Comfort Management v OGSP Engineering: Costs Allocation After Breach of Contract Dispute

In a suit between Comfort Management Pte Ltd (Plaintiff) and OGSP Engineering Pte Ltd (Defendant), the High Court of Singapore, General Division, presided over by Justice Vinodh Coomaraswamy, addressed the issue of costs following a judgment on the merits of a breach of contract claim and counterclaim related to air conditioning ducting system and mechanical ventilation works. The court ruled that Comfort Management is entitled to recover its costs from OGSP Engineering, but is deprived of 50% of those costs due to failing on several claims and defenses. The court also ruled that the second defendant is entitled to recover his costs from the plaintiff. The court ordered OGSP Engineering to pay GST at 7% on the net sum of $363,030.51 which it owes to Comfort Management.

1. Case Overview

1.1 Court

General Division of the High Court

1.2 Outcome

Judgment for Plaintiff

1.3 Case Type

Civil

1.4 Judgment Type

Judgment

1.5 Jurisdiction

Singapore

1.6 Description

Following a breach of contract dispute, the court addresses costs allocation, ruling Comfort Management is entitled to recover costs from OGSP Engineering, but is deprived of 50% due to failed claims.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
COMFORT MANAGEMENT PTE LTDPlaintiff, Defendant in CounterclaimCorporationJudgment for PlaintiffPartial
OGSP ENGINEERING PTE LTDDefendant, Plaintiff in CounterclaimCorporationJudgment Against DefendantLost
PINTU KUMAR SARKERDefendantIndividualClaim DismissedWon

3. Judges

Judge NameTitleDelivered Judgment
Vinodh CoomaraswamyJudge of the High CourtYes

4. Counsels

4. Facts

  1. Lead Management Engineering & Construction Pte Ltd subcontracted the Works to the plaintiff under the Lead Contract.
  2. The plaintiff subcontracted the Works to the first defendant under the Comfort Contract, a lump-sum contract at a price of $1.25m.
  3. The Comfort Contract was back-to-back with the Lead Contract.
  4. The second defendant was the plaintiff’s project manager for the Works.
  5. The first defendant commenced the Works in October 2013 and demobilised its team in October 2014 before completing the Works.
  6. The plaintiff sought to recover a total of just over $1.5m from the first defendant on four claims.
  7. The first defendant sought to recover a total of just over $780,000 from the plaintiff on two counterclaims.

5. Formal Citations

  1. Comfort Management Pte Ltd v OGSP Engineering Pte Ltd and another, Suit No 509 of 2017, [2022] SGHC 77
  2. Comfort Management Pte Ltd v OGSP Engineering Pte Ltd and another, , [2020] SGHC 165

6. Timeline

DateEvent
First defendant commenced the Works
First defendant demobilised its team and withdrew from the site
Hearing date
Judgment reserved
Hearing date
Judgment reserved
Judgment issued

7. Legal Issues

  1. Allocation of Costs
    • Outcome: The court ruled that Comfort Management is entitled to recover its costs from OGSP Engineering, but is deprived of 50% of those costs due to failing on several claims and defenses.
    • Category: Procedural
    • Sub-Issues:
      • Departure from general rule
      • Type I order
      • Type II order
    • Related Cases:
      • [2007] EWHC 2699 (Comm)
      • [2004] 2 Lloyd’s Rep 119
      • [2000] ECDR 266
      • [2003] BLR 331
      • 149 NLJ 1222
      • [2006] EWHC 2428 (Ch)
      • [1998] EMLR 161
      • [2005] EWCA Civ 358
      • [2003] EWCA Civ 402
      • [2008] EWHC 2280 (TCC)
      • [1992] 1 WLR 1207
      • [1994] 2 SLR(R) 501
      • [1891] AC 173
      • (1998) 193 CLR 72
      • [2011] EWCA Civ 790
      • [1976] Fam 93
      • [1984] 2 WLR 349
      • [2009] 4 SLR(R) 155
      • [2020] SGHC 140
      • [1999] 1 WLR 347
      • [2005] 3 SLR(R) 116
      • [2006] EWHC 2885 (Comm)
      • [2004] EWCA Civ 1703
      • [2002] 1 WLR 2409
      • [2001] EWCA Civ 2020
      • [1999] 1 WLR 1507
      • [2001] EWCA Civ 535
      • [2012] EWCA Civ 494
      • [2008] FCAFC 107
      • [1929] 1 AC 68
      • [2014] 1 SLR 245
  2. Breach of Contract
    • Outcome: The court found that the first defendant owed the plaintiff a net sum of $363,030.51, subject to GST.
    • Category: Substantive

