Crescendas Bionics v Jurong Primewide: Damages for Delay in Biopolis 3 Construction
In Crescendas Bionics Pte Ltd v Jurong Primewide Pte Ltd, the High Court of Singapore addressed the assessment of damages for delays in the construction of Biopolis 3. Crescendas Bionics, the plaintiff, sued Jurong Primewide, the defendant, for delays in completing the project. The court, presided over by Justice Tan Siong Thye, found both parties responsible for the delays, with Jurong Primewide liable for 161 days. The court considered claims for loss of net rental revenue, holding costs, and site staff expenses, ultimately awarding Crescendas Bionics $2,693,573.91 in damages. The court rejected the multi-year model for calculating damages, favoring the single-year model and addressing issues of causation, remoteness, and apportionment.
1. Case Overview
1.1 Court
General Division of the High Court1.2 Outcome
Judgment for Plaintiff; damages awarded in the amount of $2,693,573.91
1.3 Case Type
Civil
1.4 Judgment Type
Judgment
1.5 Jurisdiction
Singapore
1.6 Description
Crescendas Bionics sued Jurong Primewide for delays in the Biopolis 3 construction. The court assessed damages, addressing causation, remoteness, and apportionment.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Crescendas Bionics Pte Ltd | Plaintiff, Defendant in counterclaim | Corporation | Judgment for Plaintiff | Won | |
Jurong Primewide Pte Ltd | Defendant, Plaintiff in counterclaim | Corporation | Partial | Partial |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Tan Siong Thye | Judge of the High Court | Yes |
4. Counsels
4. Facts
- Crescendas Bionics engaged Jurong Primewide to build Biopolis 3 under a Letter of Intent.
- The contractual completion date was 22 January 2010, but Biopolis 3 was completed on 12 January 2011.
- Crescendas Bionics was responsible for 173 days of delay due to acts of prevention.
- Jurong Primewide was responsible for 161 days of delay.
- The plaintiff sought general damages for delayed completion, including loss of net rental revenue, holding costs, and site staff expenses.
- The defendant argued that the plaintiff's losses were not caused by the defendant's delay and were too remote.
- The court appointed a court expert to assist in assessing the quantum of the plaintiff’s loss of net rental revenue.
5. Formal Citations
- Crescendas Bionics Pte Ltd v Jurong Primewide Pte Ltd, Suit No 477 of 2015, [2021] SGHC 189
- Crescendas Bionics Pte Ltd v Jurong Primewide Pte Ltd, , [2019] SGHC 4
- Jurong Primewide Pte Ltd v Crescendas Bionics Pte Ltd and another appeal, , [2019] SGCA 63
6. Timeline
Date | Event |
---|---|
Letter of Intent signed | |
Parties signed Letter of Intent | |
Construction of Biopolis 3 commenced | |
Resident Engineer terminated | |
Piling works delayed | |
Chang Hua Pte Ltd introduced as tenderer | |
Tender report submitted for approval | |
Revised tender bids re-submitted | |
Tien Rui Pte Ltd and Shanghai Construction Co Pte Ltd’s joint tender submissions introduced | |
Final tender recommendation issued | |
RC works trade contract awarded | |
Contractual completion date under LOI | |
Registered Inspector conducted inspection | |
SO informed defendant of follow-up works | |
BCA conducted pre-TOP inspection | |
SO directed to apply for TOP | |
Biopolis 3 certified as completed | |
Trial bifurcated | |
Trial commenced | |
Trial concluded | |
Judgment reserved |
7. Legal Issues
- Damages
- Outcome: The court assessed damages for the delay, considering various heads of loss and applying principles of causation, remoteness, and mitigation.
- Category: Substantive
- Sub-Issues:
- Apportionment
- Assessment
- Measure of damages
- Mitigation
- Quantum
- Remoteness
- Causation
- Outcome: The court found that the defendant's delay was an effective cause of the plaintiff's losses, rejecting the defendant's arguments on causation.
- Category: Substantive
- Remoteness of damage
- Outcome: The court held that the pre-completion loss of net rental revenue was not too remote, but the post-completion loss was too remote to be recoverable.
- Category: Substantive
- Apportionment
- Outcome: The court apportioned liability for the losses between the plaintiff and the defendant based on the duration of delay attributable to each party.
- Category: Substantive
- Liquidated damages
- Outcome: The court held that the liquidated damages clause in the LOI did not act as a cap on the general damages recoverable by the plaintiff.
- Category: Substantive
- Functions of judge
- Outcome: The court outlined the functions of the judge in the proceedings.
- Category: Procedural
- Expert witnesses
- Outcome: The court outlined the role of expert witnesses in the proceedings.
