Thio Keng Thay v Sandy Island Pte Ltd: Construction Defects, Breach of Contract, Defamation

In Thio Keng Thay v Sandy Island Pte Ltd, the Singapore High Court addressed a claim by Thio Keng Thay against Sandy Island Pte Ltd, the developer, for construction defects in a luxury bungalow. The court found Sandy Island Pte Ltd liable for breach of contract due to the defects. However, it also found Thio Keng Thay in breach of the defects liability clause for impeding rectification works. The court awarded nominal damages of $1,000 to Sandy Island Pte Ltd on its defamation counterclaim. The quantum of damages for the defects will be determined in a second trial tranche.

1. Case Overview

1.1 Court

High Court of the Republic of Singapore

1.2 Outcome

Judgment for Plaintiff on breach of contract; Nominal damages awarded to Defendant on defamation counterclaim.

1.3 Case Type

Civil

1.4 Judgment Type

Judgment

1.5 Jurisdiction

Singapore

1.6 Description

Singapore High Court case involving construction defects in a luxury bungalow, breach of contract, and a defamation counterclaim. Nominal damages awarded for defamation.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Thio Keng ThayPlaintiff, DefendantIndividualBreach of contract claim allowed in part, Defamation counterclaim lostPartial, LostCavinder Bull SC, Daniel Cai, Kelly Lua
Sandy Island Pte LtdDefendant, PlaintiffCorporationBreach of contract claim lost in part, Defamation counterclaim allowedPartial, WonLok Vi Ming SC, Joseph Lee, Tang Jin Sheng, Qabir Singh Sandhu, Chiam Yunxin

3. Judges

Judge NameTitleDelivered Judgment
Lee Seiu KinJudgeYes

4. Counsels

Counsel NameOrganization
Cavinder Bull SCDrew & Napier LLC
Daniel CaiDrew & Napier LLC
Kelly LuaDrew & Napier LLC
Lok Vi Ming SCLVM Law Chambers LLC
Joseph LeeLVM Law Chambers LLC
Tang Jin ShengLVM Law Chambers LLC
Qabir Singh SandhuLVM Law Chambers LLC
Chiam YunxinLVM Law Chambers LLC

4. Facts

  1. The plaintiff purchased a bungalow from the defendant, a property developer, for $14.32 million.
  2. The property suffered from numerous defects, including water seepage, rain ingress, and an irregularly designed staircase.
  3. The plaintiff sent multiple defects lists to the defendant between April 2012 and February 2013.
  4. The defendant provided method statements for rectification works, which the plaintiff rejected.
  5. The plaintiff engaged JTA Construction to perform rectification works after a second tender exercise.
  6. The lifts in the property did not comply with the applicable regulations at the time of construction.
  7. The plaintiff made statements to The Straits Times alleging serious flaws in the property and questioning the defendant's ability to rectify them.

5. Formal Citations

  1. Thio Keng Thay v Sandy Island Pte Ltd, Suit No 1073 of 2016, [2019] SGHC 175

6. Timeline

DateEvent
Sale and purchase agreement signed
Temporary occupation permit issued by Building and Construction Authority
Notice of vacant possession received by plaintiff
Plaintiff took possession of the property
Plaintiff sent defendant a list of defects
Certificate of Statutory Completion obtained
Parties carried out a joint inspection of the property
Defendant provided a method statement for the rectification works
Defendant sent a schedule for rectification works
Defendant provided another method statement
Defendant offered the plaintiff $130,000 in settlement
Plaintiff sent a supplementary defects list
Plaintiff informed the defendant he was past having the defendant perform the rectification works
Plaintiff provided another supplementary defects list
Tender exercise for the rectification works was carried out by the plaintiff
Plaintiff rejected the defendant’s offer of $130,000
Plaintiff repeated he was past having the defendant perform the rectification works
Plaintiff sent the defendant the tender report
Defendant wrote that it would not reimburse the plaintiff should he engage Skybolt
Plaintiff's lawyers informed the defendant of the results of the second tender exercise
Defendant's lawyers replied stating agreement in principle to architect supervision
Building and Construction Authority wrote to the plaintiff regarding the lifts
Plaintiff engaged JTA Construction
Rectification work for the general defects was carried out
Defendant informed the plaintiff that Gylet was ready to undertake the modification works
Rectification work for the general defects was completed
Plaintiff commenced suit against the defendant
Trial began
Parties filed written submissions
Judgment reserved

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found that the defendant breached the sale and purchase agreement by delivering a property with defects.
    • Category: Substantive
    • Sub-Issues:
      • Defective workmanship
      • Failure to comply with building regulations
  2. Defects Liability Clause
    • Outcome: The court found that the plaintiff breached the defects liability clause by denying access to the defendant for rectification works, but this did not supplant the common law right to damages.
    • Category: Substantive
    • Sub-Issues:
      • Denial of access for rectification
      • Reasonableness of conditions imposed
  3. Defamation
    • Outcome: The court found that the plaintiff defamed the defendant but awarded only nominal damages due to the defendant's limited business activity.
    • Category: Substantive
    • Sub-Issues:
      • Justification
      • Fair comment
      • Malice

8. Remedies Sought

  1. Monetary Damages
  2. Costs of rectification
  3. Loss of use of property

9. Cause of Actions

  • Breach of Contract
  • Defamation

10. Practice Areas

  • Construction Defect Litigation
  • Commercial Litigation

11. Industries

  • Construction
  • Real Estate

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Yap Boon Keng Sonny v Pacific Prince International Pte Ltd and anotherHigh CourtYes[2008] 1 SLR(R) 285SingaporeCited regarding the obligation to allow rectification of defects.
Management Corporation Strata Title Plan No 1993 v Liang Huat AluminiumCourt of AppealYes[2001] 2 SLR(R) 91SingaporeCited for the principle that a defects liability clause does not supplant the common law right to claim damages.
Pearce and High Ltd v BaxterEnglish Court of AppealYes[1999] CLC 749England and WalesCited for the principle that a defects liability clause does not extinguish a plaintiff’s right to recover damages under common law unless there is express language to the contrary.
William Tomkinson & Sons Ltd v Parochial Church Council of St MichaelN/AYes[1990] CLJ 319N/ACited with approval in Pearce and High Ltd v Baxter regarding the interpretation of defects liability clauses.
Gilbert-Ash (Northern) Limited v Modern Engineering (Bristol) LimitedN/AYes[1974] AC 689N/ACited for the principle that a common law right cannot be abrogated unless by express wording.
Qingdao Bohai Construction Group Co, Ltd and others v Goh Teck Beng and anotherN/AYes[2016] 4 SLR 977N/ACited regarding damages recoverable in defamation for a commercial corporate entity.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Housing Developers Rules (Cap 130, R1, 2008 Rev Ed)Singapore
Workplace Safety and Health (General Provisions) Regulations (Cap 354A, Rg 1, 2007 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Defects liability period
  • Method statement
  • Rectification works
  • Temporary occupation permit
  • Certificate of Statutory Completion
  • Home passenger lift
  • Car lift
  • Qualified Professional
  • Load test certificate
  • Enhancement works
  • General defects
  • Lift defects

15.2 Keywords

  • construction defects
  • breach of contract
  • defamation
  • luxury bungalow
  • Singapore High Court
  • defects liability clause
  • rectification works
  • building regulations

16. Subjects

  • Construction Dispute
  • Contract Law
  • Defamation
  • Building and Construction Law

17. Areas of Law

  • Building and Construction Law
  • Contract Law
  • Defamation