8. Remedies Sought

  1. Monetary Damages
  2. Costs

9. Cause of Actions

  • Breach of Contract
  • Breach of Duty
  • Tort

10. Practice Areas

  • Commercial Litigation
  • Construction Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Comfort Management Pte Ltd v OGSP Engineering Pte Ltd and anotherHigh CourtYes[2020] SGHC 165SingaporeJudgment on the merits of the action from which the consequential issues of costs arise.
HLB Kidsons (A Firm) v Lloyds Underwriters subscribing to Lloyds Policy No 621/PKID00101 & OthersEnglish High CourtYes[2007] EWHC 2699 (Comm)England and WalesCited for the principles applicable to awarding costs, including the court's wide discretion and the general rule that costs should follow the event.
Kastor Navigation v Axa Global RisksCourt of AppealYes[2004] 2 Lloyd’s Rep 119England and WalesCited to support the general rule that costs should follow the event and that the 'successful party' must be determined by reference to the litigation as a whole.
Scholes Windows v Magnet (No 2)N/AYes[2000] ECDR 266N/ACited to support the principle that real weight should be given to the overall success of the winning party when awarding costs.
Barnes v Time TalkCourt of AppealYes[2003] BLR 331England and WalesCited for the importance of identifying the 'successful party' at the outset when awarding costs and that disputes are ultimately about money in commercial litigation.
BCCI v Ali (No 4)N/AYes149 NLJ 1222N/ACited for the principle that the question of who is the successful party is a matter for the exercise of common sense.
Fulham Leisure Holdings v Nicholson Graham & JonesEnglish High CourtYes[2006] EWHC 2428 (Ch)England and WalesCited for the principle that the matter must be looked at in a realistic and commercially sensible way.
Roache v News Group Newspapers Limited and othersN/AYes[1998] EMLR 161N/ACited for the principle that the judge must look closely at the facts and ask who, as a matter of substance and reality, has won.
Burchell v BullardCourt of AppealYes[2005] EWCA Civ 358England and WalesCited for the principle that in commercial litigation, the event is typically in favor of the party whom the court has found is entitled to receive money.
AL Barnes Limited v Time Talk (UK) LimitedCourt of AppealYes[2003] EWCA Civ 402England and WalesCited for the principle that the most important thing in deciding who is the successful party is to identify the party who is to pay money to the other.
Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd and anotherEnglish High CourtYes[2008] EWHC 2280 (TCC)England and WalesCited for the principle that in litigation comprising both claims and counterclaims, the event is typically in favor of the party whom the court has found is entitled to receive money.
Re Elgindata (No. 2)Court of AppealYes[1992] 1 WLR 1207England and WalesCited for the five principles to regulate the judicial discretion to depart from the general rule by making a Type I or a Type II order.
Tullio Planeta v Maoro Andrea GCourt of AppealYes[1994] 2 SLR(R) 501SingaporeEndorsed the Elgindata principles regarding the judicial discretion to depart from the general rule when awarding costs.
Sharp v WakefieldHouse of LordsYes[1891] AC 173United KingdomCited for the principle that judicial discretion must be exercised on fixed principles, adhering to reason and justice.
Oshlack v Richmond River CouncilN/AYes(1998) 193 CLR 72AustraliaCited for the principle that every party has a reasonable expectation that, if he succeeds, he will recover his costs from the unsuccessful party.
Fox v Foundation Piling LtdCourt of AppealYes[2011] EWCA Civ 790England and WalesWarned against the growing tendency to depart from the general rule too far and too often, leading to uncertainty and satellite litigation over costs.
Calderbank v CalderbankN/AYes[1976] Fam 93N/AMentioned in passing as an example of Calderbank offers at common law.
Cutts v Head and anotherN/AYes[1984] 2 WLR 349N/AMentioned in passing as an example of Calderbank offers at common law.