- Category: Procedural
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Commercial Litigation
- Construction Law
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Crescendas Bionics Pte Ltd v Jurong Primewide Pte Ltd | High Court | Yes | [2019] SGHC 4 | Singapore | Affirmed on appeal, establishing liabilities of parties for delays in construction. |
Denka Advantech Pte Ltd and another v Seraya Energy Pte Ltd and another and other appeals | Court of Appeal | No | [2020] SGCA 119 | Singapore | Cited for the principles underpinning general and liquidated damages. |
J G Collins Insurance Agencies Ltd v Elsley Estate | Supreme Court of Canada | No | [1978] 2 SCR 916 | Canada | Cited by the defendant for the proposition that the amount of damages recoverable under a liquidated damages clause should act as a cap on the defendant’s liability to pay general damages. |
Guay Seng Tiong Nickson v Public Prosecutor | High Court | No | [2016] 3 SLR 1079 | Singapore | Cited for the principle that the court approaches the question of causation on a common-sense basis. |
Sunny Metal & Engineering Pte Ltd v Ng Khim Ming Eric | Court of Appeal | No | [2007] 3 SLR(R) 782 | Singapore | Cited for the usual test of causation to be applied in breach of contract cases is the but-for test. |
Smile Inc Dental Surgeons Pte Ltd v OP3 International Pte Ltd | High Court | Yes | [2020] 3 SLR 1234 | Singapore | Cited for the principle that when the defendant’s breach of contract is one of two concurrent causes of the plaintiff’s losses, the defendant can be held liable so long as his breach was an effective cause of the plaintiff’s losses. |
Financial Conduct Authority v Arch Insurance (UK) Ltd and others (Hiscox Action Group Intervening) | UK Supreme Court | No | [2021] 2 WLR 123 | United Kingdom | Cited by the plaintiff for the approach to causation where there are concurrent causes of loss. |
Out of the Box Pte Ltd v Wanin Industries Pte Ltd | Court of Appeal | Yes | [2013] 2 SLR 363 | Singapore | Cited for the principles of remoteness of damage in breach of contract cases, applying the rule in Hadley v Baxendale. |
Hadley v Baxendale | N/A | Yes | (1854) 9 Exch 341 | N/A | Cited for the rule on remoteness of damage in contract law. |
Victoria Laundry (Windsor) Ld v Newman Industries Ld; Coulson & Co Ld (Third Parties) | English Court of Appeal | Yes | [1949] 2 KB 528 | England | Cited for the restatement of the rule in Hadley v Baxendale and the distinction between direct and indirect losses. |
Singapore Telecommunications Ltd v Starhub Cable Vision Ltd | Court of Appeal | No | [2006] 2 SLR(R) 195 | Singapore | Cited for the principle that whether a particular head of loss is direct or indirect may depend on the circumstances. |
PH Hydraulics & Engineering Pte Ltd v Airtrust (Hong Kong) Ltd and another appeal | Court of Appeal | No | [2017] 2 SLR 129 | Singapore | Cited by the defendant for the argument that the plaintiff’s entire claim for loss of net rental revenue is no different from a claim for loss of profits, which is a form of indirect loss. |
Multiplex Constructions Pty Ltd v Abgarus Pty Ltd | New South Wales Supreme Court | No | (1992) 33 NSWLR 504 | Australia | Cited by the defendant for the argument that the plaintiff’s entire claim for loss of net rental revenue is no different from a claim for loss of profits, which is a form of indirect loss. |
Ajit Chandrasekar Prabhu and another v Yap Beng Kooi and another | High Court | No | [2015] SGHC 280 | Singapore | Cited by the defendant for the argument that the plaintiff’s entire claim for loss of net rental revenue is no different from a claim for loss of profits, which is a form of indirect loss. |
Robertson Quay Investment Pte Ltd v Steen Consultants Pte Ltd and another | Court of Appeal | No | [2008] 2 SLR(R) 623 | Singapore | Cited for the principle that loss of profits or rental would not necessarily be recoverable under the first limb of the rule in Hadley v Baxendale. |
Chua Tian Chu and another v Chin Bay Ching and another | High Court | No | [2011] SGHC 126 | Singapore | Cited for the principle that where liquidated damages are unavailable, general damages may be recoverable at common law for any delay occasioned after the reasonable date for completion. |
Alvin Nicholas Nathan v Raffles Assets (Singapore) Pte Ltd | Court of Appeal | Yes | [2016] 2 SLR 1056 | Singapore | Cited for the principle that claims for expectation losses and reliance losses are generally alternative claims between which a plaintiff must elect. |
Tembusu Growth Fund Ltd v ACTAtek, Inc and others | Court of Appeal | Yes | [2018] 4 SLR 1213 | Singapore | Cited for the principle that a plaintiff must take all reasonable steps to mitigate the loss it suffered as a result of a defendant’s breach. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Building Control Act (Cap 29) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Biopolis 3
- Letter of Intent
- Acts of prevention
- General damages
- Liquidated damages
- Net rental revenue
- Holding costs
- Site staff expenses
- Stabilised occupancy
- Multi-year model
- Single-year model
- Remoteness of damage
- Causation
- Apportionment
15.2 Keywords
- Construction Delay
- Damages
- Contract Law
- Singapore High Court
- Biopolis 3
17. Areas of Law
16. Subjects
- Construction Dispute
- Contract Law
- Damages Assessment