positions had already secured actual benefits from their prior positions.

13. Applicable Rules

Rule Name
UNCITRAL Model Law on International Commercial Arbitration
UNCITRAL Model Law on International Commercial Arbitration Art 33
UNCITRAL Model Law on International Commercial Arbitration Art 34(2)(a)(ii)
UNCITRAL Model Law on International Commercial Arbitration Art 34(3)
UNCITRAL Model Law on International Commercial Arbitration Art 34(4)

14. Applicable Statutes

Statute NameJurisdiction
International Arbitration ActSingapore
International Arbitration Act (Cap 143A, 2002 Rev Ed) s 24(b)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Wet Commissioning
  • Cost Overrun
  • Securities Purchase Agreement
  • Bulk Power Transmission Agreement
  • Cut-off Date
  • Penstock
  • Transmission Line
  • Rewelding Method
  • Relining Method

15.2 Keywords

  • Arbitration
  • Setting Aside
  • Breach of Natural Justice
  • Time Limit
  • International Arbitration Act
  • UNCITRAL Model Law
  • Construction Dispute
  • Energy Project

17. Areas of Law

16. Subjects

  • Arbitration
  • Contract Law
  • Civil Procedure