Ng Eng Ghee and others v Mamata Kapildev Dave and others (Horizon Partners Pte Ltd, intervener) and another appealCourt of AppealYes[2009] 4 SLR(R) 155SingaporeCited for the principle that a party who succeeds in litigation is accorded complete justice if and only if he recovers compensation for the costs of the litigation.
Element Six Technologies Ltd v IIa Technologies Pte LtdHigh CourtYes[2020] SGHC 140SingaporeCited for the principle that the indemnity principle incentivizes discipline in litigation by shifting the costs to the unsuccessful party.
R v Lord Chancellor, Ex parte Child Poverty Action Group and another matterN/AYes[1999] 1 WLR 347N/ACited for the principle that the indemnity principle focuses the minds of parties on the need to assess carefully the strength of their case.
Lim Lie Hoa v Ong Jane Rebecca and others and another appealCourt of AppealYes[2005] 3 SLR(R) 116SingaporeCited for the principle that the factors enumerated in Order 59 Rule 6A are not intended to be exhaustive or to detract from the width of the discretion conferred by Order 59 Rule 2(2).
Travelers Casualty and Surety Co of Canada v Sun Life Assurance Company of Canada (UK)English High CourtYes[2006] EWHC 2885 (Comm)England and WalesCited for the principle that the aim always is to make an order that reflects the overall justice of the case.
Smithkline Beecham plc and another v Apotex Europe Limited and othersCourt of AppealYes[2004] EWCA Civ 1703England and WalesCited for the difficulties associated with segregating the costs of an individual issue and the impossibility of achieving great precision in awarding costs.
English v Emery Reimbold & Strick LtdCourt of AppealYes[2002] 1 WLR 2409England and WalesCited for the principle that an order which allows or disallows costs by reference to certain issues should be made only if other forms of an order cannot be made which sufficiently reflect the justice of the case.
Summit Property Limited v Pitmans (a firm)Court of AppealYes[2001] EWCA Civ 2020England and WalesCited for the principle that a successful party could be subject to a Type II order even if he did not act unreasonably or improperly.
A.E.I. Rediffusion Music Limited v Phonographic Performance LimitedN/AYes[1999] 1 WLR 1507N/ACited for the principle that it is no longer necessary for a party to have acted unreasonably or improperly before he can be required to pay the costs of the other party of a particular issue on which he has failed.
Johnsey Estates (1990) Ltd v The Secretary of State for the EnvironmentCourt of AppealYes[2001] EWCA Civ 535England and WalesExpressed enthusiasm for the discretion to make a Type II order.
Specsavers International Healthcare Ltd and others v Asda Stores LtdCourt of AppealYes[2012] EWCA Civ 494England and WalesCited for the principle that the nature of typical intellectual property litigation lends itself more readily to Type II orders.
Bowen Investments Pty Ltd v Tabcorp Holdings Ltd (No 2)N/AYes[2008] FCAFC 107AustraliaCited for the principle that the ultimate objective in making a costs order is to produce a result which is fair to both the successful and the unsuccessful parties.
Medway Oil and Storage Co Ltd v Continental Contractors Ltd & OrsN/AYes[1929] 1 AC 68N/ACited for the principle that the successful party should ordinarily recover all of his common costs of the action.
Then Khek Koon and another v Arjun Permanand Samtani and another and other suitsN/AYes[2014] 1 SLR 245SingaporeCited for the principle that the indemnity is not an actual indemnity but a deemed indemnity assessed in accordance the Costs Guidelines.

13. Applicable Rules

Rule Name
Rules of Court

14. Applicable Statutes

Statute NameJurisdiction
Supreme Court of Judicature Act 1969Singapore
Civil Law Act 1909Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Works
  • Lead Contract
  • Comfort Contract
  • Variation Orders
  • Liquidated Damages
  • Overpayment
  • Back Charges
  • GST
  • Costs
  • Disbursements
  • Professional Fees

15.2 Keywords

  • costs
  • breach of contract
  • construction
  • singapore
  • litigation
  • costs allocation
  • OGSP Engineering
  • Comfort Management

17. Areas of Law

16. Subjects

  • Civil Procedure
  • Contract Law
  • Construction Law
  • Costs