Range Construction v Goldbell Engineering: Setting Aside Adjudication Determination under SOPA
Range Construction Pte Ltd applied to the High Court of Singapore to set aside part of an adjudication determination in favor of Goldbell Engineering Pte Ltd. The adjudication concerned a construction project where Range Construction sought payment, including retention sums and variation claims, while Goldbell Engineering claimed liquidated damages. Lee Seiu Kin J dismissed Range Construction's application, finding no basis to set aside the adjudicator's determination regarding liquidated damages and the valuation of the variation claim.
1. Case Overview
1.1 Court
High Court of the Republic of Singapore1.2 Outcome
Application dismissed
1.3 Case Type
Building and Construction Law
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Range Construction's application to set aside an adjudication determination awarding liquidated damages and valuing a variation claim was dismissed. The court found no jurisdictional errors or breaches of the fair hearing rule.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Range Construction Pte Ltd | Applicant | Corporation | Application dismissed | Lost | Choo Poh Hua Josephine, Chin Yan Xun |
Goldbell Engineering Pte Ltd | Respondent | Corporation | Application dismissed | Won | Campos Conrad Melville, Chong Jia Hao, Michelle Lim Ann Nee |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Lee Seiu Kin | Judge | Yes |
4. Counsels
Counsel Name | Organization |
---|---|
Choo Poh Hua Josephine | WongPartnership LLP |
Chin Yan Xun | WongPartnership LLP |
Campos Conrad Melville | RHTLaw Asia LLP |
Chong Jia Hao | RHTLaw Asia LLP |
Michelle Lim Ann Nee | RHTLaw Asia LLP |
4. Facts
- Range Construction was appointed as Goldbell Engineering's contractor.
- Range Construction filed Adjudication Application No SOP/AA/008/2020.
- Range Construction submitted claims totaling $2,445,225.58.
- Range Construction was awarded an adjudicated amount of $205,647.43.
- Goldbell Engineering claimed liquidated damages from Range Construction.
- The adjudicator awarded $852,000 in liquidated damages to Goldbell Engineering.
- The adjudicator valued the nett variation claim at $38,455.54.
5. Formal Citations
- Range Construction Pte Ltd v Goldbell Engineering Pte Ltd, Originating Summons No 382 of 2020, [2020] SGHC 191
6. Timeline
Date | Event |
---|---|
Contract awarded to Range Construction | |
Contractual completion date | |
Email from Range Construction's managing director admitting project delays | |
Payment Claim No 28 issued by Range Construction | |
Adjudication determination issued | |
Hearing date | |
Judgment issued |
7. Legal Issues
- Jurisdiction of Adjudicator
- Outcome: The court held that the adjudicator did not exceed his jurisdiction.
- Category: Jurisdictional
- Sub-Issues:
- Exceeded jurisdiction by considering liquidated damages
- Exceeded jurisdiction by designating a completion date
- Breach of Fair Hearing Rule
- Outcome: The court held that there was no breach of the fair hearing rule.
- Category: Procedural
- Sub-Issues:
- Designating a completion date without instruction
- Awarding liquidated damages on arguments not submitted
- Relying on arguments outside assigned parameters
- Failure to Consider Relevant Matters
- Outcome: The court held that the adjudicator did not fail to consider relevant matters.
- Category: Procedural
- Sub-Issues:
- Failure to consider pleadings about Temporary Occupation Permit
- Failure to consider evidence other than the 17 November Email
- Failure to consider jurisdictional objections
8. Remedies Sought
- Setting aside adjudication determination
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Construction Litigation
- Adjudication
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Coordinated Construction Co Pty Ltd v J M Hargreaves (NSW) Pty Ltd | New South Wales Court of Appeal | Yes | [2005] NSWCA 228 | Australia | Cited regarding whether a payment claim can include sums that are damages for breach of contract. |
Glaziers Engineering Pte Ltd v WCS Engineering Construction Pte Ltd | Court of Appeal | Yes | [2018] 2 SLR 1311 | Singapore | Cited for the test of whether parties have been deprived of a fair opportunity to be heard. |
W Y Steel Construction Pte Ltd v Osko Pte Ltd | High Court | Yes | [2013] 3 SLR 380 | Singapore | Cited for the recognition that cash flow is the life blood of those in the building and construction industry. |
Soh Beng Tee & Co Pte Ltd v Fairmount Development Pte Ltd | High Court | Yes | [2007] 3 SLR(R) 86 | Singapore | Cited regarding the court's duty to avoid setting aside determinations on inconsequential technical breaches of natural justice. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Building and Construction Industry Security of Payment Act (Cap 30B) | Singapore |
Section 27(5) of the Building and Construction Industry Security of Payment Act (Cap 30B) | Singapore |
Order 95, Rule 3 of the Rules of Court (Cap 322, Rule 5) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Adjudication Determination
- Liquidated Damages
- Handing-Over Certificate
- Payment Claim
- Payment Response
- Variation Works
- Completion Date
- Temporary Occupation Permit
- SOP Act
15.2 Keywords
- Building and Construction Industry Security of Payment Act
- SOPA
- Adjudication
- Liquidated Damages
- Construction Law
- Singapore
16. Subjects
- Construction Dispute
- Adjudication
- Contract Law
17. Areas of Law
- Building and Construction Law
- Construction Adjudication
- Contract Law