ICOP Construction v. Tiong Seng: Microtunnelling Dispute over Contract Termination and Delay Claims

ICOP Construction (SG) Pte Ltd sued Tiong Seng Civil Engineering Pte Ltd in the General Division of the High Court of Singapore, Suit No 1086 of 2019, before Lee Seiu Kin J, judgment on 12 October 2022, for payment of work carried out, costs incurred due to contractual variations, damages for failure to meet project specifications, and monies paid under performance and advance payment bonds. Tiong Seng Civil Engineering disputed liability and counterclaimed for damages due to delays allegedly caused by ICOP Construction. The court found partially in favor of both parties and ordered a Quantum Hearing to determine the final amounts owed.

1. Case Overview

1.1 Court

General Division of the High Court of the Republic of Singapore

1.2 Outcome

Judgment partially for Plaintiff, ICOP Construction, and partially for Defendant, Tiong Seng Civil Engineering; Quantum Hearing ordered.

1.3 Case Type

Civil

1.4 Judgment Type

Judgment

1.5 Jurisdiction

Singapore

1.6 Description

ICOP Construction sues Tiong Seng for payment and damages related to a pipe construction subcontract. Tiong Seng counterclaims for delays and wrongful termination.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
ICOP Construction (SG) Pte LtdPlaintiff, Defendant in CounterclaimCorporationPartial JudgmentPartialLee Wei Han Shaun, Ng Khim Loong Mark, Low Zhe Ning, Jonathan Choo
Tiong Seng Civil Engineering Pte LtdDefendant, Plaintiff in CounterclaimCorporationPartial JudgmentPartialHo Chien Mien, Reuben Gavin Peter, Hannah Chua, Yew Kai Ning Sophia

3. Judges

Judge NameTitleDelivered Judgment
Lee Seiu KinJudgeYes

4. Counsels

Counsel NameOrganization
Lee Wei Han ShaunBird & Bird ATMD LLP
Ng Khim Loong MarkBird & Bird ATMD LLP
Low Zhe NingBird & Bird ATMD LLP
Jonathan ChooBird & Bird ATMD LLP
Ho Chien MienAllen & Gledhill LLP
Reuben Gavin PeterAllen & Gledhill LLP
Hannah ChuaAllen & Gledhill LLP
Yew Kai Ning SophiaAllen & Gledhill LLP

4. Facts

  1. ICOP subcontracted with TSCE to perform pipe construction works.
  2. Disputes arose during the performance of the works, which were only part-completed.
  3. ICOP terminated the subcontract, claiming justification.
  4. ICOP sought payment for work carried out, costs for variations, damages for delays, and monies paid under bonds.
  5. TSCE disputed liability and counterclaimed for damages due to delays allegedly caused by ICOP.
  6. The project involved microtunnelling to install DN1200mm and DN1600mm pipelines.
  7. ICOP furnished TSCE with a performance bond for $570,000.

5. Formal Citations

  1. ICOP Construction (SG) Pte LtdvTiong Seng Civil Engineering Pte Ltd, Suit No 1086 of 2019, [2022] SGHC 257

6. Timeline

DateEvent
TSC engaged by the Public Utilities Board to construct a potable water pipeline
ICOP issued final quotation to TSCE
TSCE entered into a subcontract with ICOP for the performance of microtunnelling works
Subcontract executed between TSCE and ICOP
TSCE sent emails to ICOP with pipe jacking drawings showing 3.0m-long pipe sections
DN1200mm Pipeline works completed
TSCE sent emails to ICOP with shop drawings showing 3.0m-long pipe sections
ICOP informed TSCE that the Project was delayed by around six months
TSCE issued a notice to ICOP to proceed with mobilization at shaft P5-2 from 2018-01-15 onwards
ICOP prepared and issued a revised work programme to TSCE
ICOP to proceed with mobilization at shaft P5-2
Expected handover of Shaft P5-2
TSCE handed over the slurry treatment plant area to ICOP
TSCE handed over Shaft P5-2 to ICOP
TSCE aimed to obtain approvals from SPPG and the PUB
Primary generator and MTBM arrived on site
ICOP sought payment for the hydraulic joints it used in connection with the DN1200mm Pipeline
SPPG provided its approval
ICOP was ready to commence pipe jacking subject to the requisite approvals being obtained from SPPG and the PUB
PUB provided its approval
ICOP provided additional works and services at TSCE’s request
ICOP sent a revised version of the 8 January 2018 WP
ICOP sent letter to TSCE enclosing the 17 August 2018 WP; TSCE responded that it had “generally no objection”
TSCE sent a letter to ICOP highlighting the noise and asking that it propose mitigation measures
NEA issued a warning to TSCE cautioning them that if the applicable noise limits continued to be exceeded, the NEA “would not hesitate to issue a notice to restrict the working hours of the construction site”
TSCE forwarded letter along with a noise mitigation plan
TSCE met with the NEA which prescribed some noise mitigation measures and prohibited pipe jacking works from 10pm to 7am nightly
ICOP carried out Drive 2
ICOP carried out Drive 2
Parties agreed that the third drive would commence
Parties agreed that the third drive would commence
ICOP terminated the Subcontract
ICOP stated that the applicable baseline programme was one submitted by ICOP on 25 February 2017
TSCE called on the full sum of the Performance Bond
Agreed Bundle of Documents
Consolidated Bundle of Affidavits of Evidence-in-Chief
Notes of Evidence
Defence and Counterclaim
Joint Presentation (Quantum)
Notes of Evidence
Defendant’s Closing Submissions
Plaintiff’s Closing Submissions
Defendant’s Reply Submissions
Plaintiff’s Reply Submissions
Judgment reserved

7. Legal Issues

  1. Contractual Variation
    • Outcome: The court found that there were contractual variations for both the DN1200mm and DN1600mm pipelines, entitling ICOP to additional costs.
    • Category: Substantive
  2. Breach of Contract
    • Outcome: The court found that ICOP wrongfully terminated the subcontract, constituting a breach of contract.
    • Category: Substantive
  3. Delay Claims
    • Outcome: The court partially allowed both ICOP's and TSCE's delay claims, attributing specific delays to each party.
    • Category: Substantive
  4. Wrongful Call on Performance Bond
    • Outcome: The court reserved its decision on whether TSCE's call on the performance bond was wrongful until after the Quantum Hearing.
    • Category: Substantive

8. Remedies Sought

  1. Monetary Damages
  2. Recovery of Monies Paid Under Bonds

9. Cause of Actions

  • Breach of Contract
  • Claims for Payment
  • Claims for Damages
  • Quantum Meruit

10. Practice Areas

  • Construction Law
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
No cited cases

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
No applicable statutes

15. Key Terms and Keywords

15.1 Key Terms

  • Microtunnelling
  • Hydraulic Joints
  • Chipboard
  • Headwall
  • MTBM
  • Performance Bond
  • Slurry Disposal
  • Worksite Readiness
  • Authority Approvals
  • Noise Restrictions
  • Delay Claims
  • Termination

15.2 Keywords

  • construction
  • microtunnelling
  • contract
  • breach
  • delay
  • performance bond
  • Singapore
  • ICOP Construction
  • Tiong Seng

16. Subjects

  • Building and Construction Law
  • Contract Law
  • Civil Procedure
  • Arbitration

17. Areas of Law

  • Building and Construction Law
  • Building and construction contracts
  • Contractors’ duties
  • Damages
  • Employers’ duties
  • Quantum meruit
  • Scope of works
  • Variations
  • Termination
  • Credit and Security
  • Performance bond