Ramo Industries v DLE Solutions: Structural Steel Contract Dispute
In a suit before the High Court of Singapore, Ramo Industries Pte Ltd, the plaintiff, sued DLE Solutions Pte Ltd, the defendant, over a contract for the supply, fabrication, painting, and delivery of structural steel for an accommodation camp in Malaysia. Ramo claimed DLE breached the contract by failing to deliver the required quantities of steel, delivering unpainted steel, and improperly fabricating the steel, leading to delays and additional costs. DLE counterclaimed for retention monies and the value of bolts supplied. The court found in favor of Ramo on several claims, including the shortfall in steel, unpainted steel, improper fabrication, and demurrage charges, and the delay issue. The court allowed DLE's counterclaim for retention monies, to be set off against Ramo's claim. The court dismissed DLE's counterclaim for the value of bolts supplied.
1. Case Overview
1.1 Court
High Court of the Republic of Singapore1.2 Outcome
Judgment for Plaintiff in part; Counterclaim allowed in part.
1.3 Case Type
Civil
1.4 Judgment Type
Judgment
1.5 Jurisdiction
Singapore
1.6 Description
Singapore High Court judgment on a contract dispute between Ramo Industries and DLE Solutions regarding the supply of structural steel.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Ramo Industries Pte Ltd | Plaintiff | Corporation | Claim allowed in part | Partial | |
DLE Solutions Pte Ltd | Defendant | Corporation | Counterclaim allowed in part | Partial |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Chan Seng Onn | Judge | Yes |
4. Counsels
4. Facts
- Ramo and DLE entered into a contract for the supply of structural steel.
- DLE was to supply, fabricate, paint, and deliver structural steel to a site in Malaysia.
- Ramo claimed DLE failed to deliver the required quantities of steel.
- Ramo claimed DLE delivered unpainted steel.
- Ramo claimed DLE improperly fabricated the steel.
- Ramo claimed DLE's actions caused delays and additional costs.
- DLE counterclaimed for retention monies and the value of bolts supplied.
5. Formal Citations
- Ramo Industries Pte Ltd vDLE Solutions Pte Ltd, Suit No 1170 of 2017, [2020] SGHC 04
6. Timeline
Date | Event |
---|---|
Letter of Award issued by Ramo to DLE | |
Dennis sent Guna a Whatsapp message regarding costing | |
Dennis sent an email to Rohit inquiring about steel grade and pricing | |
Dennis sent Sri an email requesting project information | |
Oral Price Agreement reached between Sri and Dennis | |
Sri sent Dennis a draft of the Letter of Award | |
Elaine replied to Sri with an email attaching an unsigned draft with handwritten mark-ups | |
Dennis confirmed receiving structural drawings | |
Elaine sent an email to Sri regarding comments on the contract draft | |
DLE sent Ramo an email enquiring about seven issues for Ramo to clarify | |
Ramo replied on the seven issues | |
Elaine replied to Ramo seeking to negotiate on the payment terms by Letter of Credit | |
Elaine sent an email to Sri to forward the revised contract | |
Ramo clarified the issue of payment terms by letter of credit | |
Elaine sent Ramo an email regarding payment terms and LC requirements | |
Whatsapp correspondence between Dennis and Guna regarding LC | |
Elaine sent Mahe an email proposing CIF term | |
Dennis sent a Whatsapp message to Guna regarding LC requirements | |
Sri sent Elaine a revised draft Letter of Award | |
Sri sent an email to DLE enclosing a copy of the PO signed by Ramo | |
Dennis replied in an email to Sri regarding the PO | |
DLE accepted the PO | |
UOB issued the first letter of credit | |
Elaine sent an email to Sri regarding discrepancies in the contract | |
Guna sought Dennis’ confirmation on the shipment process | |
Parties agreed that the retention monies from the seventh shipment onwards would be 5% | |
UOB issued Letter of Credit Amendment No. 4 | |
Sri sent DLE an email requesting the signed contract | |
Elaine replied to Sri noting that DLE had already signed the PO | |
Remaining structural steel received by Ramo | |
Trial bifurcated into Liability Phase and Assessment of Damages Phase | |
Trial began | |
Judgment reserved |
7. Legal Issues
- Breach of Contract
- Outcome: The court found that DLE breached the contract by failing to meet its obligations.
- Category: Substantive
- Sub-Issues:
- Failure to deliver requisite quantities of structural steel
- Delivery of unpainted structural steel
- Improper fabrication of structural steel
- Contract Interpretation
- Outcome: The court held that the contract was constituted by the Letter of Award, the Oral Price Agreement, and the Purchase Order.
- Category: Substantive
- Sub-Issues:
- Determining the terms of the contract
- Binding nature of the Letter of Award
- Liability for Demurrage Charges
- Outcome: The court found DLE liable for the demurrage charges incurred as a result of its failure to deliver painted structural steel and delays in the customs clearance process.
- Category: Substantive
- Sub-Issues:
- Delays in customs clearance
- Failure to deliver painted structural steel
- Liquidated Damages
- Outcome: The court found DLE liable for liquidated damages for the delay in the delivery of the structural steel.
- Category: Substantive
- Sub-Issues:
- Delay in delivery of structural steel
8. Remedies Sought
- Monetary Damages
- Liquidated Damages
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Construction Law
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Ng Chee Chuan v Ng Ai Tee | High Court | Yes | [2009] 2 SLR(R) 918 | Singapore | Cited for the principle regarding the assessment of witness credibility. |
Simpson Marine (SEA) Pte Ltd v Jiacipto Jiaravanon | Court of Appeal | Yes | [2019] 1 SLR 696 | Singapore | Cited for the principle regarding the use of subsequent conduct in Singapore contract law. |
ARS v ART and anor | High Court | Yes | [2015] SGHC 78 | Singapore | Cited for the principle that conduct can be explained by a number of reasons. |
Beckkett Pte Ltd v Deutsche Bank AG and another and another appeal | Court of Appeal | Yes | [2009] 3 SLR(R) 452 | Singapore | Cited for the principle that a bifurcation is only a procedural order that is not binding on a trial judge. |
Millenia Pte Ltd (formerly known as Pontiac Marina Pte Ltd) v Dragages Singapore Pte Ltd (formerly known as Dragages et Travaux Publics (Singapore) Pte Ltd) and others (Arup Singapore Pte Ltd, third party) | High Court | Yes | [2019] 4 SLR 1075 | Singapore | Cited for the principle regarding the acceptance of evidence based on a sample. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Structural steel
- Letter of Award
- Purchase Order
- Letters of Credit
- Demurrage
- Fabrication
- Customs clearance
- Retention monies
- Delivery schedule
15.2 Keywords
- construction contract
- structural steel
- breach of contract
- liquidated damages
- demurrage
- Singapore High Court
17. Areas of Law
16. Subjects
- Construction Dispute
- Contract Law
- Building and Construction Law