Thio Keng Thay v Sandy Island Pte Ltd: Damages for Breach of Sale and Purchase Agreement
In a civil suit before the General Division of the High Court of Singapore, Thio Keng Thay sought damages from Sandy Island Pte Ltd for breach of a sale and purchase agreement concerning a property purchase. The court, presided over by Lee Seiu Kin J, found in favor of Thio Keng Thay, awarding damages of $1,308,645.48. The judgment addressed issues of admitted and non-admitted defects, mitigation of damages, betterment, deterioration, neglect, architectural intent, and warranty claims.
1. Case Overview
1.1 Court
General Division of the High Court1.2 Outcome
Judgment for the Plaintiff in the sum of $1,308,645.48.
1.3 Case Type
Civil
1.4 Judgment Type
Judgment
1.5 Jurisdiction
Singapore
1.6 Description
Judgment on damages owed to Thio Keng Thay by Sandy Island Pte Ltd for breach of a sale and purchase agreement regarding a property purchase.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Thio Keng Thay | Plaintiff | Individual | Judgment for Plaintiff | Won | |
Sandy Island Pte Ltd | Defendant | Corporation | Judgment against Defendant | Lost |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Lee Seiu Kin | Judge | Yes |
4. Counsels
4. Facts
- Plaintiff purchased a property from the Defendant for $14.32 million.
- Plaintiff discovered numerous defects after taking possession of the property.
- Plaintiff engaged a building surveyor to inspect the property and prepare a list of defects.
- Defendant offered to repair many of the defects, but Plaintiff did not permit access.
- Plaintiff called a tender for rectification works, awarding the contract to JTA Construction Pte Ltd.
- Defendant denied liability for some defects, claiming they were not defects under the SPA.
- The lifts in the property were defective, and the Plaintiff did not permit the supplier to rectify them.
5. Formal Citations
- Thio Keng Thay v Sandy Island Pte Ltd, Suit No 1073 of 2016, [2022] SGHC 69
6. Timeline
Date | Event |
---|---|
Plaintiff took possession of the Property | |
Plaintiff called a tender based on specifications prepared by his building surveyor | |
JTA Contract work commenced | |
JTA Contract work completed | |
Suit No 1073 of 2016 filed | |
First tranche of the trial was heard over eight days in 2018 | |
Trial adjourned while hearing on quantum was still ongoing | |
Decision on the issue of liability given in Thio Keng Thay v Sandy Island Pte Ltd [2019] SGHC 175 | |
Court of Appeal dismissed the appeal in Sandy Island Pte Ltd v Thio Keng Thay [2020] SGCA 86 | |
Trial scheduled to resume with the hearing of the remaining evidence pertaining to the quantum of damages | |
Written submissions filed | |
Counsel appeared for oral reply submissions after which judgment was reserved | |
Counsel submitted further written submissions on a specific issue | |
Judgment Reserved |
7. Legal Issues
- Breach of Contract
- Outcome: The court found the Defendant liable for breach of the sale and purchase agreement.
- Category: Substantive
- Sub-Issues:
- Failure to rectify defects
- Breach of defects liability clause
- Related Cases:
- [2019] SGHC 175
- [2020] SGCA 86
- Mitigation of Damages
- Outcome: The court found that the Plaintiff's refusal to allow the Defendant to rectify the defects was justified under the unique circumstances of the case, particularly regarding the lifts.
- Category: Substantive
- Sub-Issues:
- Failure to allow rectification
- Reasonableness of refusal
- Related Cases:
- Pearce and High Ltd v Baxter (1999) 66 Con LR 110
- Assessment of Damages
- Outcome: The court assessed the damages based on the JTA Contract, making deductions for betterment, deterioration, and architectural intent where applicable.
- Category: Substantive
- Sub-Issues:
- Betterment
- Deterioration
- Neglect
- Architectural intent
- Warranty
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Construction Law
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Thio Keng Thay v Sandy Island Pte Ltd | High Court | Yes | [2019] SGHC 175 | Singapore | Cited as the First Judgment in this suit, where the court made its decision on the issue of liability. |
Sandy Island Pte Ltd v Thio Keng Thay | Court of Appeal | Yes | [2020] SGCA 86 | Singapore | Cited as the CA Judgment, where the Court of Appeal dismissed the Defendant's appeal against the First Judgment. |
Pearce and High Ltd v Baxter | English Court of Appeal | Yes | Pearce and High Ltd v Baxter (1999) 66 Con LR 110 | England | Cited for the principle that where an owner breaches a defects liability clause, they cannot recover more than what it would have cost the contractor to rectify the defects. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Evidence Act (Cap 97, 1997 Rev Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Sale and Purchase Agreement
- Defects Liability
- Mitigation of Damages
- Betterment
- Deterioration
- Architectural Intent
- Warranty
- Rectification Works
- JTA Contract
- Admitted Defects
- Non-admitted Defects
15.2 Keywords
- breach of contract
- construction defects
- damages
- Singapore High Court
- property dispute
17. Areas of Law
Area Name | Relevance Score |
---|---|
Assessment of Damages | 90 |
Damages | 80 |
Construction Law | 75 |
Breach of Contract | 60 |
Contract Law | 50 |
16. Subjects
- Construction Dispute
- Contract Law
- Damages Assessment